nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

The Robot Probe Cannot Confirm Where is the Melted Fuel of Unit 1

24 03 2017.jpg

 

Tokyo Electric Power Company announced on February 23 that it had completed a robot probe survey lasting five days in the reactor containment vessel of Fukushima Daiichi nuclear power plant Unit 1.

Its goal was to confirm the whereabout of the melted nuclear fuel, but it was blocked by piping and could not put the camera in athe place where nuclear fuel could be seen.

Information necessary for taking out the nuclear fuel to decommission the reactor remains inadequate, and some voices began to question the robot conducted investigation method.

During the 5-day survey, there was also a point where the measuring instrument with an camera and a radiation dosimeter integrated together was hung up in a range from 0 to 3 meters from the bottom of the containment vessel, pipes and debris blocking its path in many points. The radiation dose in the water is from 3.0 to 11 Sv. Per hour. It was not possible to directly check the melted nuclear fuel.

TEPCO and the country are facing the decommissioning of a furnace …

http://www.asahi.com/articles/photo/AS20170323005483.html

Advertisement

March 24, 2017 - Posted by | Fukushima 2017 | , , , ,

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: