TEPCO to scrap Onagawa NPP’s reactor#1

Utility plans to scrap reactor at Onagawa plant
Tohoku Electric to scrap aging No. 1 unit at Onagawa nuclear plant
Fukushima Daiichi Unit 1-2 Vent Tower Sump Drain Sample Tested
Tepco collected a sample from the sump drain connected to the Unit 1-2 vent tower.
They found 60cm of water in the 100 cm deep container.
The water sample tested as follows:
beta radiation: 60,000,000 bq/liter
Cesium 134: 8,300,000 bq/liter
Cesium 137: 52,000,000 bq/liter
These readings are among the higher ranges of contaminated water found around the plant.
Fukushima Daiichi Reactor 1 Spraying & Cover Removal
Spraying of anti-scattering agent before taking down the wall panels of Unit 1 building cover at Fukushima Daiichi Nuclear Power Station.
Video taken on: August 4 and September 3, 2016
Produced by: TEPCO Holdings, Inc.
Fukushima plant building exposed as TEPCO opens old wounds
The outer layer of the crippled No. 1 reactor building at the Fukushima No. 1 nuclear power plant is exposed as Tokyo Electric Power Co. removes one of the panels covering the facility at 6:22 a.m. on Sept. 13.
The devastated outer layer of Fukushima No. 1 nuclear power plant’s No. 1 reactor building has been exposed for the first time in almost five years in the painstaking reactor decommissioning process.
Plant operator Tokyo Electric Power Co. began removing on Sept. 13 the exterior walls of the cover installed around the structure to prevent the dispersal of radioactive materials on Sept. 13.
Shortly past 6 a.m., a large crane began removing a massive piece of the cover installed around the reactor building. The panel dismantled that day measured 23 by 17 meters and weighed 20 tons.
The cover was installed in October 2011 as a temporary measure after a nuclear meltdown occurred following the Great East Japan Earthquake and tsunami in March that year. The meltdown caused a hydrogen explosion, blowing the walls off the building.
Once the cover is dismantled, the operator can assess the state of the building’s interiors and remove the debris fallen onto the spent fuel pool inside.
“Steady progress is necessary in reconstruction, but we hope they will carry on the procedure with safety as the No. 1 priority,” said a Fukushima prefectural government official.
TEPCO said that it plans to remove the remaining 17 panels of the covering by the end of the year. The portion covering the roof has already been removed.
Once the cover is removed, the utility will begin drawing up plans to remove the 392 fuel assemblies from the spent fuel pool and melted nuclear fuel from inside the building.
The plant operator said that it plans to be extra careful during the procedure. It will shroud the building in tarpaulins once the cover is removed as a precautionary measure against dust and other materials containing radioactive materials from being carried aloft by the wind.
The utility and central government’s joint schedule for the decommissioning process of the reactor states that the removal of the fuel rods from the pool will start in fiscal 2020.
http://www.asahi.com/ajw/articles/AJ201609130070.html
TEPCO resumes removal of Fukushima plant cover
The operator of the Fukushima Daiichi nuclear power plant has resumed work to remove a temporary cover from a damaged reactor building.
Tokyo Electric Power Company had covered the partially collapsed No. 1 reactor building to prevent radioactive materials generated by the 2011 accident from spreading.
It started the removal process in July last year, the first step in the retrieval of spent nuclear fuel from a storage pool in the building.
The operation was suspended after sheets from the roof area were removed to assess the building’s condition.
On Tuesday, cranes were used to detach the panels from the side of the building, and the debris inside was exposed for the first time in 5 years. Each panel is 23 by 17 meters and weighs 20 tons.
TEPCO officials say they will spray chemicals to ensure that radioactive substances do not disperse even in strong winds.
They say they plan to complete the operation by the end of November, so that the debris can be removed. The removal of spent fuel is due to begin in 2021.
Industry ministry official Masato Kino who monitored the progress at the scene said difficult procedures will continue, but the first step has been taken. He said he hopes to carefully and safely proceed.
http://www3.nhk.or.jp/nhkworld/en/news/20160913_28/
Removal of the top southwest panel off reactor 1 today
2016.09.13_06.00-09.00.Unit1 side
Third ceiling panel removed from Fukushima reactor
Workers at the Fukushima Daiichi nuclear plant have removed half of the ceiling panels covering a damaged reactor building. The work is part of efforts to decommission the facility.
The No.1 reactor building was heavily damaged by a hydrogen explosion during the 2011 meltdown. Tokyo Electric Power Company installed a cover around it to prevent the spread of radioactive material.
The utility is now removing the cover so it can clean up debris inside the facility. Two of the 6 ceiling panels that make up the cover were removed between late July and early August.
The utility then halted the work to monitor radiation levels and check the conditions of the debris. Since no abnormalities were found, workers removed a 3rd panel on Tuesday using a remote-controlled crane.
TEPCO says there’s been no change in radiation levels around the reactor buildings. It says measurements taken before the work on Tuesday showed that wind blowing inside the cover was weaker than expected.
The utility plans to finish dismantling the cover by around late next year.
Source: NHK
http://www3.nhk.or.jp/nhkworld/english/news/20150908_21.html
Tepco started removing the cover of Reactor 1 building
According to Tepco, they started removing the main part of cover of Reactor 1 on 7/28/2015.
They announced that there was no significant change in dust monitoring data and radiation monitoring post readings.
The former Fukushima worker “Happy11311″ commented on Twitter that the high level of contamination might be retained on the ground floor with rain after they take the cover away.
Sources:
Click to access handouts_150728_07-j.pdf
http://photo.tepco.co.jp/date/2015/201507-j/150728-01j.html
https://twitter. com/Happy11311/status/625634149794123776
http://fukushima-diary.com/2015/07/photo-tepco-started-removing-the-cover-of-reactor-1-building/
Removal starts of protective shroud over reactor at Fukushima No. 1
Tepco on Tuesday began dismantling the temporary shroud covering the wrecked reactor 1 building at the Fukushima No 1 nuclear plant.
Tokyo Electric Power Co. installed the cover in October 2011 to keep radioactive materials from dispersing.
Workers used a crane Tuesday to remove one of the six panels that form the shroud’s roof. Each panel is about 7 meters wide and about 42 meters long.
As the panel came off, the upper part of the reactor building could be seen for the first time since December, when part of the cover was temporarily removed. The building’s exterior was shattered in a hydrogen explosion in March 2011, in the first few days of the crisis.
Tepco plans to complete removing the shroud in fiscal 2016 and to clear debris and install equipment for the sensitive process of removing the 392 spent fuel assemblies currently lying in the building’s storage pool. That procedure is expected to begin in fiscal 2020.
Takao Kikori, a senior nuclear safety official in the Fukushima Prefectural Government, called for care to be taken in the dismantling work to ensure the safety of local people.
The utility plans to remove the second panel in early August or later and complete the removal of all six panels by the end of this year. Later it will remove the side panels and install windbreaker sheets ahead of clearing the debris.
The cover was installed as an emergency measure to keep radioactive dust from scattering. Tepco initially planned to dismantle it in fiscal 2013 or 2014 but was forced to delay the work to take additional dust control and other measures.
Source: Japan Times
http://www.japantimes.co.jp/news/2015/07/28/national/removal-starts-protective-shroud-reactor-fukushima-no-1/#.VbelrPmFSM9
TEPCO removes canopy panel from Fukushima reactor N°1 building
The interior of the No. 1 reactor building of the Fukushima No. 1 nuclear power plant can be seen from above after a canopy panel was removed on July 28.
OKUMA, Fukushima Prefecture–Tokyo Electric Power Co. on July 28 started removing a canopy covering a damaged reactor building at the Fukushima No. 1 nuclear plant to prepare for the eventual extraction of spent nuclear fuel inside.
Around 7 a.m., workers using a giant crane lifted away the first of six canopy panels, each measuring 40 meters long and 7 meters wide, from the No. 1 reactor building.
The 30-minute removal of the panel left a large hole in the canopy through which steel beams on the damaged upper part of structure could be seen from above. Workers closely monitored radiation levels in the surrounding areas during the removal process.
The utility plans to remove the remaining five panels from next week.
The removal of the canopy will allow TEPCO to clear debris inside the building, possibly in the latter half of fiscal 2016. That process should pave the way for the removal of nuclear fuel rods from the spent fuel pool in the building.
Before removing the canopy panel, the utility sprayed the inside of the reactor building with liquid resin through holes drilled in the cover to prevent radioactive materials from being stirred up during the dismantling work.
TEPCO initially planned to start removing the canopy panels from the No. 1 reactor building in summer 2014, but the schedule was delayed because a large amount of radioactive substances was released into the environment when the utility removed debris from the No. 3 reactor building in August 2013.
Even after the anti-scattering resin was sprayed into the No. 1 reactor building in May, removal of the canopy panel was postponed by a problem inside the building.
Source: Asahi Shimbun
http://ajw.asahi.com/article/0311disaster/fukushima/AJ201507280071
TEPCO to Resume Fukushima Daiichi Reactor One Protective Cover Removal on July 28
TEPCO will start dismantling the cover on July 28.
TOKYO (Sputnik) — Japanese utility company TEPCO will resume work to remove a protective cover from the stricken Fukushima reactor building in late July, a public Japanese broadcaster said.
A dome was installed over Reactor No.1 in 2011 to stop radioactive particles from escaping into the atmosphere after the facility suffered a meltdown when a tsunami caused by a powerful earthquake crippled the Fukushima nuclear plant.
According to the NHK broadcasting organization, the operator will begin dismantling the cover on July 28 if weather permits.
TEPCO began preparatory work to dismantle the protective cover over the Reactor 1 building in May. The preparations began with anti-dispersal agents poured through holes in the cover’s roof to prevent radioactive dust from escaping into the surrounding environment during the dismantling process.
Dismantling has been delayed several times due to technical failures.
Source: Sputnik News
Cover of Fukushima reactor 1 building to be removed
The operator of the crippled Fukushima Daiichi nuclear plant has decided to resume work to dismantle the cover of the No.1 reactor building later this month.
The work is part of efforts to decommission the facility, which suffered a meltdown after the March 2011 earthquake and tsunami disaster.
A hydrogen explosion damaged the No.1 reactor building. Tokyo Electric Power Company installed the cover to prevent radioactive material from dispersing.
The utility initially planned to start dismantling the cover last year to clear away radioactive rubble and remove spent nuclear fuel stored at a pool inside the building.
The plan was postponed several times after people expressed concern about the dispersal of radioactive substances.
Engineers also found a problem with a device that controls the air flow in the building when dismantling work was set to begin in May.
The engineers say they have addressed the problem. TEPCO decided to resume the dismantling work on July 28th as long as weather conditions permit.
As part of the plan, chemical agents will be sprayed to prevent radioactive dust from being released into the air.
Engineers plan to remove the six roof panels in about 4-months’ time.
Source : NHK
http://www3.nhk.or.jp/nhkworld/english/news/20150716_01.html
TEPCO removes 2nd canopy panel covering Fukushima reactor building
November 10, 2014
OKUMA, Fukushima Prefecture–In preparation for clearing debris and eventually removing nuclear fuel from inside, Tokyo Electric Power Co. on Nov. 10 temporarily removed another panel from the canopy covering a damaged reactor building at the crippled Fukushima No. 1 nuclear power plant.
Debris inside the building were visible from the opening, which is 40 meters long and 14 meters wide, equivalent to one-third the size of the entire roof.
The first of the six canopy panels was removed on Oct. 31.
The utility has been spraying the inside of the reactor building with liquid anti-scattering resin since Oct. 22 to prevent radioactive materials from being stirred up during the dismantling work. The interior of the building will be checked throughout this month.
TEPCO also plans to keep a close eye on radioactivity levels inside the plant grounds and will notify local municipalities if any abnormalities are recorded.
The removed roof panels will be reinstalled as early as within this month, and their full-scale removal is expected to begin in March 2015.
Sources:
NHK http://www3.nhk.or.jp/nhkworld/english/news/20141110_11.html
Asahi Shimbun http://ajw.asahi.com/article/0311disaster/fukushima/AJ201411100047
Strontium-90 detected in potentially discharged water from Reactor 1 and 3
October 20, 2014
2,800 ~ 11,000 Bq/m3 of Strontium-90 have been detected from pumped water around Reactor 1 and 3, according to Tepco.
On 10/1/2014, Tepco released nuclide analysis data of groundwater. The tested groundwater was pumped up from the facilities called “sub-drain” located beside Reactor 1 ~ 4.
These “sub-drains” were originally to reduce groundwater volume to flow into the basement of each reactor building, however abandoned because of the high level of contamination after 311. Tepco is trying to restart using these sub-drains to pump up highly contaminated water and to discharge to the sea.
(cf, Tepco to pump up highly contaminated groundwater for potential discharge today / Drainage plan submitted to NRA.
The samples were taken this September and last September. From the sample near Reactor 1, 11,000 Bq/m3 of Strontium-90 was detected last September. From the sample near Reactor 3, 2,800 Bq/m3 of Strontium-90 was measured this September.
These readings were not checked by third party organizations, so the actual density can be higher than announced.
Either way, the data shows groundwater contamination is spreading from around the reactor buildings to the outside of the port. (cf, Strontium-90 detected outside of Fukushima port / Highest reading in front of Reactor 4 too.
Click to access around_rb_141001-j.pdf
Source: Fukushimary Diary
http://fukushima-diary.com/2014/10/strontium-90-detected-potentially-discharged-water-reactor-1-3/
-
Archives
- June 2022 (276)
- May 2022 (375)
- April 2022 (378)
- March 2022 (405)
- February 2022 (333)
- January 2022 (422)
- December 2021 (299)
- November 2021 (400)
- October 2021 (346)
- September 2021 (291)
- August 2021 (291)
- July 2021 (257)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Fuk 2022
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS