Aomori Rokkasho Reprocessing Plant Stops Cooling Function “Valve Mistakenly Closed?”

July 19, 2022
Regarding the trouble at a spent nuclear fuel reprocessing plant in Rokkasho Village, Aomori Prefecture, where the cooling function for high-level radioactive liquid waste temporarily stopped, the operator, JNFL, revealed the results of its investigation, which indicated that workers likely accidentally closed a valve on an operating pipe that circulates water for cooling.

At the Rokkasho Reprocessing Plant, the cooling system at one of the tanks storing high-level radioactive liquid waste stopped for about eight hours on the second of this month, and JNFL was investigating the cause.

There are two systems of piping for circulating cooling water, and as a result of the investigation, it was revealed at the press conference that there is a high possibility that workers mistakenly closed the valve of the piping in operation, when they were instructed to close the piping under construction.

According to JNFL, the valves were not clearly labeled and instructions were given only orally. JNFL said that it will take measures by the end of this month, such as attaching tags to valves in more than 500 locations in the building where the trouble occurred, so that the status of the system and valves open and closed can be identified.

JNFL has informed the Nuclear Regulation Authority and the local government of the results of the investigation and measures to prevent recurrence. We have strongly requested that JNFL take all possible safety measures, and the village will continue to closely monitor the response.
https://www3.nhk.or.jp/news/html/20220719/k10013725711000.html?fbclid=IwAR1JCD1htc96PAjbz9jJ3Zn7SKjRBvKTuL1akwhNLcdRkRH5J0fsUzTp7zM

Advertisement

July 22, 2022 Posted by | Japan | , , , | Leave a comment

Aomori wants reassurance that it won’t be final nuclear waste site



Aomori Gov. Shingo Mimura (left) and Chief Cabinet Secretary Katsunobu Kato (right) attend a meeting of a council for nuclear fuel cycle policy held at the Prime Minister’s Office Wednesday.

Oct 21, 2020

Aomori Prefecture on Wednesday urged the government to reconfirm its policy of not building in the prefecture a facility for the final disposal of high-level radioactive waste from nuclear power plants across the nation.

The request was made during a meeting of a council for discussions on issues related to the country’s nuclear fuel cycle policy between relevant Cabinet ministers and officials of the prefecture, where a spent nuclear fuel reprocessing facility is under construction. It was the first meeting of the council since November 2010.

At the day’s meeting, the Aomori side called on Prime Minister Yoshihide Suga’s Cabinet, launched last month, to maintain the promise not to make the prefecture a final disposal site, upheld by past administrations.

Participants in the meeting, held at the Prime Minister’s Office in Tokyo, included Chief Cabinet Secretary Katsunobu Kato and industry minister Hiroshi Kajiyama from the central government, and Aomori Gov. Shingo Mimura.

“It’s necessary for the state and the operator (of the reprocessing plant) to make the utmost efforts to promote, with support from Aomori, the nuclear fuel cycle policy, including the launch of the plant,” Kato said at the start of the meeting.

Mimura told reporters after the meeting that he asked the central government to abide by the promise and promote the nuclear fuel cycle policy, in which uranium and plutonium are extracted from spent fuel and reprocessed into fuel for use at nuclear power plants.

Mimura indicated that Kato showed the state’s understanding of his requests.

In July, the central government’s Nuclear Regulation Authority concluded that the basic design of the nuclear fuel reprocessing plant in the Aomori village of Rokkasho meets the country’s nuclear safety standards, which were crafted after the March 2011 accident at Tokyo Electric Power Company Holdings Inc.’s tsunami-stricken Fukushima No. 1 nuclear plant.

Japan Nuclear Fuel Ltd. aims to complete the plant in fiscal 2022. The NRA spent over six years screening the Rokkasho facility’s design.

Following the NRA’s conclusion, the Aomori side asked the state to hold a meeting of the nuclear fuel cycle policy council.

Aomori has agreed to accept spent nuclear fuel from nuclear plants across the country on the condition that a final disposal facility is not constructed in the prefecture.

The central government regards the nuclear fuel cycle as a pillar of its nuclear energy strategy.

Besides the reprocessing plant, a facility to make mixed oxide, or MOX, fuel from extracted uranium and plutonium is also under construction at the same site in Rokkasho.

https://www.japantimes.co.jp/news/2020/10/21/national/japan-aomori-nuclear-waste-disposal/

October 26, 2020 Posted by | Japan | , , | Leave a comment

Pro-nuclear incumbent Shingo Mimura wins fifth term in Aomori gubernatorial election

Distance from Fukushima to Aomori is 342 kilometers northward. This air travel distance is equal to 213 miles. Those people haved learned nothing from their Fukushima neighbors.
n-aomori-a-20190603-870x662
Aomori Gov. Shingo Mimura (center) raises his hands in the city of Aomori on Sunday after being predicted to win Sunday’s gubernatorial election
June 3, 2019
AOMORI – Shingo Mimura, a pro-nuclear incumbent, won his fifth term in the Aomori gubernatorial election on Sunday, stressing his past achievements and focusing away from the area’s involvement in the country’s nuclear fuel recycling policy during campaigning.
 
Mimura, 63, backed by the local chapter of the ruling Liberal Democratic Party and its coalition partner, Komeito, defeated 65-year-old dentist Wakako Sahara, who was supported by opposition parties.
 
The incumbent garnered 329,048 votes, against 105,466 votes collected by Sahara. Voter turnout stood at 40.08 percent.
 
The prefecture hosts a cluster of nuclear facilities, including an incomplete plant in Rokkasho where spent uranium fuel will be reprocessed for recycling.
 
During the 17-day official campaigning, Mimura touted his role in having expanded agricultural exports and promoted administrative reforms, while mostly avoiding discussion of the controversial nuclear policy.
 
Aomori Prefecture received about ¥20 billion in nuclear fuel tax income from nuclear facility operators in fiscal 2017, accounting for about 11 percent of the prefecture’s annual tax revenue.
 
A person involved in Mimura’s campaign said there were many residents in Aomori Prefecture who did not want the nuclear issue to be the focus of the election as they financially benefit from having the fuel recycling facilities there.
 
Sahara, who opposes nuclear power generation, criticized Mimura for promoting the central government’s nuclear power policy, but was unable to gain broad support from voters.

June 10, 2019 Posted by | Japan | , | Leave a comment

Tohoku Electric says donation not a payoff for idle nuclear plant

safe_image.php.jpg
Tohoku Electric Power Co.’s Higashidori nuclear power plant in Aomori Prefecture, which has been idled since the 2011 Fukushima nuclear disater
March 20, 2019
Tohoku Electric Power Co. plans to give an estimated 400 million yen ($3.58 million) to a village that hosts one of its nuclear power plants, but denies it is compensation for losses stemming from the facility’s suspension since the 2011 Fukushima nuclear disaster.
The utility said March 19 it will make a donation to Higashidori, Aomori Prefecture, where its Higashidori nuclear power plant is located, through a corporate version of the “furusato nozei” (hometown tax payment) system.
The company did not disclose the amount, but only said it wants to donate “about half” the maximum amount that the village is allowed to receive under this system. The ceiling for the village is about 800 million yen.
 
… Satoshi Shimoyashiki, vice manager of Tohoku Electric’s Aomori branch, rejected the notion that the donation was meant as compensation for such economic losses and emphasized that it is being made as “part of corporate social responsibility (CSR).”
“We decided to provide this form of cooperation because co-prosperity with local communities has been part of our management philosophy since the founding of our company,” Shimoyashiki told reporters at the Aomori prefectural government building.
“We believe that Tohoku Electric decided to support the village’s regional revitalization projects,” said Higashidori Mayor Yasuo Echizen….
 
… The furusato nozei system allows individuals to divert part of their local tax payment to a local government of their choice. In return, many of those governments send local specialties to donors.
Its corporate version allows companies to reduce their corporate and other tax payments if they donate to projects of local governments.
Read more:

March 25, 2019 Posted by | Japan | , | Leave a comment

Extended screening pushes back MOX fuel plant construction for 3rd time

Oma Npp, Aomori.jpg
Sep 4, 2018
AOMORI – Construction in Aomori Prefecture of the world’s first commercial reactor to operate solely on plutonium-uranium mixed oxide fuel will be pushed back for the third time due to prolonged safety checks, the utility building the reactor said Tuesday.
Electric Power Development Co. had been planning to begin construction of major facilities at the Oma nuclear power plant in the prefecture during the latter half of this year, but told the Oma Municipal Assembly on Tuesday it has decided to delay the work by about two years. The delay means the new target for the reactor to begin operations is fiscal now 2026.
The move clouds the course of Japan’s policy for the nuclear fuel cycle, in which the reactor was supposed to play a key role. Mixed oxide (MOX) fuel is produced by extracting plutonium from spent nuclear fuel and mixing it with uranium. Tokyo is also under international pressure to slash its stockpile of plutonium, which has the potential to be used to produce nuclear weapons.
“We would like Electric Power Development to put top priority on safety and respond appropriately to the Nuclear Regulation Authority’s screening,” industry minister Hiroshige Seko said at a news conference.
The company, also known as J-Power, initially sought to start operations at the nuclear plant, to be located in the Aomori town of Oma with an output of 1.38 million kilowatts, in fiscal 2021, but put it back by one year in 2015 and then postponed it to fiscal 2024 in 2016.
Oma Npp, Aomori2.jpg
Construction of the reactor began in 2008 after gaining state approval, but was stalled following the nuclear meltdowns at the Fukushima No. 1 power plant triggered by the 2011 earthquake and tsunami disaster.
About 40 percent of the construction has been completed, but work so far has centered on setting up office buildings and conducting road repairs.
J-Power applied for safety checks in December 2014, but NRA examinations have focused on assumptions about tsunami and earthquake risk at the overall complex and not at its nuclear facilities. An official at the company told the Oma Municipal Assembly that it may take two more years for the reactor to pass the screening.
J-Power said it hopes to start construction of the reactor and other facilities in the latter half of 2020 and complete it by the second half of 2025.
“It’s very regrettable that the project will be postponed once again. I hope (J-Power) will strive to swiftly pass the screening and help revitalize the regional economy,” Oma Mayor Mitsuharu Kanazawa said at the assembly meeting after hearing from the company official.
The Oma plant has also faced lawsuits seeking suspension of the project.
Residents in Hakodate, Hokkaido, which is some 23 kilometers northwest of Oma across the Tsugaru Strait, filed a lawsuit against the company and the central government with the Hakodate District Court in July 2010, claiming they are concerned about the large amount of highly toxic plutonium that will be used as reactor fuel.
The city of Hakodate also filed suit against the two parties with the Tokyo District Court in April 2014, saying it fears the impact of an accident at a so-called full-MOX reactor will be far more devastating than that of the Fukushima disaster, which led to the long-term evacuation of many local residents.

September 6, 2018 Posted by | Japan | , , , , | Leave a comment

Proposed storage of spent nuclear fuel sparks resistance in Aomori Pref. City

Recyclable Fuel Storage Co interim storage facility mutsu, Aomori Prefecture.jpg
The Recyclable-Fuel Storage Co. interim storage facility is seen fenced off in Mutsu, Aomori Prefecture, on March 6, 2018
March 22, 2018
The selection of a site to house an interim storage facility for spent fuel from nuclear power plants operated by Kansai Electric Power Co. (KEPCO) has run into rough waters. In January, the Aomori Prefecture city of Mutsu surfaced as a candidate, but resistance quickly emerged from locals.
 
With KEPCO’s nuclear power plants being concentrated in Fukui Prefecture, the prefectural government has set a basic premise of storing spent nuclear fuel outside the prefecture. The utility aims to announce a candidate site this year, but there remains fierce opposition to accepting nuclear fuel from other prefectures, and because of this, its prospects of settling on a site are unclear.
 
After a 20-minute drive along a national route from central Mutsu during a visit by the Mainichi Shimbun in early March, an imposing fence could be seen along a snowy field. Beyond the fence was a square building — an interim storage facility that is being built by Recyclable-Fuel Storage Co. (RFS), a company founded by Tokyo Electric Power Company Holdings, Inc. and Japan Atomic Power Co. The facility’s storage capacity is around 3,000 tons of spent fuel. There are plans to build a second building in the future.
 
In January, this facility gained nationwide attention. As the Nuclear Regulation Authority (NRA) came to the final stage of its screening of the facility, news organizations reported that KEPCO was considering transporting spent nuclear fuel from its plants to the facility.
 
Mutsu Mayor Soichiro Miyashita immediately held a news conference, saying he had heard no such thing from the central government, KEPCO, or RFS. “The feelings of the region are being completely ignored,” he said.
 
In an interview with the Mainichi Shimbun on March 6, Miyashita suggested it was unlikely KEPCO would bring its nuclear fuel into the facility as things stand. “Operations at the site haven’t started yet. Without the facility having cleared the NRA’s screening, it’s unthinkable that they could change the status quo,” he said.
 
The Shimokita Peninsula in northern Aomori Prefecture, where the city of Mutsu is located, not only houses the interim storage building, but has a collection of other nuclear facilities including the Higashidori Nuclear Power Plant in the Aomori Prefecture village of Higashidori, the Oma Nuclear Power Plant in the town of Oma and the reprocessing plant for spent nuclear fuel in the village of Rokkasho. But since the outbreak of the Fukushima nuclear disaster in March 2011, construction of nuclear facilities has been suspended or delayed.
 
“We had expected our nonresident population to increase in line with nuclear power plant construction and inspections. But taxi companies are going out of business, and the economic chill is severe,” Miyashita said.
 
Alongside concerns about the storage of nuclear fuel, there are also deeply rooted aspirations regarding the operation of nuclear power plants in the region. Katsura Sonoda, head of the Mutsu Chamber of Commerce and Industry, commented, “In local economic circles, there is little resistance to reactivating nuclear power plants, and we want the interim storage facility to go into operation quickly. Fixed property taxes and subsidies will also increase.
 
A figure in the energy industry commented, “The mayor is up for election for a second term in June. It’s not the case that he lacks understanding of nuclear power-related projects; I guess it’s just that he had to be sensitive toward antinuclear public sentiment in the wake of the nuclear disaster (in Fukushima).”
 
In late January, KEPCO announced that it would set up an office in Aomori in June to handle payment-related issues, employing about 70 people. A public relations representative for the company maintained that this had nothing to do with the interim storage facility, but this has not swept away the view that the company is entering Aomori Prefecture to warm the region to the idea of hosting the facility.
 

March 22, 2018 Posted by | Japan | , , , , | Leave a comment

KEPCO studying moving spent nuclear fuel from Fukui to Aomori

kjiok).jpg
Kansai Electric Power Co. is considering transferring spent nuclear fuel stored in its three nuclear plants in Fukui Prefecture to an intermediate storage facility in Aomori Prefecture, sources said on Jan. 6.
KEPCO had promised to move the fuel outside the prefecture when the Fukui prefectural government allowed the utility to restart two reactors at its Oi nuclear power plant.
KEPCO President Shigeki Iwane has said that a facility will be secured by the end of 2018 to accept the fuel.
According to the sources, KEPCO is also considering other locations. However, the intermediate storage facility, located in Mutsu in northern Aomori Prefecture, is a promising candidate because it has already been constructed.
However, since consent from local governments is required, KEPCO could face difficulties in transferring the fuel to the facility.
At present, KEPCO is storing spent nuclear fuel, which is produced in its Takahama, Oi and Mihama nuclear power plants in Fukui Prefecture, in pools in their compounds. However, about 70 percent of the capacity of those pools have been filled.
If the restarts of the reactors in the plants proceed as expected, the remaining 30 percent will also be filled in about seven years. Therefore, KEPCO is trying to secure an intermediate storage facility to temporarily store the fuel by putting it in metal containers.
The intermediate storage facility in Mutsu was jointly constructed by Tokyo Electric Power Company Holdings Inc. and Japan Atomic Power Co. at a cost of about 100 billion yen ($884.6 million) to store spent nuclear fuel produced by their nuclear plants.
However, acceptance of the fuel from those plants has yet to start because the facility is currently undergoing screenings to see if it is in compliance with new safety standards introduced after the 2011 Fukushima nuclear disaster.
The intermediate storage facility has a capacity of accepting a total of 5,000 tons of spent nuclear fuel.
KEPCO is considering securing storage space there by purchasing part of the shares of a company that will operate the facility.

January 8, 2018 Posted by | Japan | , , , , , , | Leave a comment