nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

‘Long journey ahead’ for nuclear plant clean-up

Piers Hopkirk, BBC News, Dungeness, 16 Dec 24

It took about 16 years to build Dungeness B nuclear power station, but to return the site to its original state will take nearly a century.

This is the scale of the task facing EDF as the company continues the process of removing the uranium from this decades-old facility that sits on a remote headland on the Kent coast.

The turbines stopped turning at Dungeness in 2018 and, with the decision taken to cease electricity production, the process of defueling the plant has begun.

In the giant reactor hall the scale of the task becomes apparent.

Buried under the floor are the uranium-filled fuel assemblies that powered the station’s two nuclear reactors.

There are more than 400 rod-filled assemblies in each reactor and it will take six years to safely remove them all.

It is done with the help of a giant 2,000 tonne crane that will carefully lift each one out before moving them into another part of the plant to cool.

Plant Manager, Paul Windle, said: “So far we have removed around 25% of the fuel from one reactor.

“We have got a long journey ahead.”

From the reactor hall the fuel ends up in an area called the ponds.

The fuel, still hot, is stored under water here for 90 days before it is deemed safe enough to be placed into steel flasks which will be moved on to lorries to begin the journey to a nuclear waste facility at Sellafield in Cumbria.

Dungeness B was the first advanced gas cooled nuclear reactor to start construction in the UK.

It was at the vanguard of 20th Century nuclear power generation.

However, in the face of technical challenges that were seen to be too expensive and complicated to address, the decision was taken by EDF to halt energy production………………………………………………………….. https://www.bbc.co.uk/news/articles/cz7qvderej9o

December 20, 2024 Posted by | decommission reactor, UK | Leave a comment

Explosives speed Sizewell A turbine hall decommissioning

WNN, Friday, 6 December 2024

More than 1200 holes were drilled and 700 kilogrammes of explosive used for the demolition of large concrete plinths in the turbine hall of Sizewell A nuclear power plant in the UK.

Nuclear Restoration Services said it was the largest use of explosives on a nuclear site for conventional demolition purposes in decades.

After the holes were drilled into the plinths, the charges were set and covered for the detonation, which was all planned and carried out with Office for Nuclear Regulation (ONR) oversight.

A series of test blasts had to take place and special detonator timings designed to meet nuclear site regulations for air overpressure and ground vibration, with Offive for Nuclear Regulation (ONR) having placed a hold point on the work until they were sure any risks from the novel operation had been minimised.

The ONR said that following the blasts, the huge turbine supporting concrete bases can be removed using heavy machinery within two weeks, rather than “deploying older and slower methods of drilling the structure apart which would have taken several months”.

Sizewell A’s twin reactors shut down in 2006 after 40 years of operation. Planning consent was given to demolish the turbine hall and electrical annexe in August and more than 35 miles of cabling and 8000 scaffolding boards, clips and pipes have been taken out………………………….. https://www.world-nuclear-news.org/articles/explosives-used-in-sizewell-a-turbine-hall-decommissioning

December 9, 2024 Posted by | decommission reactor, UK | Leave a comment

Decommissioning old nuclear sites to cost £130bn in blow to Miliband

The figures mean the cost of the UK’s nuclear clean-up alone is close to the total value of electricity produced by atomic power stations since the 1950s.

If the cost of building Britain’s 20-odd past and present nuclear power stations were included – around £30bn each in today’s money – the total cost of several hundred billion pounds would far exceed the value of the power produced, say experts.

Expense to taxpayer of cleaning up former power plants is higher than previously estimated, say auditors

Jonathan Leake, Telegraph, 29 Nov 24

Ed Miliband faces a bill of almost £130bn to clean up Britain’s old nuclear sites after estimated costs jumped.

It will cost £128.8bn to safely wind down old facilities, according to an investigation by the National Audit Office (NAO) – £23.5bn more than previously expected, after factoring in the cost of shutting eight power stations that are currently operational.

Seven nuclear stations are due to shut down in 2028 at which point operator EDF, France’s state-owned energy firm, will hand them back to the British Government for decommissioning.

Another station, Sizewell B, is expected to keep operating into the 2030s when it too will be decommissioned at taxpayer expense.

The NAO report, which looked at the overall operation of Mr Miliband’s Department for Energy Security and Net Zero (Desnz), said: “The current best estimate is that the eight existing sites will each cost £23.5bn to defuel and decommission.”

This is in addition to £105.3bn already set aside for dealing with other legacy projects, chiefly waste stockpiled at Sellafield in Cumbria.

Desnz oversees a Nuclear Liabilities Fund set up to save the money needed for decommissioning the eight stations, but the NAO said this had proven woefully inadequate.

It also warned that the final costs and taxpayer contributions could rise even higher.

The NAO said: “Costs could rise further, particularly if defuelling takes longer than planned … There is a risk that further taxpayer contributions may be required.”

However, the cost of decommissioning the UK’s remaining working nuclear stations is dwarfed by the amount which the NAO found was needed for dealing with legacy waste since the 1950s.

About 70pc of the costs relate to the Sellafield site in Cumbria, where thousands of tonnes of highly radioactive waste are stored in buildings and cooling ponds that are up to 70 years old – many considered extremely hazardous.

The figures mean the cost of the UK’s nuclear clean-up alone is close to the total value of electricity produced by atomic power stations since the 1950s.

Figures released by the Department of Energy and Climate Change show that since Britain’s first nuclear power station opened in 1956, they have generated 2.6bn megawatt hours (MWh) of electricity with a wholesale value of about £200bn at today’s prices.

If the cost of building Britain’s 20-odd past and present nuclear power stations were included – around £30bn each in today’s money – the total cost of several hundred billion pounds would far exceed the value of the power produced, say experts.

The NAO report also looked at the system of Contracts for Difference (CfD) – a financing method created by the UK to guarantee investors in wind farms, solar farms and nuclear power stations sufficient income.

Such schemes, it warned, were already set to cost consumers £89bn by the 2030s – but the final sums could be far higher because of unreliable estimates for the amount of power likely to be produced……………………… https://www.telegraph.co.uk/business/2024/11/29/decommissioning-old-nuclear-sites-to-cost-130bn-in-blow/

December 4, 2024 Posted by | decommission reactor, Reference, UK | Leave a comment

Hunterston B decommissioning approved

 The UK Office for Nuclear Regulation (ONR) has granted consent to EDF
Energy’s application to start decommissioning the Hunterston B nuclear
power station. This follows a public consultation and a detailed assessment
by ONR specialist inspectors of EDF’s environmental statement.

The
statement included a detailed environmental impact assessment (EIA) for the
proposed decommissioning project at the North Ayrshire site in Scotland,
along with mitigation measures designed to prevent or reduce any
significant adverse environmental impacts.

The EIA identified two
significant impacts during decommissioning: temporary adverse visual impact
of dismantling activities of the power station for local residents and the
socioeconomic effects on the regional employment market and workers at
Hunterston B released from their roles during phases of the project. ONR
said it is satisfied that the environmental statement proposes adequate
mitigation measures to address these factors and considers the statement to
be complete, of the right quality, and in line with relevant good
practices.

 Nuclear Engineering International 19th Nov 2024 https://www.neimagazine.com/news/hunterston-b-decommissioning-approved/

November 23, 2024 Posted by | decommission reactor, UK | Leave a comment

Nuclear Decommissioning Services Market Expected to Reach $11.79 Billion by 2034 – BIS Research

Industry Today 12th Nov 2024

As nuclear facilities worldwide reach the end of their operational lives, the nuclear decommissioning services market is witnessing substantial growth. The Nuclear Decommissioning Services Market is projected to grow from $6.70 billion in 2024 to $11.79 billion by 2034, fueled by the rising number of decommissioned nuclear facilities and the increasing emphasis on sustainable practices.

Published 12 November 2024

Market Overview 

Market Size and Growth Rate 

The Nuclear Decommissioning Services Market is projected to grow from $6.70 billion in 2024 to $11.79 billion by 2034, at a CAGR of 5.81% during the forecast period. This growth is driven by the escalating number of decommissioned reactors and a shift toward stringent regulatory frameworks prioritizing safe and sustainable decommissioning processes. …………………………………………………..

Demand Drivers 

The market is significantly driven by the retirement of aging nuclear facilities, increased regulatory scrutiny, and advancements in decommissioning technology. Environmental sustainability mandates are pushing the demand for efficient and compliant decommissioning solutions. 

Challenges 

Complex regulatory requirements and high costs remain key challenges. Additionally, the intricate nature of nuclear waste disposal raises concerns over potential delays and budget overruns in large-scale decommissioning projects. …………………………………………………………………………………………………….

