Second review of ARC’s Small Modular Nuclear Reactor not complete, despite layoffs

That’s after ARC Clean Technology Canada said it downsized with that review now over

Telegraph Journal, Adam Huras, Jul 04, 2024 

A second design review of a New Brunswick-based company’s proposed small modular nuclear reactor is not yet complete, according to the Canadian Nuclear Safety Commission.

That’s after ARC Clean Technology Canada said it downsized with that review now over.

Brunswick News reported last month that ARC, one of two companies pursuing SMR technology in the province, had handed out layoff notices to some of its employees, citing its latest design phase coming to an end.

That’s as its CEO also departed.

But the Canadian Nuclear Safety Commission says it’s “months” away from completing its review, and may need more information from the company.

“We have received all of ARC’s major submissions as part of the vendor design review process and our experts are carefully reviewing them,” commission spokesperson Braeson Holland told Brunswick News.

“It is possible that staff will have additional questions for the vendor. In that case, additional information may be requested, and the company will be expected to provide it for the vendor design review to proceed.

“Provided that any additional information requested is submitted in a timely manner and that the company remains in compliance with its service agreement with the Canadian Nuclear Safety Commission, we anticipate that the review will be complete within several months.”

A vendor design review is an optional service that the commission provides for the assessment of a vendor’s reactor design.

The objective is to verify, at a high level, that Canadian nuclear regulatory requirements and expectations, as well as Canadian codes and standards, will be met.

The company did complete a Phase 1 review of its ARC-100 sodium-cooled fast reactor in October 2019.

An executive summary of that review, made public by the commission, noted that there were requests for additional information, as well as technical discussions through letters, emails, meetings and teleconferences, after an initial submission.

The result of that first review found that “additional work is required by ARC” to address findings raised in the review, specifically around the reactor’s management system.

It then lists a series of technical concerns, but concludes that “these issues are foreseen to be resolvable.”

A Phase 2 design review, which ARC is undergoing right now, goes into further detail, and focuses on identifying fundamental barriers to licensing for a new design in Canada, according to the commission.

That review started in February 2022, and was expected to be completed in January of this year.

It’s unclear why it has yet to be completed.

At a New Brunswick Energy and Utilities Board hearing last month into a recent power rate hike, NB Power vice president Brad Coady testified he doesn’t expect SMRs will be ready by an original target date of 2030.

The utility now believes they’ll be ready by 2032 or 2033……………….
https://tj.news/new-brunswick/second-review-of-arcs-smr-not-complete-despite-layoffs

July 7, 2024 - Posted by | Canada, Small Modular Nuclear Reactors

No comments yet.

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.