Ontario Power Generation (OPG) Acknowledges the West’s First SMR is Behind Schedule

Immature reactor engineering and stretched GE Hitachi resources threaten Darlington’s cost and schedule.
Decouple 10th Nov 2026
Ontario Power Generation (OPG) has acknowledged that “DNNP Unit 1 is no longer expected to achieve the previously disclosed commercial operation date target of October 2030 or be completed within the previously disclosed estimated cost of $7.7 billion.”
OPG explicitly identifies unfinished engineering by GE Vernova Hitachi as the primary contributing factor going on to say…
“This reflects GE Vernova Hitachi (GEVH) Nuclear Energy’s ongoing engineering for its first-of-a-kind SMR, which has impacts on construction execution and supply chain performance.”
OPG has not yet provided updated cost or schedule estimates indicating the extent of the anticipated budget increase or delay. According to CEO Nicolle Butcher, the assessment informing these revised estimates is expected to be substantially complete by mid-2027.
What can be inferred is that detailed engineering is falling behind construction, causing costly delays, rework, and lost productivity. These pressures are compounded by the departure of several senior engineers at a critical stage of the project, when GVH’s already stretched engineering resources are needed most.
Meanwhile, GVH is pursuing an expanding portfolio of projects, including Clinch River in Tennessee, where TVA aims to begin construction with a design more than 95 percent complete and benefit directly from lessons learned at Darlington. Ontario is thus absorbing the risks of pioneering the first BWRX-300 while the vendor prepares to deliver its successors.
The admission exposes a troubling Canadian vulnerability. Having committed billions to pioneering an American reactor design, Ontario now depends on a foreign vendor whose scarce engineering resources are being pulled in competing directions.
The question is whether Queen’s Park and Ottawa can use the considerable financial and commercial leverage at their disposal to demand that GE Hitachi prioritize the engineering resources needed to get Darlington back on track, and whether Ontario will repeat this mistake as it weighs another American reactor design, the AP1000, for its next generation of large nuclear plants.
The Engineering Challenge Behind Darlington’s Delays
The BWRX-300 was sold on the promise of simplicity. At 300 megawatts, its smaller output, passive safety systems and simplified configuration were supposed to avoid the complexity that has plagued large Western nuclear construction projects.
For decades, the nuclear industry developed progressively larger reactors from proven designs. Scaling down was expected to be easier, but the BWRX-300 may be challenging that assumption. The physics of boiling water, coolant circulation and heat transfer do not scale neatly with reactor dimensions. Although the BWRX-300 draws on decades of GE boiling water reactor experience, its integrated design is new. Translating it into thousands of coordinated engineering specifications, fabrication drawings and installation instructions is proving an enormous undertaking.
Construction becomes especially unforgiving when engineering falls behind. A late change to a seismic calculation can require modifications to structural supports, piping routes and equipment layouts. Engineers must revisit interconnected analyses while construction teams decide whether to proceed at the risk of expensive rework or stand idle awaiting finalized designs.
Experienced engineers are particularly valuable at this stage. Their familiarity with the design’s evolution, regulatory commitments, and complex interfaces cannot be readily replaced by adding inexperienced personnel. Yet GVH has been losing precisely this sort of expertise……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………….
Are We About to Make the Same Mistake Again?
Ontario is considering the American AP1000 for its next generation of large nuclear reactors, competing against Canadian CANDU technology. Yet the vulnerabilities emerging at Darlington could recur if Canada finds itself competing with an ambitious American nuclear construction program for scarce engineering resources…………………………………………………………………………………………………………….
There are also unresolved questions about AP1000 design maturity. Westinghouse has updated its standard design to incorporate lessons from Vogtle, but thousands of field modifications and change orders must be reconciled with engineering calculations, three-dimensional models and fabrication drawings to produce a repeatable, construction-ready design.
How much of Vogtle’s engineering has been incorporated into that package? And does Westinghouse have the experienced personnel to adapt it for Canadian requirements while meeting its expanding American and international commitments?
These questions deserve serious scrutiny before Ontario commits billions more to a second American vendor facing competing demands from Washington’s own nuclear ambitions.
The Larger Lesson for Canada
………………………………………………………………………………………………….. The larger lesson concerns the next generation of nuclear construction. Canada has already assumed extraordinary first-of-a-kind risks to establish an American reactor design as an international commercial product. We cannot afford to repeat this arrangement with the Westinghouse AP1000, committing billions of dollars and decades of energy planning to foreign vendors whose scarce engineering resources and strategic priorities ultimately lie elsewhere………………… https://www.decouple.media/p/opg-acknowledges-the-wests-first
No comments yet.
-
Archives
- November 2026 (162)
- October 2026 (302)
- September 2026 (339)
- August 2026 (330)
- July 2026 (355)
- June 2026 (287)
- May 2026 (306)
- April 2026 (356)
- March 2026 (251)
- February 2026 (267)
- January 2026 (308)
- December 2025 (358)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS






Leave a Reply