Fukushima Decommissioning Safety Monitoring Council accepts the draft report as “safe”

July 26, 2022
In response to the Nuclear Regulation Commission’s approval of a plan to discharge treated water from TEPCO’s Fukushima Daiichi Nuclear Power Plant (Okuma and Futaba, Fukushima Prefecture) into the ocean by diluting it with seawater, the prefectural decommissioning safety monitoring council, consisting of prefectural governments and coastal municipalities, held a meeting at the prefectural office on July 26.
The committee approved a draft report by experts that concluded that “the safety of the surrounding areas will be ensured by the measures TEPCO has proposed.
The draft report evaluated that the measurement of radioactive material concentrations in the treated water and the safety measures for the seabed construction work were all properly planned. The report then sets forth eight requirements for TEPCO, including the dissemination of easy-to-understand information on radiation environmental impact assessments. The experts will complete the report by adding drawings, etc.
https://www.tokyo-np.co.jp/article/191904?rct=national&fbclid=IwAR3fpY_7qDRBsbWDd57FXnvI9EDBFA_WTlN7zzHzD_9ldK_hG8AgxSclWDM
High anxiety as Japan takes another step toward releasing wastewater from crippled Fukushima nuclear plant into sea

July 25, 2022
Tokyo — The fishing industry around Japan’s Fukushima coast expressed disappointment and resignation over the weekend as long-expected plans to start releasing treated wastewater into the ocean from the crippled Fukushima Daiichi nuclear power plant moved one step closer to reality. The drastic measure has been adopted as the only practical way out of a dilemma that’s plagued the damaged plant for more than a decade.
Late last week, Japan’s national nuclear regulator formally endorsed the plan to discharge more than 1 million tons of wastewater from the plant into the sea off Japan’s Pacific coast. The water will be filtered first to remove about 60 radioactive isotopes, with the exception of tritium, which can’t be extracted using existing technology.
After inspection and dilution with seawater, the water will be pumped out beyond Japan’s fishing zones through a 0.6-mile-long undersea tunnel, which will be carved through ocean bedrock starting near the Fukushima Daiichi plant’s reactor number 5.
The unprecedented, controversial disposal operation is likely to take decades.
Since the massive 2011 earthquake and tsunami triggered meltdowns in three of the plant’s reactors, operator Tepco has struggled to manage the vast amount of contaminated water — a combination of reactor cooling water, rainwater and groundwater, all irradiated as it flows through the highly-radioactive melted reactor cores – accumulating at the facility.
As a stopgap, the grounds surrounding the damaged reactors have been converted into a giant tank farm, with more than 1,000 storage vessels holding 1,310,000 tons of wastewater.
Tepco has long warned that it will run out of storage space as soon as spring 2023, and that the structures are hampering the technologically challenging work of decommissioning the plant. The temporary storage solution is also highly vulnerable to any future natural disasters.
In an effort to assuage concerns from neighboring countries, Japan sought a review by the International Atomic Energy Agency (IAEA). Last spring, IAEA Director General Rafael Mariano Grossi declared ocean disposal “both technically feasible and in line with international practice.”
He noted that normally functioning nuclear power plants (including in South Korea and China) regularly discharge wastewater into the sea, but he acknowledged “the large amount of water at the Fukushima plant makes it a unique and complex case.“
Before construction of the undersea tunnel can even begin, however, Tepco’s proposal must win backing from the regional government in Fukushima Prefecture and the two affected towns of Okuma and Futaba. A Fukushima fish processing company representative told the Asahi newspaper, “to be honest, even if we oppose this, I don’t feel like we have any chance of overturning the decision.”
After years of painstaking efforts to convince the Japanese public and the rest of the world that their seafood is safe, the local fishing industry fears the ocean release will tarnish their brand anew. Tokyo has promised to buy catches if the industry suffers reputational damage.
Of the 55 countries and regions that imposed restrictions on imported Japanese food after the Fukushima Daiichi catastrophe — including the U.S. — five (China, South Korea, Taiwan, Hong Kong and Macau) still have import bans in place.
Regulators solicited public comment and said they had received more than 1,200 responses, including people voicing concern over whether the undersea tunnel would be earthquake-safe, and what was being done to protect workers.
Tokyo has said levels of tritium — the one isotope that can’t be filtered out — will be diluted to below 1/40th of the allowable level for discharge in Japan, and 1/7th the WHO ceiling for drinking water.
Still, some experts have called for greater transparency, fearing unintended consequences of the operation. There is also concern about whether the discharge of enormous amounts of wastewater could set a bad precedent for dealing with future nuclear accidents.
TEPCO Approves Plan to Discharge Treated Water into Ocean, Focuses on Local Consent to Begin Construction
July 22, 2022
The Nuclear Regulation Authority (NRA) held an extraordinary meeting on July 22 and approved a plan for the offshore discharge of treated water from TEPCO’s Fukushima Daiichi Nuclear Power Plant (Okuma and Futaba, Fukushima Prefecture), finding no safety issues. TEPCO plans to begin full-scale construction of the discharge facilities after obtaining the consent of local authorities. TEPCO aims to begin discharging the water in the spring of next year.
TEPCO applied for the review in December 2021. According to the plan, the concentration of tritium, a radioactive substance, in the treated water will be diluted with a large amount of seawater so that it is less than 1/40th of the national standard, and discharged about 1 km offshore through a newly constructed undersea tunnel.

There is strong opposition to the discharge of treated water into the ocean, mainly from the fishing industry, which is concerned about harmful rumors.
https://www.tokyo-np.co.jp/article/191227?rct=national&fbclid=IwAR0s4gKwWiMVmlLjToo0VuL0vGPtINMOVFCmrO8hYvCHwUpQc6lQly8kgQc
Official approval for ocean discharge of “treated water” from Fukushima nuclear power plant…Undersea tunnel construction to begin next spring
On March 22, the Nuclear Regulatory Authority officially approved TEPCO’s plan to discharge “treated water” from the Fukushima Daiichi nuclear power plant into the sea, on the grounds that there are no safety concerns. Once prior approval from Fukushima Prefecture and the cities of Okuma and Futaba is obtained, TEPCO will begin construction of the facilities for the sea discharge. The government and TEPCO aim to start the discharge next spring.

July 22, 2022
On July 22, the Nuclear Regulation Authority (NRA) officially approved TEPCO’s plan to discharge the ever-increasing amount of “treated water” from TEPCO’s Fukushima Daiichi Nuclear Power Plant into the sea, saying there are no safety issues. TEPCO will now begin full-scale construction of facilities to discharge the water into the ocean after obtaining prior approval from Fukushima Prefecture and the towns of Okuma and Futaba in Fukushima Prefecture, where the plant is located. The government and TEPCO aim to begin the discharge next spring.
According to TEPCO’s plan, an undersea tunnel will be constructed from the plant to about 1 km/meters offshore, and treated water will be discharged from the top of the tunnel. The water will be diluted with seawater before discharge, and the concentration of radioactive tritium (triple hydrogen) will be reduced to less than 1/40th of the national discharge standard and 1/7th of the World Health Organization (WHO) standard for drinking water. The concentration of tritium in the water will be reduced to less than 1/40th of the national discharge standard and 1/7th of the World Health Organization’s drinking water standard.
The time required for the construction of the undersea tunnel and other work was initially estimated to be about 10.5 months, but will be shortened to about 8.5 months so that the discharge can begin next spring.
The treated water is produced by the ALPS (ALPS is a system for removing contaminated water after cooling nuclear fuel that has melted and hardened as a result of the 2011 meltdown accident). The amount of treated water continues to increase, and is currently about half of the total amount of radioactive materials in the plant. The amount of water has been increasing, and currently about 1.31 million tons are stored in more than 1,000 tanks on the plant’s grounds. The capacity of the tanks is expected to be reached by the end of next summer or fall. The tanks are expected to be full by next summer or fall.
Since continued storage would hinder decommissioning work, the government decided in April last year to begin discharging the waste into the ocean in the spring of 2011. It is expected to take several decades to complete the discharge.
The government and TEPCO need to provide more careful information.
The offshore discharge of “treated water” from TEPCO’s Fukushima Daiichi NPP is an unavoidable step to reduce the number of tanks on the plant site as much as possible and to facilitate the decommissioning of the plant. If decommissioning does not proceed steadily, it will hinder the reconstruction of Fukushima.
The treated water is water that has been purified from the contaminated water at the plant and most of the radioactive materials have been removed. Although tritium is technically difficult to remove, it has been scientifically confirmed that tritium has no effect on humans or the environment if it is diluted and its concentration is reduced. Tritium is also generated in the normal operation of nuclear power plants, and its release to the sea is permitted in Japan and other countries.
In April this year, the International Atomic Energy Agency (IAEA), which includes experts from China and South Korea who oppose the release of treated water, released a report on the safety of TEPCO’s plans and purification facilities after studying them. The report found no problems with safety.
Nevertheless, concerns about harmful rumors persist, and local fishermen are opposed to the ocean discharge. In May of this year, after the Regulatory Commission approved a draft review report summarizing the results of its examination, it solicited opinions from the general public. As a result, 1,233 opinions were received, many of them from people who questioned the safety of the plant. The government and TEPCO need to further disseminate information carefully and seek the understanding of the public as a whole. (Makio Hattori, Science Department)
https://www.yomiuri.co.jp/science/20220722-OYT1T50110/?fbclid=IwAR1vstNjc7PCvVofMs-9yAA5GBKitGS0BkJPJw1-x62lwBfAt-0ghm-Ly6A
Regulatory Commission to Approve Plan for Ocean Discharge of Treated Water on 22nd, TEPCO Fukushima Daiichi Nuclear Power Plant
July 20, 2022
The Nuclear Regulation Authority (NRA) announced on July 20 that it will discuss at an extraordinary meeting on July 22 a draft review report on TEPCO’s plan to discharge contaminated water from the Fukushima Daiichi Nuclear Power Plant after purification and treatment, stating that the plan has no safety problems and meets the requirements of government policy. Based on the results of a public comment period, the committee is expected to decide on the review report and approve the plan.
According to the Regulatory Commission, it received approximately 1,200 comments from the public during the period from May 19 to June 17. The Regulatory Commission will also present its views on the opinions at the meeting.
According to the plan, the treated water, which is mainly tritium, will be diluted with a large amount of seawater to less than 1/40th of the national discharge standard, and then discharged through a newly constructed undersea tunnel about 1 km offshore. More than 1.3 million tons of the treated water is stored in tanks on the plant’s premises, and TEPCO plans to finish releasing it over a period of about 30 years starting next spring.
TEPCO is preparing for the construction of the tunnel by installing a shield machine to excavate the tunnel on a site near the seawall of the plant. Tunnel excavation can only begin after receiving approval from the Regulatory Commission and obtaining the consent of Fukushima Prefecture and the two towns of Okuma and Futaba, where the plant is located.
Fishermen and fishermen are strongly opposed to the release of treated water. (Shinichi Ogawa and Kenta Onozawa)
Processed water at the Fukushima Daiichi Nuclear Power Plant Contaminated water generated when cooling water injected into the reactors of Units 1-3 came into contact with nuclear fuel debris that melted down in the accident and mixed with groundwater and rainwater that flowed into the buildings, and was purified by a multinuclide removal system (ALPS). Tritium, a radioactive substance that cannot be removed, remains in concentrations exceeding the national discharge standard. In April 2021, the government decided to discharge the treated water into the ocean by the spring of 2023. TEPCO is proceeding with a plan to use a large amount of seawater to dilute the tritium concentration to less than 1/40th of the discharge standard and discharge the water into the sea.
https://www.tokyo-np.co.jp/article/190829?fbclid=IwAR39Bvgz0pCGmfeTUIeMKiljEVAZgDWOVGRMwAnP2O_mbbKL9LlaUbwt40w
The Pacific faces a radioactive future
11th July 2022
Japan plans to dump radioactive water from Fukushima into the Pacific Ocean, but its effects on Pacific nations are not clear.
When the earthquake and tsunami hit Fukushima, Japan in 2011, it resulted in the tragic death of many people, and severe damage to a nuclear power plant, which required a constant flow of cooling water to prevent further catastrophe. More than 1.3 million tonnes of radionuclide-contaminated water have now been retained on-site. The Fukushima plant operator, Tokyo Electric Power Company (TEPCO), with the approval of the Japanese Government, plans to begin releasing this water into the Pacific Ocean starting next year. But compelling, data-backed reasons to examine alternative approaches to ocean dumping have not been adequately explored.
Claims of safety are not scientifically supported by the available information. The world’s oceans are shared among all people, providing over 50 percent of the oxygen we breathe, and a diversity of resources of economic, ecological and cultural value for present and future generations. Within the Pacific Islands in particular, the ocean is viewed as connecting, rather than separating, widely distributed populations.
Releasing radioactive contaminated water into the Pacific is an irreversible action with transboundary and transgenerational implications. As such, it should not be unilaterally undertaken by any country. The Pacific Islands Forum, which meets on July 12, has had the foresight to ask the relevant questions on how this activity could affect the lives and livelihoods of their peoples now and into the future. It has drawn on a panel of five independent experts to provide it with the critical information it needs to perform its due diligence.
No one is questioning the integrity of the Japanese or International Atomic Energy Agency (IAEA) scientists, but the belief that our oceans’ capacity to receive limitless quantities of pollutants without detrimental effects is demonstrably false. For example, tuna and other large ocean-going fish contain enough mercury from land-based sources to require people, especially pregnant women and young children, to limit their consumption. Tuna have also been found to transport radionuclides from Fukushima across the Pacific to California. Phytoplankton, microscopic plant-like life that floats free in the ocean, can capture and accumulate a variety of radioactive elements found in the Fukushima cooling water, including tritium and carbon-14. Phytoplankton is the base for all marine food webs. When they are eaten, the contaminants would not be broken down, but stay in the cells of organisms, accumulating in a variety of invertebrates, fish, marine mammals, and humans. Marine sediments can also be a repository for radionuclides, and provide a means of transfer to bottom-feeding organisms.
The justification for dumping is primarily based on the chemistry of radionuclides and the modelling of concentrations and ocean circulation based on assumptions that may not be correct. It also largely ignores the biological uptake and accumulation in marine organisms and the associated concern of transfer to people eating affected seafood. Many of the 62-plus radionuclides present in the Fukushima water have long periods over which they can cause harmful effects, called half-lives, of decades to millennia. For example, Cesium-137 has a half-life of 30 years, and Carbon-14, more than 5,700 years. Issues like this really do matter, as once radioactive materials enter the human body, including those that release relatively low-energy radiation (beta particles), they can cause damage and increase the risk of cancers, damage to cells, to the central nervous system and other health problems.
The Fukushima nuclear disaster is not the first such event, and undoubtedly won’t be the last. The challenges of cleaning-up, treating and containing the contaminated cooling water is also an opportunity to find and implement safer and more sensible options and setting a better precedent to deal with future catastrophes. The Pacific region and its people have already suffered from the devastation caused by United States, British and French nuclear testing programmes. Documented problems have led to international agreements to curtail such testing. In this case, the members of the Pacific Islands Forum are key stakeholders that are finding a unified voice against the planned dumping of radionuclides and other pollutants into the ocean that surrounds their homes, and holds their children’s futures.
The world’s oceans are in trouble and experiencing mounting stress from human-induced impacts tied to global climate change, overfishing, and pollution, with consequential cumulative effects on living resources and the people who depend on them. Pollution, particularly from land-based sources, is one of the greatest threats and challenges to ocean resource sustainability and associated elements of human health.
Japan and TEPCO plan to begin dumping radioactively contaminated water into the Pacific Ocean in 2023. A more deliberative and prudent approach would adhere to the precautionary principle – that if we are not sure no harm will be caused, then we should not proceed. The rush to dilute and dump is ill-advised and such actions should be postponed until further due diligence can be performed. Sound science, and a much more careful consideration of the alternatives, and respect for the health and well-being of the peoples of the Pacific region, all demand it. Far better and transparent communications are needed to provide accurate and adequate information for leaders, resource managers and stakeholders to use in their deliberations on the way forward. If the Island nations lead, other nations are sure to follow.
Robert H. Richmond, PhD is a Research Professor and Director of the Kewalo Marine Laboratory, University of Hawaii at Manoa. He is also a Pew Fellow in Marine Conservation, Aldo Leopold Fellow in Environmental Leadership and Fellow of the International Coral Reef Society. He is part of the advisory panel to the Pacific Islands Forum on the Fukushima dumping, who funded this research. He gratefully acknowledges the contributions of the other panel members, Dr Arjun Makhijani, Dr Ken Buesseler, Dr Ferenc Dalnoki Veress, and Dr Tony Hooker.
https://www.bignewsnetwork.com/news/272615799/the-pacific-faces-a-radioactive-future
New Chairman of All Fishermen’s Federation “firmly opposed” to discharge of treated water The person who agreed to an interview at METI was… a retired counselor, not a minister

June 27, 2022
Masanobu Sakamoto, chairman of the National Federation of Fishermen’s Associations (ZENYOREN), visited the Ministry of Economy, Trade and Industry (METI) on June 27 for the first time since becoming chairman, and handed a special resolution to Akira Matsunaga, counselor at METI, stating “firm opposition” to the ocean discharge of water contaminated from the Fukushima Daiichi Nuclear Power Plant (Okuma-cho and Futaba-cho, Fukushima Prefecture), which is mainly radioactive tritium, after purification and treatment.
Sakamoto is the chairman of the Chiba Prefectural Fisheries Federation, and was recently appointed chairman of the All Fisheries Federation at its general meeting on March 23. Meanwhile, Mr. Matsunaga, who responded to the letter, is a former director general of the Japan Patent Office who was involved in post-nuclear power plant reconstruction at the Cabinet Office and the Agency for Natural Resources and Energy, but retired at the end of March this year to become a part-time counselor.
According to METI, the meeting with Minister Koichi Hagiuda did not take place because he could not adjust his schedule in time. Immediately after the interview, the ministry monitor showing Hagiuda’s schedule was marked “meeting.
Sakamoto said at the meeting, “Regardless of the replacement of the chairman, we will remain opposed to the proposal,” and called for the creation of a fund for the continuation of the fishing industry, such as support for fuel costs for fishing boats, in addition to the fund for reputational damage measures and other measures budgeted by the government.
Mr. Matsunaga said, “The entire ministry will work together to present effective and concrete measures.
After the meeting, Mr. Sakamoto responded to media interviews, saying, “Eleven years ago, when the accident occurred in Chiba Prefecture, I myself suffered from severe reputational damage. Based on my own experience, I cannot condone (the release of radioactive materials into the ocean). As for not being able to meet with Mr. Hagiuda, he said, “Naturally, I would like to meet with the minister as soon as possible and convey my thoughts directly to him. (Kenta Onozawa)
Contaminated water generated when cooling water injected into reactors No. 1 through No. 3 at the Fukushima Daiichi Nuclear Power Plant comes into contact with nuclear fuel debris that melted down in the accident and mixes with groundwater and rainwater that has flowed into the buildings. Tritium, a radioactive substance that cannot be removed, remains in concentrations exceeding the national discharge standard. In April 2021, the government decided to discharge the treated water into the ocean by the spring of 2011. TEPCO is proceeding with a plan to use a large amount of seawater to dilute the tritium concentration to less than 1/40th of the discharge standard and discharge the water into the sea.
https://www.tokyo-np.co.jp/article/186025?fbclid=IwAR3Fw9AOVsfvzCZumK6LhzD__csp1hPC0YdUNksj9lPYN5AxPgj6152zM5E
All fishermen’s federation “opposition to discharge will remain unchanged” Special resolution on treated water from nuclear power plant
June 23, 2022
The National Federation of Fishermen’s Associations (ZENYOREN) held an ordinary general meeting in Tokyo on June 23, and unanimously adopted a special resolution stating that it remains “firmly opposed” to the ocean discharge of treated water from TEPCO’s Fukushima Daiichi Nuclear Power Plant. This is the third resolution opposing the ocean discharge.
The resolution pointed out that the government’s April response to a request from the Federation of Fishermen’s Associations at the time of the decision to discharge nuclear fuel into the ocean lacked specific measures to explain the situation to fishermen and the public, or to deal with harmful rumors. He stressed, “We demand that the government provide careful and sincere explanations and effective concrete measures to gain the understanding of the public.
Vice President Masanobu Sakamoto, who was elected as the new president at the general meeting, stated at the press conference that “ocean discharge is a matter of life and death for fishermen.
https://www.chunichi.co.jp/article/494903?fbclid=IwAR2rM7hA8hi4Q9oWxOs8_F6o576aTCeoQh2k-2RelZEJSzi3pTXpqlfzst0
Nuke contaminated water from Fukushima may be out of sight, but should never be out of one’s mind

May 30, 2022
In 2011, the “3/11” earthquake in Japan caused the meltdown of the Fukushima Daiichi Nuclear Power Plant reactor core, unleashing enormous amounts of radioactive material. The operator of the plant, Tokyo Electric Power Company (TEPCO), decided to pour in seawater to cool the reactor and contain the leakage. And because the used seawater became highly contaminated with radioactive material, TEPCO had to put it in storage tanks. A decade on, the nuclear contaminated water generated by the Fukushima Daiichi Nuclear Power Plant are about 150 tons per day in 2021, and will reach the upper limit of the storage tank capacity of 1.37 million tons in the spring of 2023.
According to estimates by the Japan Center for Economic Research, it will cost 50-70 trillion yen (about $400-550 billion) to scrap and decontaminate the reactor, the bulk of which goes to the treatment of contaminated water. So in April 2021, the Japanese government announced that the problem of increasing amounts of nuclear contaminated wastewater would be addressed by dumping it into the sea. On May 18, 2022, the Japan Atomic Energy Regulatory Commission granted initial approval for TEPCO’s ocean dumping plan.
After the Fukushima nuclear accident, the Japanese government set up the “Nuclear Damage Compensation and Decommissioning Facilitation Corporation” (NDF), which is an official agency with 50.1 percent of TEPCO’s voting rights, in order to prevent TEPCO from going bankrupt. In other words, TEPCO is now under direct jurisdiction and control of the Japanese government. It is not hard to see that both TEPCO and the Japanese government are the masterminds behind the nuclear contaminated water dumping plan, because for them, this is the most expedient, cost-effective and trouble-saving way. Japan would need to spend only 3.4 billion yen (about $27 million) according to this plan. But the threat to nature, the environment and human life as a result of such reckless actions was probably never on their minds.
Nuclear contaminated water is not nuclear treated water
Monitoring data collected in 2012 showed that the concentration of Cesium in the waters near Fukushima was 100,000 becquerels per cubic meter, which is 100 times higher than what was detected in the Black Sea after the Chernobyl nuclear leak. Ten years later in 2021, 500 becquerels of radioactive elements per kilogram of weight could still be detected in the flat scorpionfish caught by Japanese fishermen off the coast of Fukushima Prefecture, or five times higher than Japan’s own standards. In the 11 years since the nuclear disaster, one or two thyroid cancer cases have been reported for every 60,000 children in Fukushima Prefecture, much higher than the normal rate.
The Japanese government and TEPCO have repeatedly claimed that nuclear contaminated water is “safe” to be dumped into the ocean because it would go through the multi-nuclide removal system (Advanced Liquid Processing System, ALPS). But it is only the radioactive substance called “Tritium” that has reached this standard. And what Japan doesn’t say is that, even after treatment, the water still contains other radioactive substances such as Strontium 90 and Carbon 14 that cause genetic mutation in the ecosystem. Since the release of the ALPS-related report, the Japanese government has not held any briefings or hearings for the public. And in order to justify the dumping plan, the Japanese government contacted citizen and groups to ask them to stop using the words “nuclear contaminated water”, and use “nuclear treated water” instead. Vigorous public relations (PR) efforts have also been carried out to whitewash the plan. In the 2021 budget of the Japanese Reconstruction Agency, PR expenses related to the Fukushima nuclear accident have increased to 2 billion yen (around $16 million), over four times than the previous year figure. The money has been used on professional teams to weaken and remove negative public opinion in Japan and abroad about the nuclear contaminated water through various propaganda programs.
Furthermore, TEPCO’s track records for handling the nuclear accident have been filled with deception and distortion. In 2007, TEPCO admitted that it had tampered with data and concealed potential safety hazards in a total of 199 regular inspections of 13 reactors in its nuclear power plants since 1977, including the cooling system failure in the Fukushima nuclear accident. One week after the 2011 nuclear accident when experts had already made the judgment that the cores of Units 1 to 3 of the Fukushima Daiichi Nuclear Power Plant had melted, the company still refused to announce the truth to the public, and instead chose to use “core damage,” a term that was significantly less alarming. With a past so bad it is hard to make one believe that TEPCO will dump “safe” nuclear contaminated water into the sea.
Waves of opposition at home and abroad
The Japanese government has so far failed to provide sufficient and credible explanations on the legitimacy of the nuclear contaminated water dumping plan, the reliability of nuclear contaminated water data, the effectiveness of the purification devices, and the uncertainty of the environmental impact. To promote the plan under such circumstances has only brought about wide criticism and questions by various communities in Japan and beyond.
Up to 70 percent of the people in Fukushima Prefecture have expressed opposition to the dumping plan. Konno Toshio, former president of Fukushima University, was opposed to advancing the ocean dumping plan without prior understanding at home and abroad, because this plan could affect future generations and must be treated with great caution. The fishery cooperatives and local councils in Miyagi Prefecture, which is adjacent to Fukushima Prefecture, believe that the dumping of nuclear contaminated water into the ocean may affect the safety of local aquatic products and cause significant economic losses to related industries. Already, 180,000 people in Japan have signed the petition to the Japanese government to adopt disposal options other than ocean dumping.
Vladimir Kuznetsov, academician at the Russian Academy of Natural Sciences, said that radioactive substances in the nuclear contaminated water can only be partially filtered, and the treated water still contains extremely dangerous radionuclides, which will pollute marine life and spread to the entire ocean through fish migration. This will gravely harm the global marine environment and cause serious harm to the health of people in the periphery. According to a research model established by GEOMAR Helmholtz Centre for Ocean Research Kiel, half of the Pacific Ocean will be polluted in less than 57 days if nuclear contaminated water is dumped at the speed announced by Japan.
Voices of justice
Japan’s ocean dumping plan of nuclear contaminated water is a serious threat to the marine environment, and it damages marine interests of the neighbors and other littoral countries. It also violates multiple international conventions such as the United Nations Convention on the Law of the Sea, the Convention on Assistance in Nuclear Accidents or Radiation Emergencies, and the Convention on Nuclear Safety as well as principles of the international law. Many countries, including China, have expressed concern over or opposition to it.
The Russian Foreign Ministry issued a statement criticizing the Japanese government for not consulting with or providing any related information to its neighbors when the decision was made, and expressing grave concern over Japan’s dumping of nuclear polluted water into the ocean. The South Korean Foreign Ministry summoned the Japanese ambassador to Seoul to make a serious protest against Japan’s unilateral decision while large crowds gathered in front of the Japanese embassy to protest. The International Atomic Energy Agency (IAEA) has launched an assessment of Japan’s plan.
The spokesperson of the Chinese Ministry of Foreign Affairs has repeatedly pointed out that Japan’s dumping of nuclear contaminated water into the ocean is extremely irresponsible, and demanded that Japan fully consult with neighboring countries, other stakeholders, and relevant international institutions to find a proper way to dispose of the nuclear contaminated water, before which the dumping into the ocean shall not be initiated.
The ocean is a treasure for all mankind and our home for survival. It is essential for sustainable development and our future. To dump nuclear contaminated water from Fukushima into the ocean is a major issue that bears on the environment for human survival and health, it is not just Japan’s internal affairs. Although keenly aware of the grave harm to the global marine environment caused by the dumping of such water into the sea, Japan has attempted to push through the plan without exhausting all other safe methods. Such an opaque and irresponsible approach is unacceptable, let alone trusted by countries in the region and the larger international community.
Fukushima citizens’ group urges TEPCO to “stop construction of facilities to discharge contaminated water into the ocean without understanding and agreement” and to Governor Uchibori, “Do not agree to the prior consent request
May 25, 2022
On May 25th, members of the Fukushima citizens’ group “Don’t Pollute the Sea Anymore! Citizens’ Council” and other members visited the Fukushima branch office of TEPCO’s Fukushima Reconstruction Headquarters and the Fukushima Prefectural Government on the morning of May 25 to submit a written request to TEPCO. They again demanded that TEPCO “stop construction of facilities for discharging contaminated water into the ocean without understanding and agreement” and that Fukushima Prefecture “not agree to the request for prior consent. Although there is still no consent from Fukushima Prefecture and there are voices of opposition, TEPCO is steadily preparing for the oceanic discharge as “construction work that does not require permission. Upon receiving the request, TEPCO asked the interviewer to leave the room to exchange opinions, but no concrete response was given. While the voices of the people are being ignored, the time for Governor Masao Uchibori to make a decision is approaching.
The “clean sea” cannot be promised.
The letter of request to TEPCO asks for five points.
(1) Stop the full-scale construction of facilities for discharging contaminated water into the ocean without understanding and agreement.
(2) Disclosure of all information, including the concentration and total amount of all radioactive nuclides to be discharged.
(3) Establish drastic measures for contaminated water, such as groundwater sealing, as soon as possible.
(4) Hold explanations and public hearings in Fukushima Prefecture and throughout Japan.
(5) Cancellation of the statement made by the director of the Nuclear Energy Center and an apology.
The group also calls on Fukushima Prefecture Governor Masao Uchibori to address the following four points.
(1) Refrain from agreeing to prior consent for oceanic discharge without understanding and agreement.
(2) Make the government and TEPCO disclose all information, including the concentration and total amount of all radionuclides to be released.
(3) Demand that the government and TEPCO establish measures to prevent contaminated water, such as groundwater sealing.
4) Demand that the government and TEPCO hold explanations and public hearings in Fukushima Prefecture and throughout Japan.
At the Fukushima branch office of TEPCO’s Fukushima Reconstruction Headquarters, Mr. Tsuyoshi Shibano of the Fukushima Public Relations Department received the written request. Four representatives from citizens’ groups took part in the exchange of opinions, but TEPCO allowed only a “head shot” to the interviewers. TEPCO asked the reporters to leave the room, saying, “We do not allow interviews in the exchange of opinions,” “We cannot speak frankly when reporters are present,” and “We do so in other situations as well. When reporters asked for interviews, they were told that they would not begin unless they left the room. According to those present, TEPCO did not make any specific comments in response to the request.
The request to TEPCO included “rescinding and apologizing for the statement made by the director of the Nuclear Energy Center,” a protest against the statement he made when he visited the TEPCO headquarters on June 13 to request the cancellation of the June construction start. When a mother who participated in the protest asked TEPCO to “promise to leave a clean sea for our children,” the director of the Nuclear Energy Center replied, “I can’t promise you that. This mother shouted “Don’t make fun of Fukushima” in front of the TEPCO headquarters. In her written request, she demanded a cancellation and an apology in a strong tone, saying, “This shows a corporate culture of ignoring residents without regard for responsibility for the nuclear accident. TEPCO’s response was limited to saying that they had not been able to confirm what she had said.



The “Promise to the Fishermen’s Federation” is heavy.
At the Fukushima Prefectural Government, Shigeru Ito, Director of the Nuclear Safety Division, responded to the four requests as follows.
The Minister of Economy, Trade and Industry also said, “We will keep our promise. The Minister of Economy, Trade and Industry has also said that he will keep his promise, and we will make sure that he keeps his word.
The Minister said, “We have asked TEPCO to reconsider the safety of the water, since there is a possibility that radioactive materials other than the 64 nuclides may be detected in the water. We are asking TEPCO to reconsider the safety of the water, as there is a possibility that radioactive materials other than the 64 nuclides will be detected.
The frozen soil barrier wall has a certain degree of water interception capacity, but it has been in use for some time. We are demanding that the government and TEPCO urgently study ways to reduce the generation of contaminated water itself to near zero.
The prefectural government will also request that the government and TEPCO provide an opportunity to explain the situation to the residents of the prefecture.
The citizens’ group said, “The time to make demands to the government and TEPCO has passed. We will not make it in time unless we have a concrete plan. It is difficult for the prefecture to hold explanatory meetings and public hearings. We will convey our request to the national government and TEPCO.
A woman from Minamisoma City said, “Even with ALPS treatment and dilution, the water is still ‘contaminated water. If a person is instructed by a doctor to cut back on salt, does it mean that he or she has cut back on salt if he or she adds hot water to miso soup and drinks it all? Isn’t it the same thing?
A woman who retired from a prefectural school and is now teaching Japanese in Vietnam said, “This is not just a Fukushima problem, but a global problem. Seawater travels around the world in a few years. It is not just a rumor, but an actual damage to the world. I want everyone’s voices to be properly conveyed to the national government and TEPCO.
A man who had worked at the nuclear power plant for many years said, “It is strange that Governor Uchibori does not oppose the discharge of water into the ocean and is doing the government’s bidding. Fukushima Prefecture is not a subcontractor of the national government. If contaminated water is discharged into the ocean, it will cause real damage. If you have money to dig undersea tunnels, increase the number of tanks.
After the meeting, Mr. Ito, who was interviewed after the meeting, said, “The ‘request for prior consent’ submitted to the prefectural government is not an examination of the pros and cons of the ocean discharge plan, but rather a confirmation of the safety aspects of the facility plan and the radiation effects on the surrounding area, which must be discussed within the framework of the safety assurance agreement. If we can scientifically confirm that there are no safety issues, there will be fewer options for not obtaining prior consent. As for when the Nuclear Regulatory Commission will respond to the “prior consent request,” he said, “We would like to make a decision after the Nuclear Regulatory Commission approves the plan and we see what the public has to say about the plan.



The people of the prefecture have not forgiven you.
Don’t pollute the sea any more! Chiyo Oda, co-chair of the Citizens’ Council, appealed to reporters at a press conference held at the Fukushima Prefectural Government Press Club.
The other day at a protest in Tokyo, I was asked, “Do the people of Fukushima allow the discharge of contaminated water into the ocean?” I was asked, ‘Do the people of Fukushima allow the discharge of contaminated water into the ocean? They said, ‘We haven’t heard much opposition from the press either. I would like to ask the Fukushima press. We are really worried. We don’t want contaminated water to be discharged into the sea. Please report our voices in the newspapers and on TV. We are really worried. We want you to stop. I don’t want people to think that the people of Fukushima have forgiven us. Please help us.”
Mr. Oda read out the written request both at TEPCO and at the Fukushima prefectural office, but his voice and hands were shaking. He was nervous, of course, but he was also trembling with anger. No matter how much he voiced his opposition, he was ignored. The construction of facilities for the offshore discharge was steadily underway, claiming that the work did not require prior approval. The local media also did not take up our voices of opposition head-on…. It was only natural that he felt the need to vent his anger at the press club.
When I pointed this out to TEPCO, they said, ‘That’s just a lie. When I pointed this out to TEPCO, they said, ‘That’s like marking the ocean. Do they think that will reassure us? As the company that caused the nuclear accident, I don’t feel that they are taking any responsibility at all.
It’s upsetting to be lumped together as a company that is ‘concerned about rumors. If they are so concerned about reputational rumors, they should just stop discharging their waste into the ocean, which would spread contamination.
Kazuyoshi Sato, a member of the Iwaki City Council, also a co-chairman, said, “The government and TEPCO think that the fishermen will give up. I think that if we add some more to the so-called “reputational measures,” the All Fishermen’s Federation will give in and the Fukushima Prefectural Fishermen’s Federation will give in as well. They are disregarding the meaning of the ocean in the ecosystem, or rather, they lack imagination,” he said. He then emphasized, “The people of the prefecture have no ‘understanding’ of the situation.
The people of Fukushima Prefecture do not ‘understand,’ and they do not want to be told that they were complicit in the discharge of contaminated water into the ocean.
Members of the citizens’ group bowed their heads at TEPCO, in front of prefectural officials, and at the press club. Nevertheless, the plan to discharge contaminated water into the ocean is steadily moving forward under the guise that it will interfere with the decommissioning work (removal of fuel debris). The voices of the people are always ignored. But we will still speak out.
http://taminokoeshimbun.blog.fc2.com/blog-entry-652.html?fbclid=IwAR01KGHyaom1xxsBYyWQex07JY3sAziwRhLberOInkX3aG5twyry8PIAEMg
Japan’s plan to release toxic water into sea irresponsible

May 28, 2022
The Tokyo Electric Power Company, according to Japanese media reports, started seabed excavations on May 5 to build a drainage outlet for the nuclear-contaminated water to flow from the Fukushima Daiichi nuclear power plant to the Pacific Ocean. The seabed operation is expected to be completed in early July, meaning Japan has taken a substantive step toward discharging the radioactive water into the sea despite strong opposition at home and abroad.
In March 2011, immediately after a tsunami triggered by a massive earthquake destroyed the Fukushima Daiichi nuclear power plant, TEPCO discharged the highly radioactive water into the sea. But under great pressure from the public, it stopped its controversial move and began building tanks to store the contaminated water.
But these storage tanks can hold only 1.37 million cubic meters of water, and are expected to be full in 2023. So the Japanese government and TEPCO announced on April 13, 2021, that the radioactive water would be “discharged into the sea”.
This plan, too, has come in for severe criticism from the Japanese people and the international community, because it would cause immense damage to the marine environment, as well as human beings, especially in neighboring countries, without benefiting the Japanese people.
The Japan Atomic Energy Regulatory Commission issued “a draft of review paper” on May 18 preliminarily agreeing to the government’s plan, but will make a final decision after one month.
However, the Japanese government said the radioactive water would be treated to meet the so-called standard for discharge. After the nuclear accident, TEPCO used a kind of “purification” equipment to treat the contaminated water to make it less harmful. It claimed that all radioactive materials will be removed from the toxic water, except for tritium.
But in 2018, on studying the contaminated water treated in 2017, a group of experts found that it contained not only tritium but also other radioactive materials such as carbon 14, cobalt 60 and strontium 90, all of which are highly harmful to living beings.
TEPCO has also said the radioactive water will be discharged after being diluted with seawater. But studies show that 1 liter of the radioactive water needs to be mixed with 254 liters of clean seawater to be properly diluted, and it would take at least 30 years for the process to be completed.
The severe consequences of the Fukushima nuclear accident have been emerging over the years. The animals in the Fukushima isolation zone have been showing visible effects of radiation, radioactive materials in fish in the nearby waters are much higher than normal levels, and the incidence of thyroid cancer in Fukushima has significantly increased.
Since the marine ecosystem is a highly integrated and delicate system, the Fukushima water will be enough to contaminate the entire Pacific and beyond.
The international scientific community has reached a consensus on the cumulative effects of radioactive materials. For instance, a Greenpeace report issued in October 2020 said that if discharged into the sea, the radioactive water could also affect human beings’ DNA. And the US National Oceanic and Atmospheric Administration and other marine authorities said that once the Fukushima water enters the sea, its radioactive materials will spread across the Pacific and other oceans, causing unprecedented damage to the marine ecology.
Ever since the Japanese government decided last year to discharge the radioactive water, countries around the Pacific Rim have been opposing it. In particular, China, the Republic of Korea, Russia and some Pacific island countries have voiced serious concerns over Japan’s decision.
Many environmentalists and scholars have also criticized Japan’s plan. In Japan alone, thousands of people, mainly belonging to NGOs, as well as the National Federation of Fisheries Associations have publicly opposed the plan.
In a public opinion survey conducted by Japanese media outlets, nearly 60 percent of the respondents said they were worried about the effects of the radioactive water on the sea and marine life. And rightly so, because even 11 years after the Fukushima nuclear accident, prices of sea food, vegetables and fruits from Fukushima Prefecture, Ibaraki Prefecture, Miyagi Prefecture and nearby places are still much lower than those from places not affected by nuclear radiation.
Besides, the investigation report of the International Atomic Energy Agency’s technical work group released on April 29 did not give a final judgment on whether discharging the nuclear-contaminated water into the sea was safe, and instead suggested a series of technical improvements to reduce its environmental impact. In fact, Japan did not allow the IAEA’s technical work group to evaluate other plans. As a result, it was not possible for the agency to find the best way to deal with the problem.
But despite the strong opposition to its plan both at home and abroad, Japan is hell-bent on discharging the toxic water into the sea, which shows that it does not give two hoots to the concerns of the international community or the Japanese people.
Actually, Japan can deal with the issue in a way that would not harm the marine environment. For example, the Japan Atomic Energy Civic Committee has said that storing the radioactive water in large storage tanks installed on land or “solidification treatment with mortar” are safer ways to deal with the toxic water.
As a signatory to the United Nations Convention on the Law of the Sea, Japan knows that discharging the contaminated water into the sea will have cross-border effects. But without exhausting all safe disposal means, disclosing all relevant information, and consulting with all the stakeholders including neighboring countries, Japan has decided to go ahead with its plan in order to fulfill its selfish economic and political interests, and save costs.
Japan’s decision is a serious threat to marine life as well as human beings, and a gross violation of international rules. Therefore, Japan should change its decision, conduct a serious study on safe operational plans to deal with the contaminated water, and act like a responsible country.
http://global.chinadaily.com.cn/a/202205/28/WS62918561a310fd2b29e5f85a.html
Fukushima Daiichi Nuclear Power Plant contaminated water, after all… “Protect our oceans!
May 21, 2022
Environmental Groups Perform Against Ocean Discharge of “Contaminated Water from Fukushima Daiichi Nuclear Power Plant
Japan’s Nuclear Regulatory Commission Virtually Approves Ocean Discharge of Contaminated Water

Members of environmental citizen groups, including the Korean Citizens’ Center for Environmental Health and the Sea Committee of the Environmental Movement Coalition, held an emergency press conference in front of the Japanese Embassy in Jongno-gu, Seoul, on the morning of March 20, and made their opposition to the oceanic discharge of radioactive water from the Fukushima Daiichi nuclear power plant clear.

Japan’s Nuclear Regulation Authority effectively approved Tokyo Electric Power Co.’s plan to mix radioactive water from the Fukushima Daiichi nuclear power plant with seawater and discharge it into the ocean starting next spring on March 18. TEPCO plans to treat the contaminated water with a multinuclide removal system (ALPS) and then dilute it with seawater to lower the tritium (triple hydrogen) concentration before discharging it into the sea. Once the approval process is complete, TEPCO plans to obtain the consent of the local authorities in charge and begin construction of facilities for the discharge in earnest. We collected photos of the site.
Japan’s Nuclear Regulation Authority effectively approved TEPCO’s plan to mix radioactive water from the Fukushima Daiichi Nuclear Power Plant with seawater and discharge it into the sea starting next spring on March 18.

Jung Hyo Kim, Reporter (Inquiries: japan@hani.co.kr)
http://japan.hani.co.kr/arti/politics/43525.html?fbclid=IwAR23_nH_28-qvQTVP4UdvLlVro5H-m9EKbIJwhVYCoTWLH4cdRVAc_V9WyU
S. Korea denies report of alleged approval of Japan’s Fukushima water release plan
May 20, 2022
SEOUL, May 20 (Yonhap) — South Korea on Friday denied a Japanese media report claiming the Seoul government agreed to Tokyo’s plan to release radioactive water into the ocean from the crippled Fukushima nuclear power plant.
Earlier this week, a Japanese news agency reported that the new Yoon Suk-yeol government appears to be planning to have consultations with Japan on the premise that Tokyo will discharge contaminated water as planned, while the former Moon Jae-in government objected to the plan.
“Our government has never gone for Japan’s Fukushima water release plan. We are concerned about some arbitrary and subjective media reports,” Seoul’s foreign ministry said in a text message sent to reporters.
The ministry vowed utmost efforts to come up with “needed responses to have the contaminated water be disposed in a way that meets international laws and standards and in a safe manner from objective and scientific perspectives,” while continuing consultations with Japan.
In April 2021, Japan announced a plan to start discharging the radioactive water into the sea in 2023 in what is expected to be a decadeslong process, as all storage tanks at the Fukushima plant are expected to be full as early as fall of 2022.
Earlier this week, Japan’s Nuclear Regulation Authority gave initial approval for Tokyo Electric Power’s discharge plan, with final approval likely to come following a 30-day public comment period.

https://en.yna.co.kr/view/AEN20220520010800320?section=national/national
-
Archives
- February 2026 (181)
- January 2026 (308)
- December 2025 (358)
- November 2025 (359)
- October 2025 (376)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS