New problem at Fukushima site; sandbags found to be radioactive
Sandbags sunk in the basement of a high-temperature incinerator building at the Fukushima No. 1 nuclear power plant shortly after the 2011 nuclear crisis flared
March 31, 2020
Sandbags placed as an emergency measure to lower radiation levels of contaminated water in the aftermath of the 2011 nuclear disaster now turn out to be so highly radioactive they pose an obstacle to the decommissioning of the stricken Fukushima No. 1 nuclear power plant.
A recent survey showed that the materials are in such a hazardous state that plant operator Tokyo Electric Power Co. is having to postpone its program to discharge the contaminated water.
“The sandbags should be removed, but that will not be so simple,” said an official of the Nuclear Regulation Authority.
TEPCO is struggling to find ways to safely remove 26 tons of sandbags in the basements of two buildings near the No. 1 to No. 3 reactors, where a triple meltdown occurred. They were packed with a mineral called zeolite to absorb radioactive cesium.
They are emitting radiation levels of up to 3 to 4 sieverts per hour, which would kill half of the people exposed to the high reading for an entire hour.
Soon after the nuclear crisis began to unfold, TEPCO used the two buildings as substitutes for tanks to temporarily store a huge volume of heavily contaminated water produced on the plant site.
In doing so, the zeolite-packed sandbags were installed on the floors of the buildings’ basements to absorb radioactive substances in the water.
Interest in the sunken sandbags waned as the years passed, but the issue surfaced again in December 2018 when TEPCO measured radiation levels in the two buildings’ basements in preparation for removing radioactive water there.
Significantly high radiation levels were detected just above the floors.
A zeolite sample collected from the sandbags recorded a cesium concentration of about 130 million becquerels per gram.
TEPCO has been forced to delay the water removal procedure at the two buildings to fiscal 2023 or later. It initially planned to finish the process by 2020. If it doesn’t have countermeasures in place when the water is released, the highly radioactive sandbags will be exposed to air.
TEPCO is now weighing ways to safely dispose of the contaminated materials. One idea is to suck up the zeolite from floors above ground and store it in other receptacles, and the other is to pack the material in different containers in water for temporary storage.
But officials acknowledge that those measures will not eliminate all safety risks.
TEPCO puts cost to remove melted nuclear fuel at over 1 trillion yen
A video image shows what appears to be melted nuclear fuel within the No. 3 reactor at the Fukushima No. 1 nuclear power plant.
March 31, 2020
Tokyo Electric Power Co. estimates that 1.37 trillion yen ($12.6 billion) will be needed over 12 years to remove melted nuclear fuel from reactors at the crippled Fukushima No. 1 nuclear power plant.
TEPCO’s announcement on March 30 covers only two of the three reactors that suffered meltdowns triggered by the 2011 Great East Japan Earthquake and tsunami.
No estimate was attempted for the cost to prepare for the removal of melted nuclear fuel from the No. 1 reactor. The situation at that reactor is the most difficult among the three reactors, and TEPCO officials are still struggling to come up with a plan for removing the debris from within.
The estimate covers the period between fiscal 2020 and fiscal 2031. Of that amount, 350 billion yen will be applied as a special loss to the company’s balance statement for the fiscal year ending March 31, 2020.
The utility had already released its plan for decommissioning the three reactors, which foresaw a start to removing melted nuclear fuel from the No. 2 reactor before the end of 2021, while removal would begin for the No. 3 reactor by 2031.
In announcing its expected profits for the current fiscal year, TEPCO also outlined its estimated expenses for melted fuel removal over the next 12 years.
A total of 330 billion would be needed as preparatory measures, such as further examining the interior of the No. 2 reactor and decontaminating radiation from the area around the three reactors.
Another 20 billion yen is expected to be spent for trial removal of melted nuclear fuel from the No. 2 reactor, while 1.02 trillion yen would be required to construct the facilities needed to remove the melted fuel from the No. 2 and No. 3 reactors.
The construction cost would be written off as a special loss from TEPCO’s balance statement in the fiscal year when the work takes place.
TEPCO forecasts a net profit of 79 billion yen for the current fiscal year, a decrease of 66 percent from fiscal 2019. Sales are expected to decrease by 2.2 percent to 6.199 trillion yen.
http://www.asahi.com/ajw/articles/13259804
South Korea Expresses Concern About New Fukushima Water Release Plan

30 Mar 2020 – 08:15 by OOSKAnews Correspondent
SEOUL, South Korea
South Korea has expressed concern about a new draft plan from Japan to release contaminated Fukushima water from its disabled Fukushima nuclear power plant into the sea.
The country’s Office for Government Policy Coordination said March 26 that Japan should ensure that its plan does not affect the health and safety of South Koreans or the maritime ecosystem, while the Ministry of Oceans and Fisheries said that it “cannot support the Japanese government discharging contaminated water from the Fukushima Daiichi Nuclear Power Plant in the sea without discussions with neighbouring countries”.
South Korea’s latest protest came two days after the Tokyo Electric Power Company (TEPCO) issued a more detailed draft plan to release the contaminated water over 30 years.
Currently, treated, but still radioactive water, is accumulating at about 170 tons per day and is being treated to remove most contaminants, following the earthquake and tsunami in March 2011.
TEPCO reports that currently there is 1.19 million cubic meters of contaminated water in storage on site. The concentration of tritium, which cannot be completely removed, is about 730,000 Bq/litre, or a total of 16 grams. Quantities of treated water are increasing constantly and storage capacity is expected to run out in 2021.
The utility’s report discusses the treatment and disposal methods, which have been developed by outside experts, as being “practical options, both of which have precedents in current practice…the radiation impact of both the discharge into the sea and vapor release is notably small, compared to natural radiation exposure,” saying that the government of Japan, not TEPCO, will make the final decision as to release.
The tritium concentration will be lowered as much as possible under the plan: “For vapor release: TEPCO will study dilution of tritium at a rate equivalent to that for discharge into the sea, as against the regulatory concentration limit of tritium in the atmosphere (5 Bq in 1 liter air)…For discharge into the sea: TEPCO will study dilution rates of tritium with reference to operational standards for “groundwater bypass” and “subdrains” (1,500 Bq in 1 liter water), which are well below the regulatory concentration limit for tritium in seawater (60,000 Bq in 1 liter water).” This is against WHO drinking water guideline (10,000 Bq in 1 liter water)”
If any abnormality is detected, the disposal process will stopped under the draft plan. Monitoring will be enhanced by [an] increase in sampling points and frequency; information will be published promptly.
The report is described as being aimed at the general public and other stakeholders who plan to participate in government-organised “opinion hearings”.
TEPCO plans to take 30 years to release Fukushima nuke plant water into sea or air
Tanks holding treated radioactively contaminated water are seen on the premises of the tsunami-ravaged Fukushima Daiichi Nuclear Power Station in Okuma, Fukushima Prefecture, in this file photo taken from a Mainichi Shimbun helicopter on March 3, 2017
March 25, 2020
TOKYO — Tokyo Electric Power Company Holdings Inc. (TEPCO) is planning to take about 30 years to release treated radioactively contaminated water accumulating at its crippled Fukushima nuclear plant into the sea or air if the government chooses that option.
According to a draft plan, TEPCO will complete the disposal of radioactively contaminated water at its Fukushima Daiichi Nuclear Power Station, which was hit by the 2011 Great East Japan Earthquake and tsunami, sometime between 2041 and 2051. By that time, the government plans to end work to decommission the plant.
If the state decides to release the water into the sea, TEPCO will aim to lower the density of radioactive tritium to around one-fortieth the upper limit set by the government at 60,000 becquerels per liter, while lowering the levels of other radioactive substances as much as possible. The World Health Organization sets the upper limit of radioactive tritium in water for human consumption at 10,000 becquerels per liter. Tritium cannot be removed from contaminated water even if an advanced liquid processing system (ALPS) is used to treat the water.
TEPCO will pay compensation if the release of such water gives rise to harmful rumors and causes damage to local industries.
If the government chooses to release treated water into the atmosphere, TEPCO will also strive to lower the levels of tritium well below the upper limit set by the government.
The government’s subcommittee comprising experts released a report this past February proposing to release radioactively contaminated water at the Fukushima nuclear plant into either the sea or air. The report then emphasizes the advantages of the plan to release the water into the sea.
Junichi Matsumoto, head of TEPCO’s division promoting the decommissioning of the crippled power plant, said the utility remains undecided over the way to dispose of the treated water.
While agreeing that releasing the water into the sea is a better option, Matsumoto said “it’s not true that we can’t technically explore the possibility” of releasing the water into the air.
“We haven’t decided whether to release the water into the sea or atmosphere,” he added.
Tanks on the premises of the nuclear complex are currently holding some 1.19 million metric tons of treated radioactively contaminated water. Since the water contains not only tritium but also other radioactive substances, TEPCO has indicated a plan to begin in the business year of 2020 to conduct experiments using an ALPS and other devices to lower the levels of radioactive substances in treated water.
The government is scheduled to hold hearings to listen to opinions from local communities about the disposal of radioactively contaminated water at the plant, starting in the city of Fukushima on April 6. While explaining the subcommittee’s report and TEPCO’s draft plan in these meetings, the government will make a final decision on the disposal method.
Study: Cesium levels in fish in Fukushima lakes, rivers differ
The Otagawa river, which runs through Minami-Soma, Fukushima Prefecture, and elsewhere, was surveyed for cesium levels in fish following the accident at the Fukushima No. 1 nuclear power plant. (Provided by the National Institute for Environmental Studies)
March 27, 2020
A team of scientists discovered that radioactive cesium released from the crippled Fukushima No. 1 nuclear power plant accumulates in freshwater fish differently in lakes and rivers.
How easily cesium is taken into bodies is determined by what the fish consume in lakes, although factors associated with water quality–such as the ratio of mud particles–are more important for those inhabiting rivers, according to the researchers.
The findings are expected to help predict the cesium concentration in aquatic creatures more accurately even when all of them are not examined individually, the researchers from the National Institute for Environmental Studies said.
“The discovery could be used for estimating how the cesium level has lessened in each fish species,” said Yumiko Ishii, a senior researcher at the institution’s Fukushima Branch.
Higher radioactive cesium levels are reported in freshwater fish than those in the ocean in regions contaminated by the nuclear accident that started to unfold at the Tokyo Electric Power Co. plant in March 2011 following the Great East Japan Earthquake and tsunami.
While cesium remains mainly in the flesh, how the substance is ingested differs greatly depending on the species, habitat and other elements.
Sweetfish, char, landlocked salmon, carp and other species are still banned from shipping in certain areas, even nine years after the nuclear accident.
The research team studied how cesium accumulated in different species in areas of Fukushima Prefecture, targeting 30 kinds of fish in lakes Hayamako, Inawashiroko and Akimotoko as well as the Udagawa, Manogawa, Niidagawa, Otagawa and Abukumagawa rivers two to four years after the accident.
The results revealed that cesium levels could change in lakes if the fish consume differing foods. Higher readings were measured for landlocked salmon, char and other creatures preying on small fish, likely because cesium becomes concentrated in their bodies by eating tiny creatures.
On the other hand, the kinds of food they consume do not affect the cesium concentration in fish species living in rivers.
The findings showed cesium accumulates more easily when the water contains a smaller amount of tiny mud particles and carcasses of living creatures. The higher the ratio of those particles, the lower the cesium level becomes.
The researchers said the reason is apparently that cesium in water is absorbed into those particles, making it difficult for cesium to remain in the fish bodies as the substance is discharged in the particles through feces.
Meanwhile, higher cesium levels were detected for larger species both in lakes and rivers.
The discovery has been published in the international magazine Journal of Environmental Radioactivity at: (https://www.sciencedirect.com/science/article/pii/S0265931X1830715X).
Tepco to pursue its radioactive water sea release plan
Tepco to pursue its radioactive water sea release plan and “Tepco also plans to use social media to counter rumors that exposure to radiation from the released water is harmful.”

Plan to dispose of Fukushima wastewater drafted
March 24, 2020
NHK has learned that Tokyo Electric Power Company, or TEPCO, has drafted a plan for disposing of radioactive wastewater stored at the troubled Fukushima Daiichi nuclear power plant.
Water used to cool molten nuclear fuel from the 2011 accident is treated to remove most radioactive material. But tritium and other substances remain in the water, a huge amount of which is stored in about 1,000 large tanks.
A government panel last month compiled a report that says releasing diluted radioactive wastewater into the sea or air are realistic options.
TEPCO’s plan for doing so would involve diluting the wastewater with seawater, aiming for a tritium level of one-fortieth that allowed by national regulation.
The firm would gradually release the diluted water over about 30 years, taking into consideration the amount of similar water released at other nuclear plants.
TEPCO would also test treating the wastewater again to further remove other radioactive materials.
The utility is to explain the plan to local officials and residents in Fukushima Prefecture. People in the local fishery and tourism industries oppose releasing the water into the ocean.
https://www3.nhk.or.jp/nhkworld/en/news/20200324_42/
Tanks storing contaminated water at the Fukushima No. 1 nuclear power plant in February
Tepco may take 30 years to release Fukushima No. 1 radioactive water
March 25, 2020
Tokyo Electric Power Company Holdings Inc. said Tuesday it may spend up to 20 to 30 years releasing contaminated water into the surrounding environment from its disaster-crippled Fukushima No. 1 nuclear power plant.
The possible time span was mentioned in draft plans Tepco drew up in line with a government panel’s report in February, calling the release of the water into the ocean or the air in the form of vapor a “realistic option.”
The company currently stores roughly 119 tons of water that still contains tritium and other radioactive substances after passing through a treatment process at the nuclear plant, which suffered a triple meltdown in March 2011 caused by a magnitude 9.0 earthquake and tsunami. The amount of contaminated water stored at the facility is still increasing.
According to the draft plans, Tepco will first conduct secondary treatment work to reduce the amount of radioactive substances in the water other than tritium — which cannot be removed by existing systems — to levels below national standards.
Following the treatment, the water will be released into the ocean, after being diluted with seawater to lower the radiation level to 1,500 becquerels per liter, or emitted into the air from a tall exhaust stack after being vaporized.
Tepco also plans to use social media to counter rumors that exposure to radiation from the released water is harmful.
27
Dramatizing the reality of a nuclear meltdown
We can be heroes: “Fukushima 50” offers a dramatic account of real-life on-site manager Masao yoshida (pictured here with reporters in 2011) and his team as they fought to prevent the crippled nuclear plant from melting down in the wake of the Great East Japan Earthquake and tsunami.
March 21, 2020
As with many feature films based on real-life incidents, “Fukushima 50,” which opened nationwide March 6 and depicts the actions of the men who struggled to contain the disaster at the Fukushima No. 1 nuclear power plant following the Great East Japan Earthquake of March 2011, is a blend of factual exposition and dramatic enhancement. Stories require conflict to keep them interesting, usually with a hero fighting an adversary. In “Fukushima 50,” the hero is plant manager Masao Yoshida (Ken Watanabe), who makes life-and-death decisions in resistance against higher-ups rendered as incompetents.
One of these “villains,” as pointed out by writer and editor Yusuke Nakagawa in the March 6 online edition of Gendai Business, is Naoto Kan, who was the prime minister at the time of the disaster. In the movie, Kan’s name is never uttered and, as Nakagawa points out, the actor who plays him, Shiro Sano, doesn’t look like him, but that’s not what concerns Nakagawa. Sano portrays Kan as a puddle of hysteria whose decisions threaten lives because they make Yoshida’s job more difficult. Kan has an infamous temper and Nakagawa acknowledges that he made mistakes during the course of the emergency, but the movie fails to detail the reasons for his actions. Turning him into a babbling fool makes the filmmakers’ job easier, which is to show Yoshida as a towering figure of courage and resourcefulness in the face of a crisis that could have ended in the destruction of eastern Japan.
Nakagawa admits to having a horse in this race, as he helped Kan write his own account of what went down at the Prime Minister’s Office during those fateful days, and he concurs with the conclusion that Yoshida and the men who worked at the plant are heroes and that Yoshida’s employer, Tokyo Electric Power Company Holdings Inc. (Tepco), was the main problem. However, he can’t help but think that the film’s pillorying of Kan was due to more than dramatic license. There was something political about it. Kan has since become a pariah to many people. As much as any other matter, it was Kan’s handling of the Fukushima disaster that led to the destruction of his party. The Democratic Party of Japan no longer exists.
Nevertheless, Kan has no problem with the portrayal, according to the film’s director, Setsuro Wakamatsu, who said so during a news conference at the Foreign Correspondents’ Club of Japan following a press screening of “Fukushima 50” on March 4. Kan’s magnanimity is noble, perhaps, but it should be noted that he has his own film to promote, or, at least, a film that shows him in a more sympathetic light. “The Seal of the Sun,” originally released in 2016, had a much smaller budget than “Fukushima 50” and no marquee stars. It looks at the disaster from the vantage point of the Prime Minister’s Office, focusing on Tepco’s lack of cooperation with the government, and while it doesn’t contradict the Yoshida hero narrative, it does complicate it with points that “Fukushima 50” downplays or doesn’t even bring up.
Kan has made himself available to discuss those points at public screenings of “The Seal of the Sun.” Such local events aren’t going to counteract the message of “Fukushima 50,” and they aren’t meant to, but the narrative distinctions do show how uneven the coverage of the Fukushima disaster has been. The most glaring example of this unevenness is a 2014 story by the Asahi Shimbun’s special investigative team based on an interview that Yoshida gave to the government. The report undermined the Fukushima hero narrative by saying that 90 percent of the plant workers fled the facility in fear for their lives. The Asahi Shimbun management, already smarting from other recent scandals, eventually retracted the piece after receiving complaints saying the article implied the workers were cowards, effectively ending the special investigative team in the process. Ryusho Kadota, the journalist who wrote the book that was the basis for the “Fukushima 50” script, wrote another book refuting the Asahi Shimbun’s coverage, though, as former New York Times Tokyo bureau chief Martin Fackler points out in an article he wrote for the Asia-Pacific Journal, there was nothing essentially untrue in the Asahi Shimbun story. In fact, Tepco admitted that about 650 workers had fled, but said many were not regular company employees. The legendary “Fukushima 50” (in reality, they numbered 69), a term coined by foreign media, remained at the plant.
The argument about what really happened isn’t over facts. It’s over how those facts are interpreted. In “Fukushima 50,” Kan’s desperation is presented as a danger to the country. In “The Seal of the Sun,” it shows how hard he is trying to grasp the actual situation on the ground. Before the Yoshida report in 2014, the Asahi Shimbun’s editorial slant was generally critical of nuclear power. Afterward, it became neutral.
Nakagawa thinks these differences are politically influenced. Almost all of Japan’s nuclear power capacity has been off-line since the Fukushima incident, a situation the present government wants to reverse but finds difficult to do because of public resistance. In that sense, the story of the men who saved Japan from nuclear catastrophe can be exploited by both sides. Anti-nuclear forces say it proves how dangerous nuclear power is, while pro-nuclear forces say that it shows how Japanese ingenuity and dedication prevails.
However, even that distinction is subject to dispute. Retired Fukui District Court Chief Justice Hideaki Higuchi was one of the few judges to find in favor of plaintiffs suing to stop resumption of nuclear power plants. Higuchi reached these decisions after carefully studying the Fukushima No. 1 disaster and concluding that it was averted as much by serendipity as by Yoshida’s and the Fukushima 50’s bravery. These “miracles,” which had to do with the availability of cooling water and quake-related damage to the reactor housing, have been openly discussed, but they aren’t emphasized as much because it takes something away from the hero tale. As a judge, Higuchi had to pay closer attention to all the facts than a feature film script writer does.
Fukushima compensation guidelines need further revision
The difficult-to-return-zone around Ono Station on the JR Joban Line in Okuma, Fukushima Prefecture is empty on March 1. A part of evacuation order was lifted on March 5, but most of the area remains eerily the same as when the nuclear disaster happened in 2011.
March 19, 2020
The Sendai and Tokyo high courts recently said in separate rulings that Tokyo Electric Power Co. should pay more in compensation to victims of the 2011 accident at the company’s Fukushima No. 1 nuclear power plant.
Some 30 class action lawsuits have been filed by people who were forced to evacuate from their homes in the wake of the nuclear disaster to seek damages beyond the amounts the electric utility has agreed to pay.
The fact that the two rulings, the first high court decisions concerning these cases, both questioned the adequacy of the existing Fukushima compensation program is highly significant in its legal and policy implications.
During the trials, the plaintiffs argued that it is difficult to return to their homes even if the evacuation orders are lifted. Even if they return, they claimed, they will face local towns and communities that have been radically altered by the accident.
The two high courts acknowledged the seriousness of the corrosive effects of what these victims call “the loss and transformation” of their hometowns and ruled that they deserve to be compensated for this problem in addition to damages for being forced to flee their homes and the mental anguish caused by their lives as evacuees.
The courts awarded the plaintiffs additional damages beyond the amounts the company has already paid.
The utility has adamantly refused to pay any blanket compensation to victims beyond the amounts based on the guidelines set by the Dispute Reconciliation Committee for Nuclear Damage Compensation, a panel established within the government to settle disputes over compensation for victims of the Fukushima disaster.
TEPCO has also rejected deals to settle these class action suits proposed by the Nuclear Damage Compensation Dispute Resolution Center, a body created to help resolve such disputes through simplified procedures.
The company has even turned down a compromise recommendation issued by the Fukushima District Court based on arguments during a trial over a compensation dispute it had heard.
Clearly, the company fears that accepting such a deal would affect the entirety of its compensation talks and cause the total of damages it has to pay to soar.
After the devastating accident, however, TEPCO made “three vows.” It pledged to pay compensation to all victims without leaving a single one uncompensated, ensure that compensation will be paid quickly according to individual circumstances and respect proposals to settle disputes.
As the company that is responsible for the unprecedented nuclear accident, TEPCO has a duty to make sincere responses to the high court rulings in line with its own vows.
The government, which has promoted nuclear power generation as a national policy and is effectively the largest shareholder of the utility, has the responsibility to provide strict guidance for the company’s actions concerning the matter.
The two rulings have also brought to the fore some shortcomings of the guidelines set by the dispute reconciliation committee.
Established immediately after the accident, the guidelines are obviously out of tune with the complicated realities of the accident’s aftermath despite several revisions that have been made.
The “loss and transformation” of hometowns is a consequence of the accident that has become clearly visible over the nine years that have passed since that day in 2011.
It is time for the government to have some in-depth debate on the effects of this problem on affected people and embark on a sweeping review of the guidelines.
The high court rulings are not totally acceptable, however. Arguing that the money TEPCO has already paid covers part of the additional damages owed to the victims, the rulings only awarded the plaintiffs 1 million yen to 2.5 million yen ($23,000) per head in additional compensation.
Many victims have criticized the amounts for being “too small to be fitting compensation for the actual damage” suffered by the victims.
There is no easy solution to this complicated problem. But that does not justify inaction in the face of such gross injustice.
All the parties concerned need to offer ideas and ingenuity to spare the victims the need to spend any more effort and time with regard to compensation issues.
http://www.asahi.com/ajw/articles/13227560
State funds to be juggled to cover cleanup costs from Fukushima
Interim storage facilities for radioactive waste from the Fukushima No. 1 nuclear disaster are shown in the foreground in Okuma, Fukushima Prefecture. Seen in the background is the nuclear complex.
March 18, 2020
The government has moved to revise a law to allow for the diversion of budgetary funds set aside for the promotion of renewable energy to help cover ballooning costs related to the storage of radioactive waste produced during cleanup work after the Fukushima nuclear disaster.
Tax revenues appropriated for renewable-related projects are not permitted to be used for nuclear power programs under the special account law, which governs budgets allocated for specific purposes.
Earlier this month, however, the government submitted a bill to the Diet to revise the law to make the diversion of funds legal. It plans to enact the legislation during the current Diet session and put the revised law into force in April 2021.
This would be the first time for a revenue source earmarked for a specific expenditure to be diverted to a different purpose.
But the revision bill is likely to draw criticism from the public as it concerns the divisive issue of nuclear power and raises further questions about the government’ longstanding insistence that nuclear power is an inexpensive energy source.
Energy-related expenditures are booked under the government’s special account, separately from the general account.
These expenditures are grouped into more categories, such as one for nuclear energy and another for renewable energy sources.
About 300 billion yen ($2.78 billion) a year is allocated for programs associated with nuclear energy, including grants to local governments hosting nuclear power plants, while 800 billion yen or so is set aside to promote renewable energy, energy saving efforts and ensuring a stable energy supply.
Revenues for nuclear energy-related programs are collected under the promotion of power resources development tax, which are levied on electricity rates. Those for renewables are collected from businesses importing petroleum and coal under the petroleum and coal tax.
They are project-specific tax revenues, meaning they cannot be used for other purposes. The amount of those budgets remains at similar levels each year.
The government’s move was prompted by runaway costs to process a vast volume of contaminated waste due to the 2011 disaster at the Fukushima No. 1 nuclear plant and maintain them in interim storage facilities in Fukushima Prefecture.
The government decided to shoulder some of the costs to help Tokyo Electric Power Co, operator of the stricken plant, and gained Cabinet approval to do so in December 2013.
Since fiscal 2014, it has set aside about 35 billion yen annually for the interim storage facilities. The funds come from revenues earmarked for nuclear energy-related projects in the special account.
But expenditures concerning the storage facilities are running a lot higher than initially envisaged.
An estimate released in late 2016 by the Ministry of Trade, Economy and Industry showed that the project will eventually cost 1.6 trillion yen, compared with an initial projection of 1.1 trillion yen.
The government has allocated an additional 12 billion yen annually for the storage facility project since fiscal 2017.
Government officials say the price tag could further increase in coming years, likely leaving the government with scant financial resources to cover the project.
The revision bill has a clause stipulating that funds diverted to nuclear energy-related programs must eventually be returned to renewable energy project-specific tax revenues.
But it remains unclear if the clause will ease objections from opponents of nuclear energy, even if the fund diversion is a temporary measure.
Yoshikazu Miki, former president of Aoyama Gakuin University and a specialist of the tax system in Japan, called on the government to justify its proposed fund diversion by providing a full explanation of the issue.
“A special account budget has rarely been scrutinized during Diet debate, unlike the general account,” Miki said. “The revision bill requires special attention as it is related to a nuclear power plant. Some members of the public may raise objections to the revision. The government needs to explain the matter to taxpayers to defend its need to act in this way.”
Tokyo High Court slashes damages to Fukushima nuclear disaster evacuees
Isao Enei (left), head of a group of plaintiffs seeking damages for evacuating after the 2011 Fukushima No. 1 nuclear power plant accident, speaks at a news conference Tuesday in Tokyo alongside their attorney Junichiro Hironaka.
March18, 2020
The Tokyo High Court on Tuesday ordered ¥1 million in additional damages be paid each to some 300 evacuees from the 2011 Fukushima nuclear disaster, down by two-thirds from the amount awarded by a lower court ruling.
The total amount of additional compensation Tokyo Electric Power Company Holdings Inc. must pay was reduced to about ¥360 million from the ¥1.1 billion awarded by the Tokyo District Court in 2018.
The nuclear accident occurred at the Fukushima No. 1 nuclear power plant operated by Tepco, after it was affected by the March 2011 earthquake and tsunami.
In their petition, the plaintiffs, including former residents of the Odaka district in Minamisoma, Fukushima Prefecture, sought additional damages of ¥10.9 billion in total.
The ruling was the second by a high court on a collective damages lawsuit filed by those displaced by the nuclear accident, following one issued by Sendai High Court last week.
On Tuesday, presiding Judge Wataru Murata said Tepco must pay additional damages on top of the ¥8.5 million it paid per person based on estimates calculated under government-set interim standards.
The additional damages have to be paid to compensate for the loss of hometowns, as “the foundations of residents’ lives have changed greatly and have yet to be restored,” Murata said.
But the amount of the additional damages should be reduced because individual circumstances of the evacuees should not be taken into account, Murata said, denying the need for such consideration as had been recognized by the lower court.
“The reduction is unavoidable, also considering that returning to hometowns is possible,” the judge concluded.
Plaintiff Isao Enei criticized the latest ruling at a news conference, saying that actual circumstances in areas hit by the nuclear disaster were completely ignored.
“There is no point in filing a collective suit if individual damages are ignored. The ruling is inconceivable,” said Junichiro Hironaka, an attorney for the plaintiffs.
70% do not expect Tokyo Olympics to be held as scheduled: Kyodo poll
March 15, 2020
A total of 69.9 percent of people do not expect the Tokyo Olympic and Paralympic Games this summer to be held as scheduled amid the global outbreak of the novel coronavirus, a Kyodo News survey showed Monday.
The poll, conducted from Saturday to Monday by phone, comes as Japan continues with preparations for the Olympics, from July 24 to Aug. 9, and the Paralympics, from Aug. 25 to Sept. 6, with Abe saying he has no immediate plan to declare a state of emergency, and that the Summer Games will go ahead as scheduled.
Even though public opinion is split on how well the government has responded to the crisis, the approval rating for Prime Minister Shinzo Abe’s Cabinet rose to 49.7 percent from 41.0 percent in February.
Of those who said they approved of the administration, 53.4 percent responded that it was because there were no other appropriate choices besides Abe.
Since the previous opinion poll in mid-February, steps have been taken by Abe’s government to combat the spread of the virus, including requesting large events be canceled, and schools be shut through the start of the new academic year in April, relief measures for businesses and tougher border control measures, especially for travelers from China and South Korea.
In the survey with 1,032 respondents, 48.3 percent said the government measures against the virus are appropriate, while 44.3 percent said they disapprove of them.
The spread of the pneumonia-causing virus has halted a significant amount of international and domestic travel.
To ease the adverse effects of the outbreak, Abe has introduced zero-interest loans for small and midsize companies that are in a cash crunch due to sharp falls in sales as part of funding packages totaling 1.5 trillion yen ($14 billion).
Still, 90.7 percent of the respondents said they are worried or somewhat worried about the economic impact of the new coronavirus outbreak, an increase from 82.5 percent in the previous poll.
A total of 71.8 percent answered that the school closures aimed at preventing a further spread of the virus were appropriate or somewhat appropriate, while 83.1 percent supported the implementation of tougher border control measures for travelers from China and South Korea, a move which has hit Japan’s tourism industry hard.
The virus has claimed the lives of at least 31 people in Japan, and more than 1,500 people have been infected with it, including about 700 cases from a cruise ship that was quarantined near Tokyo.
As Abe has been facing severe criticism over the handling of documents related to publicly funded annual cherry blossom viewing parties that are at the center of yet another scandal alleging cronyism, 82.5 percent said he failed to explain himself to the public over the issue sufficiently.
The survey, covering 739 randomly selected households with eligible voters and 1,219 mobile phone numbers, obtained responses from 512 and 520 people, respectively.
https://english.kyodonews.net/news/2020/03/c44332182570-urgent-70-do-not-expect-tokyo-olympics-to-be-held-as-scheduled-kyodo-poll.html?fbclid=IwAR2OkeV6C-aL7x_W7DlMUmsSBift5sozEdExA8xhw-ULZGeECHbcn6PdhOE
JR East’s Joban Line fully reopens after nine long years following Fukushima disaster
A train stops at Ono Station on the Joban Line in the town of Okuma, near the crisis-hit Fukushima No. 1 nuclear plant, on Saturday as the long-suspended train line connecting Tokyo and Miyagi Prefecture fully resumes service.
Mar 14, 2020
FUKUSHIMA – After nine long years, service on the Joban Line is fully back on track.
The reopening of a 20.8 kilometer stretch between Tomioka and Namie near the crippled Fukushima No. 1 nuclear plant means that all Tohoku train lines have now completely reopened following the March 2011 triple disaster.
While some anticipate that the improvement of public transport in disaster-hit areas along Fukushima Prefecture’s Pacific coast will lead to an increase in visitors and regional revitalization, others say the impact will be limited as cars remain the mode of transportation of choice for most residents.
Prior to reopening, JR East had offered bus services for the closed section of the Joban Line, a 344-kilometer route that connects Tokyo and Miyagi Prefecture.
Nine JR and private railway lines took more than a year to reopen following the disaster, according to the transport ministry.
The Rias Line, operated by Sanriku Railway Co., had been repaired following the 2011 disaster but was again damaged by Typhoon Hagibis last October.
With services fully resumed, limited express trains linking Tokyo with Sendai, the capital of Miyagi, will make three round-trips per day.
Among the five stations along the recently reopened section, three are in the towns of Futaba and Okuma, which host the crippled plant of Tokyo Electric Power Company Holdings Inc., as well as Tomioka.
The three municipalities had been designated by the government as a no-go zone due to high radiation levels. The entry ban was gradually lifted in Okuma and Tomioka and the restrictions for areas near the stations in the three towns were newly removed earlier this month.
As of March 1, only 1,943 people reside in Okuma and Tomioka, while no one lives in Futaba. The three towns had a combined population of around 34,000 prior to the disaster.
Repair work on the damaged stretch of the Joban Line was long-delayed as most of it was located in a zone marked as having high levels of radiation, JR East said.
Japan’s 3/11 Recovery Stalled by Fukushima Decommissioning Delays
March 13, 2020
Delays in dismantling the disaster-stricken nuclear power complex cast doubt on whether recovery goals will move forward according to schedule.
Nine years after a quake-triggered tsunami sparked a triple meltdown at Fukushima Daiichi nuclear power plant, decontamination and decommissioning continues in northeastern Japan. The ultimate goal of removing all debris is expected to take anywhere between 30 to 40 years, but progress has been slower than originally planned. So far just one-fourth of decommission work has been completed, drawing attention to work that has not yet begun.
The Fukushima decommissioning and decontamination draft has been amended five times. While changes published in December offered a specific time frame for the first time, the latest timetable for debris removal has been pushed back five years, citing the need for additional safety precautions. Previously, the process of removing spent fuel was scheduled from 2021 to 2024. But work on reactor two looks more likely to start in 2025 and last until 2027, followed by reactor one work commencing sometime between March 2028 and March 2029.
The powerful tsunami, which reached over 40 meters in some areas, took the lives of 22,167 people. At the same time, the loss of power to the entire Fukushima Daiichi plant caused reactors one, two, and three to overheat, sparking hydrogen explosions and the release of radioactive contaminants. This forced 160,000 survivors to evacuate. Despite evacuation orders being lifted in some of the “difficult to return” areas, many still opt to stay away from their homes nine years later.
The next decommissioning stage sets out the removal of 4,471 spent fuel rods inside the cooling pools of reactors one to six. But the biggest obstacle is finding a way to locate and remove the molten nuclear fuel. With frequent delays, evacuees face a constant sense of uncertainty, tangled in a waiting game to see whether decommissioning work can be completed in 30 years.
Reactor two is seen as the safest and easiest option to start full-scale debris removal since it suffered the least structural damage with only “some fuel” melting through the pressure vessel and accumulating at the bottom of the containment vessel. But with no established method for debris retrieval, attempts to survey the location and distribution of molten nuclear fuel among the rubble requires a lengthy trial and error process. In mid-February 2019 an attempt to probe and collect samples from reactor two failed to find and lift the main nuclear fuel debris, instead lifting portions of pebble-like sediment with the lowest radiation readings from the surface. At this stage there is no way for TEPCO, the company that owns the Fukushima Daiichi plant, to determine where fuel debris lies among the rest of the metal debris. It’s estimated that reactor two alone contains 237 metric tons of debris while reactors one and three contain a combined 880 tons. The complexity of debris removal requires developing specialized technology that does not yet exist.
Also plaguing decommissioning efforts is the battle over how to safely dispose of 1 million tons of contaminated water that were used to cool nuclear fuel. Currently, huge tanks on the premises store the polluted runoff, which could fill 400 Olympic swimming pools, but space is expected to run out by mid-2022.
On average 170 tons of contaminated water is produced to cool fuel in nuclear reactors. Without constant cooling, nuclear fuel risks melting from its own heat in a process called decay heat. With two years needed to prepare a disposal method, time is running out for a final decision.
Government proposals to slowly release contaminated water into the ocean has sparked fierce backlash from locals and the agriculture and fishing industries, who argue traces of radioactive materials such as tritium still found in “treated” water could further harm a region still struggling to restore its international reputation.
Last month, International Atomic Energy Agency (IAEA) Chief Rafael Mariano Grossi visited the Fukushima nuclear power plant where he commended the government’s “dual approach” of decommissioning the plant while revitalizing the local community. Grossi said the IAEA could help provide reassurance to the public that Japan’s plan to release treated water into the ocean meets international standards.
To make matters worse, decommissioning operations have been temporarily suspended due to the spread of coronavirus. Tepco was forced to cancel on-site inspections of reactor one scheduled during March, which would have brought together some 1,800 experts and members of parliament, as well as local residents and student groups.
https://thediplomat.com/2020/03/japans-3-11-recovery-stalled-by-fukushima-decommissioning-delays/
‘Fukushima’s radioactive water discharge is important to Koreans’
Greenpeace nuclear campaigner Shaun Burnie in front of the Fukushima Daiichi nuclear plant, five years after the accident. The environmental organization has launched an underwater investigation into the marine impacts of radioactive contamination on the Pacific Ocean resulting from the 2011 nuclear disaster,
By Bahk Eun-ji
March 13, 2020
Shaun Burnie, a senior nuclear specialist at Greenpeace Germany, has been working in Fukushima since 1997 to stop the operation of the Fukushima Daiichi Nuclear Power Plant, with much of his time based in Japan.
Among a number of nuclear experts around the world who have been condemning the Japanese government’s plan to discharge radioactive water from the destroyed Fukushima power plant into the Pacific Ocean, Burnie claims this issue is clearly important to Koreans as they understand the risks of nuclear energy and care about the environment.
“Fukushima is a defining issue of this time as it continues to pose a threat to the environment not just of Japan but the Asia Pacific region. This is a nuclear disaster with no end and Koreans realize that only by speaking up and opposing bad decisions can the progress be made in protecting our environment,” he said.
The nuclear expert said the opposition in Korea to the Japanese government’s plan to discharge contaminated water from Fukushima is entirely justified and essential, so the opposition should continue here in Korea. At the same time, Koreans also should be supporting the local Japanese communities who are opposed to the discharges.
Burnie also said the discharges of the contaminated water are a direct threat to the marine ecosystem and human health as all radioactivity has the potential to cause harm as technically there is no safe level of exposure. The discharges are more than tritium, which can cause damage to human and non-human DNA, but also many other radionuclides such as strontium that, even if processing of the contaminated water is successful, will still be discharged in enormous quantities.
“None of this can be justified from an environmental perspective when there is a clear alternative ― long term storage and processing to remove radionuclides, including tritium.”
The Japanese government has sought for many years to deny that there are radiation risks in Fukushima, which is a central part of their strategy to support nuclear power. By creating the illusion that Fukushima has recovered from the 2011 disaster, the Japanese government think they can convince people to support the restarting of nuclear reactors although the majority of Japanese people are against it.
“It is one reason why the human rights of tens of thousands of Fukushima citizens, including women and children, as well as tens of thousands of workers are violated consistently by the Japanese government,” he said.
https://www.koreatimes.co.kr/www/nation/2020/03/371_286064.html
-
Archives
- March 2026 (109)
- February 2026 (268)
- January 2026 (308)
- December 2025 (358)
- November 2025 (359)
- October 2025 (376)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS