Power Technology 21st June 2018, NDA to spend billions stabilising plutonium canisters. The National Audit Office (NAO) has released a report detailing the unstable condition of highly dangerous plutonium canisters at the Sellafield nuclear plant, said to be “decaying faster than anticipated”.
The report, titled ‘Progress with reducing risk at Sellafield’ warns that if these canisters were to leak it would prove an “intolerable risk” – a label defined by the Nuclear Decommissioning Authority (NDA) as a situation where reducing the risk “becomes the overriding factor”, taking precedence over matters of cost and requiring immediate action.
The NDA has refused to comment on the number of canisters affected, though it has said it is only a “small proportion” of their total number. The UK houses 40% of global civil plutonium, the majority of which is stored at the Sellafield site in Cumbria, itself overseen by the NDA. The substance is a by-product of nuclear fuel reprocessing and the site’s abundant stock has led the NDA to label Sellafield its most hazardous facility.
The new report shows Sellafield, which opened in 2012, to have ‘unsuitable’ containers for storing plutonium. The NAO has proposed the canisters be repackaged through the store retreatment plant (SRP) facility, though until this facility is ready the NDA is recommended to place the more unstable canisters in extra layers of packaging. In response to these measures, the NDA has announced its decision to pledge a further £1bn on these packaging canisters, and £1.5bn on building a new facility to house the plutonium. https://www.power-technology.com/news/nda-spend-billions-stabilising-plutonium-canisters/
June 18, 2018 The U.S. Senate today passed its annual defense authorization bill with three key provisions championed by U.S. Senator Dean Heller (R-NV) to support Nevada’s disabled veterans and veterans struggling with mental illness and to remove the $30 million to store defense nuclear waste at Yucca Mountain that was included in the version approved by the U.S. House of Representatives. The legislation, formally named the John S. McCain National Defense Authorization Act (NDAA) for Fiscal Year 2019, increases funding for training across all service branches and authorizes a 2.6 percent pay raise for troops – the largest increase in nine years for U.S. service members. Moving forward, both chambers will need to convene a joint conference committee in which representatives, who are appointed by leadership in the U.S. House of Representatives and U.S. Senate, reconcile the two versions of the defense bill and must produce a final report.
Heller worked with the U.S. Senate Armed Services Committee and the U.S. Senate Appropriations Committee to keep funding and an authorization of funding to revive Yucca Mountain out of the U.S. Senate’s version of the NDAA. Earlier this year, Heller urged U.S. Senate Armed Services Committee Chairman John McCain (R-AZ) to honor the will of the U.S. Senate appropriators and to exclude any language that authorizes funding for Yucca Mountain in the NDAA. Heller’s letter to Chairman McCain can be found HERE.
“Congress has an obligation to support our men and women in uniform, and that’s why I welcome the U.S. Senate’s passage of legislation that will give Nevada’s service members the largest pay raise in nearly a decade, provide our military with the resources it needs to keep America safe, and support Nevada’s 300,000 veterans. I’m proud that this legislation includes my provisions to support Nevada’s disabled veterans and help our veterans who may be struggling with mental illness and having difficulty finding work,” said Heller. “Furthermore, unlike the U.S. House of Representatives-passed version of the bill that contains $30 million to revive Yucca Mountain, I’m pleased I was able to work with Chairman McCain and U.S. Senate appropriators to successfully ensure that our bill did not include a single dollar authorized for Yucca Mountain. So once again, while the U.S. House of Representatives charges forward with shipping nuclear waste to Nevada, I kill their efforts in the U.S. Senate. While this is progress, we still have more work to do to stop the U.S. House of Representatives from turning Nevada into a nuclear waste dump. I remain committed to doing everything that I can to make sure that Yucca Mountain remains dead.”…….https://www.heller.senate.gov/public/index.cfm/pressreleases?ID=89EE1BBB-BB73-42D9-A192-038B549AADC4
Herald 20th June 2018 , Decommissioning the nuclear site at Sellafield faces continued delays and an overspend of up to £913 million, according to an official report. The National Audit Office (NAO) said the Nuclear Decommissioning Authority (NDA) had improved its performance in delivering major projects at the site in Cumbria. But work is still predicted to be late and to cost more than originally expected, said the spending watchdog. The NDA’s nine major projects were expected to cost an additional 60% of their budget at the design stage in 2015, but this has been reduced to 29%, said the NAO. While this was a substantial improvement, it was still a forecast overspend of
£913 million.
The NAO reported that three projects were cancelled when £586 million had already been spent on them after the NDA said it had
found a better way of delivering the work. It said Sellafield Limited has achieved £470 million in efficiency savings, but added that neither the NDA nor the company knows their make-up and admit that a proportion does not represent genuine efficiency savings.
“The strategic decisions the NDA takes around prioritising activity at Sellafield could be profoundly changed and improved by a better, more evidence-based assessment of these constraints. “The NAO has found that the role of the NDA is unclear and this could put at risk the progress we are now seeing at Sellafield,” the report said. “The Department for Business, Energy & Industrial Strategy’s
governance of the NDA is complex and not working as well as it should to support improvements at Sellafield. http://www.heraldscotland.com/news/16301638.Watchdog_warns_of_delays_and___900m_overspend_in_Sellafield_decommissioning/
Australian mining companies have a poor track record operating in Africa. Australian uranium company Paladin Energy has now put two of its mines into ‘care-and-maintenance’ and bankruptcy looms. But who cleans up the company’s mess in Namibia and Malawi, asks JIM GREEN
Many Australian mining projects in Africa are outposts of good governance – this is what Julie Bishop, the country’s Foreign Minister, told the Africa Down Under mining conference in Western Australia in September 2017. The Australian government “encourages the people of Africa to see us as an open-cut mine for lessons-learned, for skills, for innovation and, I would like to think, inspiration,” the minister said.
But such claims sit uneasily with the highly critical findings arising from a detailed investigation by the International Consortium of Independent Journalists (ICIJ). The ICIJ noted in a 2015 report that since 2004, more than 380 people have died in mining accidents or in off-site skirmishes connected to Australian mining companies in Africa.
The ICIJ report further stated: “Multiple Australian mining companies are accused of negligence, unfair dismissal, violence and environmental law-breaking across Africa, according to legal filings and community petitions gathered from South Africa, Botswana, Tanzania, Zambia, Madagascar, Malawi, Mali, Cote d’Ivoire, Senegal and Ghana.”
Paladin Energy’s Kayelekera uranium mine in Malawi provides a case study of the problems with Australian mining companies in Africa. Western Australia-based Paladin exploited Malawi’s poverty to secure numerous reductions and exemptions from payments normally required by foreign investors.
United Nations’ Special Rapporteur Olivier De Schutter noted in a 2013 report that “revenue losses from special incentives given to Australian mining company Paladin Energy, which manages the Kayelekera uranium mine, are estimated to amount to at least US$205 million (MWK 67 billion) and could be up to US$281 million (MWK 92 billion) over the 13-year lifespan of the mine.”
Standards at Kayelekera fall a long way short of Australian standards ‒ and efforts to force Australian mining companies to meet Australian standards when operating abroad have been strongly resisted. The Kayelekera project would not be approved in Australia due to major flaws in the assessment and design proposals, independent consultants concluded.
Care-and-maintenance
Kayelekera was put into care-and-maintenance in May 2014, another victim of the uranium industry’s post-Fukushima meltdown. And just last month, Paladin announced that its only other operating mine ‒ the Langer Heinrich mine (LHM) in Namibia ‒ will be put into care-and-maintenance.
Perhaps the most striking aspect of the decision to mothball LHM is that Paladin claims it is the lowest cost open-pit uranium mine in the world. Moreover, the company wasn’t even paying to mine ore ‒ mining ceased in November 2016 and since then ore stockpiles have been processed. Thus a low-cost mine can’t even turn a profit processing mined stockpiles.
The cost of production was US$23.11 / lb uranium oxide in December 2017, and the average realised sale price in the second half of 2017 was $21.82.
Anticipating the decision to mothball LHM, Paladin Energy CEO Alex Molyneux said in late-April: “The uranium market has failed to recover since the Fukushima incident in 2011, with the average spot price so far in 2018 the lowest in 15 years. It’s deeply distressing to have to consider suspending operations at LHM because of the consequences for our employees, and the broader community. However, as there has yet to be a sustainable recovery in the uranium market, and with the aim of preserving maximum long-term value for all stakeholders, it is clearly prudent to consider these difficult actions.”
Paladin hopes to resume mining at LHM and Kayelekera following “normalization” of the uranium market, which it anticipates in the next few years. But with no operating mines, Paladin may not survive for long enough to witness a market upswing.
Paladin was placed into the hands of administrators in July 2017 as it was unable to pay French utility EDF a US$277 million debt.
In January 2018, Paladin’s administrator KPMG noted that an Independent Expert’s Report found that the company’s net debt materially exceeds the value of its assets, its shares have nil value, and if Paladin was placed into liquidation there would be no return to shareholders.
The company was restructured, with Deutsche Bank now the largest shareholder, and relisted on the Australian Securities Exchange in February 2018.
Perhaps LHM will be sold for a song, either before or after Paladin goes bankrupt. A subsidiary of China National Nuclear Corporation (CNNC) has held a 25 percent stake in LHM since January 2014. Last year, the CNNC subsidiary considered exercising its contractual right to buy Paladin’s 75 percent stake in LHM, but chose not to exercise that right following an independent valuation of US$162 million for Paladin’s stake.
Mine-site rehabilitation
Paladin hopes to resume mining following “normalization” of the uranium market ‒ but low prices could be the new normal. Former World Nuclear Association executive Steve Kidd said in May 2014 that the industry is set for “a long period of relatively low prices”. Prices were far higher in 2014 than over the past twelve months. Paladin’s CEO Alexander Molyneux said that “it has never been a worse time for uranium miners” in 2016 and the situation has worsened since then for the industry ‒ prices have fallen further still.
Sooner or later ‒ probably sooner ‒ both the LHM and Kayelekera mine-sites will need to be rehabilitated. Yet it is extremely doubtful whether Paladin has set aside adequate funds for rehabilitation. Paladin’s 2017 Annual Report lists a ‘rehabilitation provision‘ of US$86.93 million to cover both LHM and Kayelekera.
One problem is that the funds might not be available for rehabilitation if Paladin goes bankrupt. A second problem is that even if the funds are available, they are unlikely to be sufficient.
For comparison, Energy Resources of Australia’s provision for rehabilitation of the Ranger uranium mine in Australia ‒ also an open-pit uranium mine, like LHM and Kayelekera ‒ is US$403 million (A$526 million). That figure is additional to US$346 million (A$452 million) already spent on water and rehabilitation activities since 2012 ‒ thus total rehabilitation costs could amount to US$749 million (A$978 million) … and the current cost estimates could easily increase as they have in the past.
Rehabilitation of LHM and Kayelekera could be cheaper than rehabilitation of Ranger for several reasons, such as the relative size of the mine-sites. However it stretches credulity to believe that the cost of rehabilitating both LHM and Kayelekera would be an order of magnitude lower than the cost of rehabilitating one mine in Australia.
Paladin was required to lodge a US$10 million Environmental Performance Bond with Malawian banks and presumably that money can be tapped to rehabilitate Kayelekera. But US$10 million won’t scratch the surface. According to a Malawian NGO, the Kayelekera rehabilitation cost is estimated at US$100 million.
Paladin has ignored repeated requests to provide information on the estimated cost of rehabilitating Kayelekera (and also ignored an invitation to comment on a draft of this article), but the figure will be multiples of the US$10 million bond and it is extremely unlikely that Paladin’s provision of US$86.93 million for the rehabilitation of both LHM and Kayelekera is adequate.
If Paladin goes bankrupt, it seems likely that most of the costs associated with the rehabilitation of LHM and Kayelekera will be borne by the Namibian and Malawian governments (with a small fraction of the cost for Kayelekera coming from the bond) ‒ or the mine-sites will not be rehabilitated at all.
Even if Paladin is able to honour its US$86.93 million provision, additional costs necessary for rehabilitation will likely come from the Malawian and Namibian governments, or rehabilitation will be sub-standard.
Problems most acute for Kayelekera
The problem of inadequate provisioning for rehabilitation is most acute for Kayelekera ‒ it is a smaller deposit than LHM and more expensive to mine (Paladin has said that a uranium price of about US$75 per pound would be required for Kayelekera to become economically viable ‒well over twice the current long-term contract price). Thus the prospects for a restart of Kayelekera (and the accumulation of funds for rehabilitation) are especially grim.
Is it reasonable for Australia, a relatively wealthy country, to leave it to the overstretched, under-resourced government of an impoverished nation to clean up the mess left behind by an Australian mining company? Malawi is one of the poorest countries in the world. According to a 2013 UN report, more than half of the population live below the poverty line.
Australia’s Foreign Minister Julie Bishop should intervene to sort out the situation at Kayelekera and to prevent a repetition of this looming fiasco. The conservative Minister’s eyes might glaze over in response to a moral argument about the importance of Australia being a good global citizen. But there is also a hard-headed commercial argument for intervention to ensure that the Kayelekera mine-site is rehabilitated.
It does Australian companies investing in mining ventures abroad no good whatsoever to leave Kayelekera unrehabilitated, a permanent reminder of the untrustworthiness and unfulfilled promises of an Australian miner and the indifference of the Australian government.
Australia is set to become the biggest international miner on the African continent according to the Australia-Africa Minerals & Energy Group. But Australian companies can’t expect to be welcomed if problems such as Kayelekera remain unresolved.
Dr Jim Green is the national nuclear campaigner with Friends of the Earth Australia and editor of the Nuclear Monitor newsletter, where a version of this article was originally published. He is co-author of a new report titled ‘Undermining Africa: Paladin Energy’s Kayelekera Uranium Mine in Malawi’.
FES nuclear decommissioning funds inadequate, consumer groups tell NRC, Cleveland Business, When FirstEnergy Solutions closes the Perry nuclear power plant east of Cleveland, the Davis-Besse nuclear plant near Toledo and the Beaver Valley nuclear plant near Pittsburgh it will have up to 60 years to decommission the reactors and clean up the land at a cost of billions of dollars. A coalition of consumer and environment groups is arguing that the decommissioning trust funds are inadequate, that FES will not be able to begin decommissioning for years after the plants are closed and that parent company FirstEnergy Cop. must be held responsible to make up the funding deficit.(Plain Dealer file)
CLEVELAND, Ohio — The trust funds that FirstEnergy created years ago to pay for the demolition of its nuclear power plants and clean-up are no longer adequate, a coalition of consumer and environmental groups is arguing today at the Nuclear Regulatory Commission.
Japan to cap plutonium stockpile to allay U.S. concerns, THE ASAHI SHIMBUN, June 17, 2018
Japan plans to boost measures to curb surplus plutonium extracted from the reprocessing of spent fuel at nuclear power plants, including capping the country’s stockpile of the highly toxic material.
The move followed the U.S. and other countries’ calls for Japan to reduce excess plutonium in light of nuclear nonproliferation and the threat of terrorist attacks involving nuclear materials.
The Cabinet Office’s Japan Atomic Energy Commission will incorporate the measures in the five-point basic nuclear policy expected at the end of this month, the first revision in 15 years.
A reduction in the volume of plutonium held by Japan will also be specified in the government’s basic energy plan, which will be revised next month.
Japan possesses about 10 tons of plutonium inside the country and about 37 tons in Britain and France, the two countries contracted to reprocess spent nuclear fuel. The total amount is equivalent to 6,000 of the atomic bomb that devastated Nagasaki in 1945.
In the policy, announced in 2003, the government vowed not to possess plutonium that has no useful purpose. The government has pledged not to have surplus plutonium to the International Atomic Energy Agency………
Japan can reprocess spent nuclear fuel under the Japan-U.S. Nuclear Cooperation Agreement.
The 30-year pact is expected to be automatically extended beyond its expiration on July 16.
After the expiration, however, the pact will be scrapped six months after either Japan or the United States notifies the other side of its intention to do so.
Foreign Minister Taro Kono has expressed concern about the “unstable” future of the agreement after July, and Japan has worked to meet a request from Washington to clearly spell out steps to reduce Japan’s plutonium stocks.
The government’s draft policy calls for allowing retrieval of plutonium strictly based on the projected amount to be used at conventional nuclear reactors as mixed plutonium-uranium oxide fuel, commonly known as MOX fuel.
It will also step up oversight on utilities with the aim of reducing the amount of plutonium to a level allowing the nuclear reprocessing plant under construction in Rokkasho, Aomori Prefecture, and other facilities to operate properly.
In addition, electric power companies will cooperate with each other in the use of MOX fuel, so that the amount of Japan’s surplus plutonium that is now overseas will be reduced.
For example, Kyushu Electric Power Co. and Kansai Electric Power Co., two utilities that began using MOX fuel ahead of other utilities, will consider using more MOX fuel at their nuclear plants for the benefit of Tokyo Electric Power Co., whose prospect of bringing its Kashiwazaki-Kariwa nuclear power plant in Niigata Prefecture back on line remains uncertain.
When the 2.9 trillion yen ($26.37 billion) reprocessing plant in Rokkasho goes into full operation, about eight tons of new plutonium will be added annually as Japan’s surplus plutonium…..
of nine reactors that have resumed operations following the introduction of more stringent safety standards after the Fukushima No. 1 nuclear disaster in 2011, only four can use MOX fuel.
The operation of the Rokkasho plant will likely be significantly curtailed even if it is completed amid that environment.
The inhabitants of Jaroměřice nad Rokytnou, a village in the Vysočina region between Bohemia and Moravia, voted overwhelmingly against the construction of a nuclear waste storage site on their land in a referendum on Saturday.
Jaroměřice nad Rokytnou is one of nine Czech locations being considered by experts for the purposes of a nuclear waste store. About 45 percent of the village’s inhabitants took part in the vote, which makes the referendum valid.
The report lays out for the public complex issues regarding spent fuel management, current U.S. Nuclear Regulatory Commission regulations, the radiological contamination of the site, effects on communities and workers, and useful references regarding other reactors that have closed. It also clarifies that replacement energy is already available even without new gas power plants.
However, on site reuse, the task force report fails to examine one of the best options, which would be to decommission and clean up the whole Indian Point site within a reasonable period, such as 20 years. Instead, the task force goes into details on options for the reuse of small parcels that are highly constrained and that Entergy has said it will not make available until the site is decommissioned.
The task force took this limited approach because the the NRC, which oversees decommissioning, allows nuclear power plants up to 60 years to decommission. However, the NRC is focused on the interests of nuclear licensees, not the local community. It is therefore necessary and appropriate for the state and its task force to act as a champion of local concerns and interests during the forthcoming Indian Point decommissioning process. Experience with decommissioning so far shows that it can be done within 20 years or even faster if the will is there.
Above – Sellafield’s massive Magnox nuclear waste storage pool
Only Cthulhu can solve Sellafield’s sludgy nuclear waste problem, Wired, ByDAVID HAMBLING , 14 June 18
Cleaning up Sellafield’s nuclear waste costs £1.9 billion a year. To help with the toxic task, robots are evolving fast. Sellafield has been called the most dangerous place in the UK, the most hazardous place in Europe and the world’s riskiest nuclear waste site. At its heart is a giant pond full of radioactive sludge, strewn with broken metal, dead animals and deadly nuclear rods. The solution to clearing up Sellafield’s nuclear waste and retrieving the missing nuclear fuel? Robots, of course. And to tackle this mammoth task, the robots are being forced to evolve.
Sellafield’s First-Generation Magnox Storage Pond is a giant outdoor body of water that’s the same size as two Olympic swimming pools. It was built in the 1960s to store used fuel rods from the early Magnox reactors – which had magnesium alloy cladding on the fuel rods – as part of Britain’s booming nuclear program. In 1974, there was a delay in reprocessing; fuel rods started corroding and the pond became murky. The pool was active for 26 years until 1992 and is now finally being decommissioned as part of the £1.9 billion spent each year on Sellafield’s mammoth cleanup operation.
The pond contains about six metres of radioactive water and half a metre of sludge, composed of wind-blown dirt, bird droppings and algae – the usual debris that builds up in any open body of water. Unlike other mud, it conceals everything from dropped tools and bird carcasses to corroded Magnox cladding and the remains of uranium fuel rods.
A number of robotic creations have bee used to get to the bottom of the pool’s sludge but struggle to break through the hostile environment. Tethered swimming robots do not have the sensors to find objects in the fine mud, and lack the leverage to lift chunks of metal. Experience at Fukushima has shown robots that are not well adapted to the environment are a waste of time.
Enter Cthulhu, a tracked robot that can drive along the pond bed, feeling its way with tactile sensors and sonar. The robot, which is currently in development, is approaching Sellafield’s problem differently. The robot will be able to identify nuclear rods and then pick them up. “Rather than trying to mimic a human, we’re building a robot that can do things humans can’t do with senses that humans don’t have,” says Bob Hicks of QinetiQ, which is leading the project.
The name stands for ‘Collaborative Technology Hardened for Underwater and Littoral Hazardous Environment,’ but it’s also a nod to Cthulhu, the godlike alien created by HP Lovecraft: both are amphibious, dwell in strange surroundings, and have sensory feelers. “Much like a walrus detecting molluscs, we hope to be able to detect and identify objects in the sludge with the whiskers,” says Plamen Angelov of Lancaster University’s School of Computing and Communications.
QinetiQ is supplying the tracked body, originally from a bomb disposal robot, and Bristol Maritime Robotics is developing the tactile sensors, while Angelov’s team is providing the neural network AI. It is planned the robot will use deep learning to fuse tactile and sonar data into a single picture of the world. Existing neural networks can handle video data, and ‘image classifiers’ to distinguish objects are well-established. But nobody has tried to fuse data from different types of sensor before.
Cthulhu’s classifier will learn to divide objects into ‘fuel rods’ and ‘everything else’………
The work at Sellafield is due to take several decades to complete fully. Nuclear waste is spread through several buildings in a variety of silos and pools. Each has its own challenges for cleaning-up. For the First Generation Magnox Pond, documents from the government show all the bulk fuel should be removed by the early 2030s. http://www.wired.co.uk/article/sellafield-nuclear-robots-cleanup-waste
Workers will pump radioactive sludge to an adjacent building near the Columbia River, where it will be packaged and transported to the middle of the Hanford site. Allison Sundell, June 13, 2018
Hanford employees began work to remove radioactive sludge from a storage facility near the Columbia River and move it to a location near the center of the Hanford site, the U.S. Department of Energy announced Wednesday.
The 35 cubic yards of sludge are a mixture of tiny fuel corrosion particles, metal fragments, and dirt. It’s the result of deteriorating fuel rods that were exposed to radiation and is some of the most hazardous material at Hanford, according to the Department of Energy.
The sludge is currently stored in a facility about 400 yards from the Columbia River.
Workers will first pump the sludge to an adjacent building where they will package and prepare the material to be transported to the middle of the Hanford site. The work is expected to last until 2019.
Sludge Removal Process Near the Columbia River at the Hanford
The new storage facility has safety features including secondary containment basins, leak detectors, and vents.
The move away from the Columbia River and to a safer storage facility is to reduce risk, according to Doug Shoop, manager of the Department of Energy’s Richland Operations Office.
Hanford’s contractor, CH2M HILL Plateau Remediation Company, says workers spent years developing the sludge removal system and took extensive preparations before the work began.
A Hanford watchdog group is objecting as the Department of Energy takes the first step toward a plan to fill underground, radioactive waste storage tanks with concrete-like grout and leave them permanently in place. The C Tank Farm, which would be closed first, has not had enough radioactive waste removed to have tanks filled with grout, said Tom Carpenter, executive director of Seattle-based Hanford Challenge.
“This would be a serious setback for the cleanup at Hanford if the DOE is allowed to turn Hanford into the nation’s high-level nuclear waste dump,” Carpenter said. “This will be challenged.”
Geoffrey Fettus, a senior attorney at the Natural Resources Defense Council, said that “the people of the Pacific Northwest deserve better, and we’ll be there with them opposing this unsound and unsafe effort.”
Nikkei Asian Review 10th June 2018, US demands Japan reduce its plutonium stockpiles. Trump-Kim summit raises
questions about Tokyo’s nuclear exemption. The U.S. has called on Japan to
reduce its high levels of stockpiled plutonium, a move that comes as the
Trump administration seeks to convince North Korea to abandon its nuclear
weapons, Nikkei has learned. https://asia.nikkei.com/Politics/International-Relations/US-demands-Japan-reduce-its-plutonium-stockpiles
RICHLAND, Wash. — A Hanford watchdog group is objecting as the Department of Energy takes the first step toward a plan to fill underground, radioactive waste storage tanks with concrete-like grout and leave them permanently in place.
The C Tank Farm, which would be closed first, has not had enough radioactive waste removed to have tanks filled with grout, said Tom Carpenter, executive director of Seattle-based Hanford Challenge.
“This would be a serious setback for the cleanup at Hanford if the DOE is allowed to turn Hanford into the nation’s high-level nuclear waste dump,” Carpenter said. “This will be challenged.”
Geoffrey Fettus, a senior attorney at the Natural Resources Defense Council, said that “the people of the Pacific Northwest deserve better, and we’ll be there with them opposing this unsound and unsafe effort.”
DOE has completed a draft evaluation of the waste remaining in the C Tank Farm, concluding that radioactive waste has been removed to the extent possible and that the remaining waste, if grouted in place, would meet requirements for disposing of it as low-level radioactive waste.
The draft evaluation is a step toward classifying the waste as low-level to allow it to be left in place as tanks are filled with grout and then covered with an above-ground cap to prevent precipitation from infiltrating.
An all-day meeting is planned starting at 9 a.m. Monday at the Richland Public Library to explain the draft document and its findings. A public comment period started June 4.
DOE worked steadily to empty most of the waste in the 16 tanks of C Tank Farm from 2003 until late 2017.
The federal court-enforced consent decree requires DOE to get as much radioactive waste from the tanks as possible, with an overall goal of getting an average of 99 percent of waste removed from the 149 single-shell tanks at Hanford.
It is roughly the equivalent of a little less than an inch of waste if it were spread evenly across the bottom of a tank.
In the C Tank Farm, about 96 percent of the volume of the waste was removed, according to DOE.
The 16 tanks held 1.8 million gallons of mostly sludge and salt cake when retrieval of solids began. They now hold an estimated 64,000 gallons of waste.
DOE was required to use up to three different technologies at each tank until each technology was no longer able to remove waste under the terms of the federal court-enforced consent decree.
Technologies included various methods to spray high-pressure streams of liquid on the waste within the enclosed tanks and move it toward a pump for removal, different vacuuming systems, and soaking hardened waste in water or a caustic chemical.
Much of the remaining waste is difficult to retrieve safely without exposing workers to radiation or damaging the walls and floor of the tanks, which already are prone to leaking. Some of the remaining waste is clinging to the walls of the tank.
Hanford Challenge is not proposing that workers be put in harm’s way, Carpenter said.
In 10 to 20 years, there could be better technology to retrieve remaining waste, provided the tanks have not already been filled with grout to make that impossible, he said.
In the meantime, the solid waste in the tanks could be monitored and DOE could focus on the more pressing issue of removing waste from its other leak-prone, single-shell tanks, Carpenter said. Just one tank in addition to the 16 C Farm tanks has been emptied to regulatory standards.
Grout has not been shown to effectively contain nuclear waste for periods of more than 100 years, according to Hanford Challenge. Water can infiltrate grout, and grout can break down quickly in the presence of caustic materials such as nuclear waste, it said.
Plutonium would reach the groundwater and then the Columbia Point at some point in the future, Carpenter said.
The draft proposal would challenge the consensus that Hanford’s tank waste should be vitrified, or immobilized in glass, according to Hanford Challenge.
“Hanford is proposing shortcuts to the cleanup that will save money, but will in the end further damage the environment and impact human health and safety and future generations,” Carpenter said.
DOE said in its announcement of the draft report and public meeting that “closing the emptied tanks would be a significant achievement in DOE’s Hanford cleanup mission. DOE has a record of safely and successfully closing emptied underground waste tanks at the Savannah River Site in South Carolina and the Idaho National Laboratory.”
Public comment will be accepted through Sept. 7 at WMACDRAFTWIR@rl.gov. It also can be mailed to Jan Bovier; DOE Office of River Protection; P.O. Box 450, MSIN H6-60; Richland, WA 99354.
For more information on the report, click on the revolving banner at www.hanford.gov.
Further steps in the regulatory process will be required before the C Tank Farm is closed.
DOE will have to make a decision on whether tanks could be filled with grout or must be dug up. The Washington state Department of Ecology, a Hanford regulator, also would have to agree that tanks could be grouted.
a minimum requirement for any form of political consent to onsite storage would be a clear commitment by the government to phase out all nuclear power by a fixed date, so that the final amount of waste can be determined and will not just keep growing, along with the burden on local people.
CNIC Seminar report: The problems with Japan’s Plutonium: What are they and how do we deal with them? http://www.cnic.jp/english/?p=4135Caitlin Stronell, CNIC BY CNIC_ENGLISH · JUNE 4, 2018 On April 20, CNIC organized a seminar with guest speaker Prof. Frank von Hippel, a nuclear physicist from Princeton University’s Program on Science and Global Security, presenting alternative ways to dispose of spent fuel instead of reprocessing, as well as options for disposal of separated plutonium. After this presentation of technical solutions, a panel discussion took place. Prof. Eiji Oguma, a historical sociologist from Keio University’s Faculty of Policy Management and a well-known commentator on the post-Fukushima anti-nuclear movement in Japan, pointed out the political barriers that must be overcome if any of these technical solutions were to be actually implemented, no matter how much more reasonable they may seem from economic and safety perspectives. CNIC’s General Secretary, Hajime Matsukubo was also on the panel and brought into the discussion the international implications of Japan’s plutonium policy including the US-Japan Nuclear Agreement.
Prof. von Hippel explained that plutonium disposal is a global problem, with more than half of the existent separated plutonium being produced as a result of civilian reprocessing, the rest produced for military purposes. Disposing of the plutonium that had been produced for weapons during the cold war has been a huge headache for the United States with planned disposal by burning it as MOX fuel in commercial reactors proving hugely expensive. America has all but abandoned its half-built MOX plant and is now looking towards the ‘dilute and dispose’ option.
This process would use glove boxes to mix 300 grams of plutonium oxide into a can of ‘star dust’ (a secret ingredient from which plutonium would be difficult to separate again). This can would then be placed in a plastic bag and another ‘outer blend can.’ Another way of immobilizing plutonium is the Hot Isostatic Pressing method, which is being developed in the UK and utilizes radiation-resistant, low-solubility ceramic. After plutonium has been immobilized, it is safer to bury it underground than keep it on the surface and Prof. von Hippel mentioned the deep borehole disposal method which uses techniques developed for drilling oil and geothermal wells that can bore five kilometers into the earth. In the US, however, plans for a demonstration project of this method of radioactive waste disposal were rejected by local governments.
Prof. von Hippel stressed that the main lesson for Japan is that separated plutonium is extremely difficult to dispose of and that it is definitely better not to separate any more than is already stockpiled. Instead of sending spent fuel from the nation’s nuclear power plants to Rokkasho for reprocessing, it would be safer and much cheaper and more efficient to set up dry cask storage for the spent fuel onsite at the plant. Prof. von Hippel showed us successful examples of this method in the US and suggested that there were moves in this direction in Japan as well.
Prof. von Hippel’s detailed technical solutions were very convincing. Yet despite the dangers of holding such a large plutonium stockpile (47 metric tons, enough for approximately 6,000 nuclear weapons), despite the massive costs involved and despite having no concrete viable plans as to how to actually use the separated plutonium, official Japanese government policy is to continue to separate even more plutonium at the Rokkasho Reprocessing Plant, which is currently due to commence operations in 2021.
In the panel discussion which followed Prof. von Hippel’s presentation, Prof. Oguma agreed that reprocessing was most certainly problematic, but, he pointed out, it will be extremely difficult to just put up onsite storage of spent fuel, no matter how reasonable a technical solution it is. Political consent must be gained from the people in communities, which will not just be hosting the nuclear power plant, but will be asked to store its radioactive waste as well. As Prof. Oguma pointed out, especially post-Fukushima Daiichi, no one trusts the Japanese Government’s nuclear policy and the likelihood that they will agree to yet another imposition that can be perceived to be long-term and dangerous, is very low. Much of the Japanese public also believes that onsite storage is merely an excuse for the nuclear industry to keep afloat. If spent fuel pools fill up, utilities will not be able to operate their plants. For many activists this is one way of closing them down, which is their main aim. Prof. Oguma argued that a minimum requirement for any form of political consent to onsite storage would be a clear commitment by the government to phase out all nuclear power by a fixed date, so that the final amount of waste can be determined and will not just keep growing, along with the burden on local people.
This is a significant difference in perspective. Prof. von Hippel’s main aim is to stop reprocessing and reduce stocks of separated plutonium, even if nuclear power generation continues, but Prof. Oguma claims that without an overall reassessment of the entire nuclear power policy it will be impossible to gain political consent for Prof. von Hippel’s proposed onsite storage.
The economics is not as straightforward as it sounds either. While it is undoubtedly cheaper, in a purely mathematical sense, to simply dispose of spent fuel as waste, instead of reprocess it and fabricate MOX fuel, the accounting systems of utilities make the more efficient alternative of direct disposal very difficult. At the moment, spent fuel is counted as an asset on utility balance sheets under the premise that it will become MOX fuel. If reprocessing is officially abandoned, all of the spent fuel ‘assets’ will become ‘liabilities’ and many utilities will be facing possible bankruptcy. Prof. Oguma suggested that the only way to overcome all these political and economic barriers is for the government to disclose all information on nuclear power and reprocessing and to conduct an open public debate on how to proceed. If a public consensus is reached, based on all the scientific, technical and economic data available, then reprocessing should be stopped.
CNIC’s Hajime Matsukubo pointed out that the Japanese government’s accountability crisis was not just domestic, but international. Building up such large stocks of plutonium at huge cost and with no credible purpose inevitably makes neighboring countries suspect Japan’s intentions. Indeed documents recently revealed show that the present Vice Minister of the Ministry of Foreign Affairs has long been an advocate of Japan becoming a nuclear weapons state. Japan’s opposition to President Obama’s proposal that the US adopt a no first-use of nuclear weapons policy, was reported in the Japanese media. Thus Japan’s credibility as a strong advocator of non-proliferation is already failing and the plan to separate even more plutonium at Rokkasho could easily provoke a regional nuclear arms race, destabilizing the region, just as hopes rise that the situation in North Korea may improve.
Mr. Matsukubo also pointed out that Japan is the only non-nuclear weapons state that is permitted to separate plutonium under the US-Japan Nuclear Cooperation (123) Agreement. This creates double standards which weaken the entire global non-proliferation regime. For example, Saudi Arabia is negotiating a 123 Agreement with the US and demands that it also be allowed to reprocess spent fuel ‘like Japan.’
For all of the above safety, economic and non-proliferation reasons, it would seem that there is plenty of ammunition for the movement against reprocessing. Indeed, Mr. Matsukubo said that in many ways it should be easier to stop reprocessing than stop nuclear power generation. Why hasn’t this happened? As well as the difficulties mentioned by Prof. Oguma, there is also the factor that the movement against reprocessing in Japan has not been as strong as the movement against nuclear power. Reprocessing seems like a more convoluted, more removed issue, perhaps difficult for people to grasp and focus on. All speakers agreed that the movement against reprocessing must be strengthened. The first thing that must be done to achieve this is to raise awareness and understanding regarding this issue within the broader anti-nuclear movement (both power generation and weapons) and the general public. Providing accurate information on the nuclear fuel cycle in a format that people can understand is the vital first step. As many people as possible must be informed about the costs, the dangers and the alternatives. The movement must be strong enough to demand that governments and utilities disclose all data, engage in an open debate and commit to implementing the consensus which emerges.
Prof. Oguma said that he and many other activists in Japan were committed to conveying the messages of Fukushima to the larger world, and to contributing to international solidarity on ending nuclear power. This also includes understanding how other countries see Japan. The plutonium issue is one that has particularly strong international impacts and implications and by pursuing this present policy the Japanese government is only damaging Japan’s international credibility, especially regarding non-proliferation.
The seminar concluded that, whether on an international level or a domestic one, the Japanese government must restore accountability and democracy, it must formulate a responsible nuclear policy that is demonstrably safe, economic and realistic and which has the consent of the people. Viable technical alternatives to reprocessing spent fuel are available but can only be implemented through raising awareness and a change in political will, which as a movement, we must focus on with added strength.
The spending bill, which includes appropriations for military construction and other federal departments, contains $267 million to restart the licensing process to open the Yucca Mountain nuclear repository in Nye County, about 90 miles northwest of Las Vegas.
An amendment to strip that spending from the bill died on a voice vote.
The amendment was filed by Rep. Ruben Kihuen and supported by Rep. Dina Titus and Rep. Jacky Rosen, all Nevada Democrats.
A Senate spending bill approved last month does not include funding for Yucca Mountain.
Differences in the two bills must be reconciled by a House-Senate conference committee.
The nuclear industry and the U.S. Nuclear Regulatory Commission are threatening to restart Pennsylvania’s permanently closed and decommissioning Three Mile Island Unit 1 nuclear power station. Three expert speakers will present the resistance to this dangerous misadventure in a webinar hosted by the Clamshell Alliance, Beyond Nuclear and Massachusetts Peace Action.