Insights into Construction Delays at the Vogtle Nuclear Plant: Primary Sources of Delay Identified by the Independent Construction Monitor

The first new reactors built in the United States in decades—two Westinghouse
AP1000s, Units 3 and 4, at the Vogtle plant in Georgia that started
commercial operations in 2023 and 2024—took more than twice the estimated
time to construct and at more than double the cost.
This experience raises
questions about nuclear power’s economic viability and therefore its role
in the energy transition and energy diversification. To better understand
what went wrong so utilities and reactor consortia can reduce the chances
of such consequential delays in future US reactor builds, the authors
examined testimonies by Vogtle’s independent construction monitor (ICM).
The ICM, Dr. William R. Jacobs Jr., reviewed the project’s progress and
any issues impacting schedule or cost. Jacobs had a unique vantage point
into the unfolding debacle throughout the process, and assessed that the
project’s three primary sources of delay were the following: Vogtle Units
3 and 4 lacked a realistic, achievable schedule.
The integrated project
schedule (IPS) used to manage the project and estimate commercial operation
dates was both incomplete and based on incorrect or unrealistic
assumptions. Private entities involved in the project failed to adhere to
the stringent quality assurance requirements of the US Nuclear Regulatory
Commission (NRC). In particular, the use of a new facility in Lake Charles,
Louisiana, with no previous nuclear-grade manufacturing experience created
lasting problems. Westinghouse lacked sufficient design completion at the
start of the project and the design changed during construction.
Both factors adversely impacted procurement and construction and the changes led
to licensing conflicts between what the NRC had certified and what the
consortium built.
Center on Global Energy Policy 15th Nov 2026, https://www.energypolicy.columbia.edu/publications/insights-into-construction-delays-at-the-vogtle-nuclear-plant-primary-sources-of-delay-identified-by-the-independent-construction-monitor/
No comments yet.
-
Archives
- November 2026 (201)
- October 2026 (302)
- September 2026 (339)
- August 2026 (330)
- July 2026 (355)
- June 2026 (287)
- May 2026 (306)
- April 2026 (356)
- March 2026 (251)
- February 2026 (267)
- January 2026 (308)
- December 2025 (358)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS





Leave a Reply