The successful [whaaa-aa-aat!] decommissioning of Japan’s Fukushima Daiichi nuclear power plant highlights the potential for advanced decommissioning technology to manage complex sites safely and efficiently. ……………………………………………..https://industrytoday.co.uk/energy_and_environment/nuclear-decommissioning-services-market-expected-to-reach-1179-billion-by-2034-bis-research

November 15, 2024 Posted by | business and costs, decommission reactor | Leave a comment

Cost of maintaining decommissioned nuclear submarines

UK Defence Journal 29th Oct 2024

Graeme Downie, Labour MP for Dunfermline and Dollar, recently raised a question regarding the financial burden of maintaining decommissioned nuclear submarines at two key UK facilities: Rosyth and Devonport. Specifically, he inquired about the annual costs associated with these sites.

In response, Defence Minister Maria Eagle provided the figures for the financial year 2023-24, explaining that “the annual cost for maintaining decommissioned submarines varies each year depending on the respective maintenance requirements.”

For the last financial year, £1.7 million was spent at Rosyth, while the maintenance costs at Devonport were significantly higher, totalling £7.1 million.

These figures highlight the ongoing financial commitment required to manage the UK’s decommissioned nuclear submarines, a task dependent on the maintenance needs of each vessel and the infrastructure of the respective facilities.

Additionally, during a recent exchange in the House of Lords, Lord Coaker expressed the urgency for the UK to expedite its nuclear submarine dismantling programme, addressing the slow progress in decommissioning and dismantling outdated submarines.

Responding to a question from Baroness Bryan of Partick, he outlined the current challenges and ongoing efforts to dismantle the aging fleet, currently spread across Scotland and Devonport, and acknowledged that, without significant changes, the timeline could stretch into decades.

Baroness Bryan highlighted widespread concerns, pointing out that many submarines have been out of service for years or even decades without being dismantled. She cited, for example, the case of a Dreadnought-class submarine stationed at Rosyth since 1980, a delay emblematic of the broader issue. “There remains real concern that not one of these submarines has yet been dismantled,” she noted, adding that with the rate of dismantling, “it will take decades to dismantle the boats remaining in both Scotland and Devonport.”……………………………………………………..
https://ukdefencejournal.org.uk/cost-of-maintaining-decommissioned-nuclear-submarines

November 1, 2024 Posted by | business and costs, decommission reactor, UK | Leave a comment

MP seeks answers on Submarine Dismantling Project in Rosyth

26th October, By Ally McRoberts

THE UK Government have been asked what steps they’re taking to keep West Fife safe and mitigate the “potential risks” posed by the Submarine Dismantling Project.

Radioactive waste is being removed from old nuclear subs at Rosyth Dockyard and Babcock have just applied for permission for more hazardous material to be taken out in the next stage.

Christine Jardine, Lib Dem MP for Edinburgh West, submitted a question at Westminster: “To ask the Secretary of State for Defence (John Healey), what steps his department is taking to (a) ensure the safety of and (b) mitigate potential risks posed by the decommissioning of nuclear submarines at Rosyth Royal Dockyard for surrounding residential areas.”

 On Mr Healey’s
behalf, Maria Eagle, Minister for Defence Procurement, replied: “All the
submarines currently stored at Rosyth have already been de-fuelled, which
has significantly reduced overall potential risk. “Further, steps include
contractual requirements with Babcock International around safety and
environmental factors. “These include regular sampling of surrounding
waters and beaches, and dismantling one boat as a demonstrator to determine
the safest methods before starting on other boats.

 Dunfermline Press 26th Oct 2024, https://www.dunfermlinepress.com/news/24679595.mp-seeks-answers-submarine-dismantling-project-rosyth/

October 29, 2024 Posted by | decommission reactor, UK, weapons and war | Leave a comment

  Last German nuclear power plant to receives decommissioning and dismantling permit

WNN Thursday, 24 October 2024


The Schleswig-Holstein Ministry for Energy Transition, Climate Protection, Environment and Nature has issued the first decommissioning and dismantling permit to PreussenElektra for the Brokdorf nuclear power plant. Brokdorf is the last German nuclear power plant to receive this approval and begin dismantling.

PreussenElektra – a subsidiary of EOn Group – applied for approval to decommission and dismantle the 1410 MWe pressurised water reactor in December 2017. The plant was shut down on 31 December 2021.

Phase 1 of the plant’s decommissioning and dismantling has now been approved. This includes the decommissioning and dismantling of the plant components that are no longer required and subject to nuclear regulatory supervision, with the exception of the reactor pressure vessel and the biological shield.

Since Brokdorf’s closure, the conditions for dismantling the plant have been created in close coordination with the authorities. These include the decontamination of the primary cooling circuit, systems and plant components that are no longer required have been taken out of service, and the workforce has been adjusted. A large proportion of the fuel elements still present in the plant have already been moved to the interim storage facility on site and replacement systems for the plant’s energy supply have been installed.

…………….. The next steps will be to create new logistics routes within the control area and set up a waste processing centre for the dismantled masses. In addition, systems and plant components that are no longer required will be prepared for dismantling.

A second dismantling permit is required to dismantle the reactor pressure vessel and the biological shield. This requires the removal of all fuel elements and special fuel rods, which are expected to be transported to the interim storage facility at the site in 2025. PreussenElektra submitted the application for the second dismantling permit on 30 August this year. This is currently being examined by independent experts.

………………………………. In December last year, PreussenElektra, together with EOn group companies, announced plans for the construction at the Brokdorf site of the largest battery storage facility in the EU to date. The facility – to store electricity from renewable sources – is to be expanded in two stages to up to 800 MW of power and a storage capacity of up to 1600 MWh. Commissioning could begin as early as 2026.  https://www.world-nuclear-news.org/articles/decommissioning-permit-granted-for-brokdorf-plant

October 26, 2024 Posted by | decommission reactor, Germany | Leave a comment

First ex-Royal Navy nuclear submarine to be disposed of enters final dismantling phase.

 Navy Lookout 15th Oct 2024 https://www.navylookout.com/first-ex-royal-navy-nuclear-submarine-to-be-disposed-of-enters-final-dismantling-phase/

Work has started on the third and final phase of the project to dismantle ex-HMS Swiftsure. As the demonstrator project for the dismantling programme, she will be the first former RN SSN to be fully disposed of.

The glacial project to safely scrap the growing fleet of decommissioned boats has finally begun to make some progress at Rosyth in the last few years. Each submarine will undergo a three-step process which involves Low Level Radioactive Waste (LLW) being removed first. The second and most demanding stage involves the removal of the Reactor Pressure Vessel that holds the reactor core and is classed as Intermediate Level Radioactive Waste (ILW).

Work has started on the third and final phase of the project to dismantle ex-HMS Swiftsure. As the demonstrator project for the dismantling programme, she will be the first former RN SSN to be fully disposed of.

The glacial project to safely scrap the growing fleet of decommissioned boats has finally begun to make some progress at Rosyth in the last few years. Each submarine will undergo a three-step process which involves Low Level Radioactive Waste (LLW) being removed first. The second and most demanding stage involves the removal of the Reactor Pressure Vessel that holds the reactor core and is classed as Intermediate Level Radioactive Waste (ILW).

Swiftsure’s disposal is a notable achievement as the first Pressurised Water Reactor (PWR) anywhere in the world to be dismantled. Other nations use a much simpler process and cut the entire reactor compartment out of the submarine and transport it structurally complete for burial in land storage facilities. The US has successfully disposed of over 130 nuclear ships and submarines since the 1980s. The Russians have disposed of over 190 Soviet-era boats (with some international assistance) since the 1990s while France has already disposed of 3 boats from their much smaller numbers.

Besides the progress with Swifsure, LLW has been safely removed from ex-HMS Resolution, Revenge and Repulse. As experience has been gained working on successive boats techniques have been refined and more waste has been managed to final disposal at reduced cost. The optimisation of the process allowed 50% greater tonnage of waste to be removed in 75% of the time it took for Swiftsure. So far the work has been completed safely on budget and on time. Work has yet to begin on ex-HMS Dreadnought, Churchill and Renown still afloat in the basin at Rosyth.

While there is positive progress at Rosyth, 14 Dock at Devonport is still not ready to accept the first boat to begin defuelling and dismantling. There are now 15 decommissioned submarines filling up the basins in Plymouth (soon to be 16 when HMS Triumph goes in 2025). Work to get rid of this legacy cannot start soon enough. At least the lessons learned in Rosyth should give the teams at Devonport an advantage although the majority of these boats still have their nuclear fuel on board and will have to undergo a 4-stage process.

October 20, 2024 Posted by | decommission reactor, UK, weapons and war | Leave a comment

First civil nuclear site decommissioned in the UK

 It took 10 years for Veolia and Imperial College London to complete the
decommissioning of the first civil nuclear site in the UK. The Reactor
Centre at Imperial’s Silwood Park eco-campus in Ascot housed the UK’s
last civilian nuclear reactor for almost 50 years until it closed in 2012.

The long and complex project required demolition of the reactor, safely
managing hazardous materials, and restoring the site to its original state
to make it safe for public use. Veolia’s specialist decommissioning team,
KDC, supported Imperial in planning the complex project, which included the
cutting operations to reduce the reactor concrete shielding, removal and
demolition of the facility. The operation required the design and use of
new equipment to safely deconstruct the facility.

 Construction Management 1st Oct 2024,
https://constructionmanagement.co.uk/first-civil-nuclear-site-decommissioned-in-the-uk/

October 4, 2024 Posted by | decommission reactor, UK | Leave a comment

Nuclear plant’s decommissioning could take 95 years

Daniel Mumby, Local Democracy Reporting Service, 19 Sept 24, https://www.bbc.com/news/articles/c8699v4dvexo

Residents are being asked for their views on how a former nuclear power station should be safely decommissioned.

The Hinkley Point B facility, which lies on the Somerset coast north of Stogursey, ceased operations in August 2022, after cracks developed in the plant’s graphite cores, creating potential safety concerns.

EDF Energy, which owns the facility, has applied to the Office for Nuclear Regulation (ONR) for formal permission to decommission the site, which could take about 95 years.

Somerset residents now have three months to voice their views.

Under the proposals, Hinkley Point B, which opened in 1976, could be decommissioned in three phases.

The first phase, which will last until 2038, includes the dismantling of all buildings and plant materials except for the site’s safestore structure. This facility will be used to store and manage the residential nuclear waste from the power station.

The second phase will see “a period of relative inactivity” of up to 70 years from 2039, to allow for the radioactive materials within the safestore to safely decay, according to the Local Democracy Reporting Service.

While physical activity within the site will be minimal during this phase, the former power station will remain under close surveillance with “periodic maintenance interventions” to prevent any risk to health or national security.

The third and final phase will see the former reactor and debris vaults being dismantled and removed and any final landscaping work being completed – with EDF estimating that this will be finished by 2118.

The consultation is running until 9 December, with the ONR expected to publish its formal response in early 2025.

Hinkley Point C

EDF is currently building Hinkley Point C, which has a target completion date of June 2027.

Costing about £46bn, it is expected to generate enough electricity to supply some six million homes for the next 60 years.

September 23, 2024 Posted by | decommission reactor, UK | Leave a comment

More than 200 Russian nuclear submarines have been dismantled.

Rosatom has said that its work to resolve nuclear legacy issues in
Russia’s Far East has been successful, including the dismantling of dozens
of decommissioned nuclear-powered submarines. In total, the state nuclear
corporation said, 202 Russian nuclear-powered submarines decommissioned
before 2022 have been dismantled, including 82 from the country’s Far East.

It added that all used nuclear fuel has been removed from the region. The
reactor compartments of the dismantled nuclear submarines have been placed
in specially constructed containers in a secure site on land, and are
subject to radiation monitoring and maintenance, such as checking the
condition of the anti-corrosion protective coating, the company said.

 World Nuclear News 11th Sept 2024

https://www.world-nuclear-news.org/articles/more-than-200-russian-nuclear-submarines-have-been-dismantled

September 15, 2024 Posted by | decommission reactor, Russia | Leave a comment

Hinkley Point B: What happens after a nuclear power station stops making electricity?

After shutting down in 2022, the job now is to carefully
remove tonnes of nuclear waste to be transported for storage at Sellafield
in Cumbria. The team is halfway through that task with one reactor empty
and one more to go.

I was given exclusive access to the power station,
getting the chance to travel deep within the bowels of the building and see
something few people outside EDF Energy get to – the cooling ponds, where
spent fuel is cooled down before being sealed for transport and storage.
there will be another couple of years to finish defuelling operations, then
EDF hands this place over to the Nuclear Decommissioning Authority as the
painstaking job of decommissioning will continue for many years.

 ITV 13th Aug 2024

https://www.itv.com/news/westcountry/2024-08-13/what-happens-after-a-nuclear-power-station-stops-making-electricity

August 16, 2024 Posted by | decommission reactor, UK | Leave a comment

Germany may take another 50 years to find final repository for waste from shuttered nuclear power

Sören Amelang, Aug 9, 2024, https://reneweconomy.com.au/germany-may-take-another-50-years-to-find-final-repository-for-waste-from-shuttered-nuclear-power/

Germany’s ongoing hunt for a final repository for highly radioactive nuclear waste could last until the 2070s, a report has warned.

The report by the Institute for Applied Ecology (Öko-Institut), which was commissioned by the country’s Federal Office for the Safety of Nuclear Waste Management (BASE), said a decision on a location can be expected in 2074 at the earliest under ideal conditions, reports Zeit Online.

This would be more than 40 years later than the original 2031 target, which the government already gave up almost two years ago. The environment ministry said the report did not take into consideration significant progress in efforts to shorten the search, for example by saving time on long exploration periods.

The ministry declared in November 2022 that the search won’t be completed in 2031, following a paper by the Federal Company for Radioactive Waste Disposal (BGE) that estimated the search could take until 2046 or, in another scenario, until 2068.

The next step will be for the BGE to propose shortlisted siting regions at the end of 2027, the ministry said. “This is the right time to discuss and regulate further acceleration in a transparent manner. A great deal of time can be saved, particularly in the surface and underground exploration,” it added.

But Journalist Bernward Janzing wrote in a commentary it was questionable how much the “scientifically well designed” process can be accelerated without compromising high safety standards.

Germany completed its nuclear phase-out last year and will now have to store 1,900 large containers, or around 28,100 cubic metres (m3), of high-level radioactive waste by 2080, when all its nuclear power stations and many research facilities will have been finally decommissioned and the fuel elements treated at other facilities.

Highly radioactive, heat-generating waste accounts for only five percent of Germany’s radioactive refuse, but is responsible for 99 percent of the radiation. It is currently held at temporary storage facilities near decommissioned nuclear power stations and in central interim repositories.

Construction of a repository following a location decision is scheduled to take about 20 years, according to current plans. The process of transporting and storing thousands of casks in the final repository will then take decades more.

Experts from a parliamentary storage commission said that loading and sealing the repository could be expected to last “well into the next century”.

August 11, 2024 Posted by | decommission reactor, Germany | Leave a comment

Radiation levels assessed for on-site burial plan at old nuclear power station

Demolition and disposal is due to start in 2030

Andrew Forgrave, 14 July 2024  https://www.dailypost.co.uk/news/north-wales-news/radiation-levels-assessed-site-burial-29523489

Potential radiation levels arising from the next-stage decommissioning of a former nuclear power station have been assessed as within safety thresholds. Magnox, owner of the Trawsfynydd site in Gwynedd, is aiming to demolish and infill the site’s ponds complex before capping it with concrete.

In two scenarios – for future site occupiers and for some local wildlife – the UK’s Nuclear Restoration Services (NRS) said dosages could exceed safe levels. But the company said its own assessments were cautious and under criteria set by Natural Resources Wales (NRW) all safety thresholds were met.

Trawsfynydd stopped generating electricity in 1991 after operating for 26 years. Years of demolition and on-site disposal are planned. The reactor buildings are scheduled for completion by 2055 with final site clearance activities ending by 2070. The site will then be released from radioactive substances regulation “some time after that”.

First to be tackled will be the ponds complex – a set of buildings running alongside the site’s two reactor buildings. This is due for demolition in 2030 and this could take up to two years.

For this Magnox needs to amend its environmental permit and has applied to NRW for permission. A four-week public consultation was launched this week.

Martin Cox, NRW’s head of operations for northwest Wales, said: “We understand this permit variation is of particular interest to the public and local community. As the regulator for this application we are committed to keeping the community and environment healthy.

We must be satisfied the proposed demolition, disposal, and capping is done in ways that are safe and meet our standards for the protection of people and the environment while allowing the site to be released from radioactive substances regulation in the future.”

The ponds complex contains concrete pools formerly used to cool and store used nuclear fuel before it was sent to Sellafield in Cumbria for reprocessing. This process ended in 1997 and 99.9% of all radioactive waste has been removed from the site.

Below the ponds and storage vaults are box-like structures capable of storing about 5,000 cubic metres of material, which is twice the volume of an Olympic-sized swimming pool. The plan is to fill these with “slightly radioactive” broken concrete from the demolished structures above them.

Magnox has submitted a “site-wide environmental safety case”, supported by more than 30 technical reports, to NRW. One includes radioactivity estimates by NRS for the ponds complex spanning four scenarios: natural evolution, human intrusion, site occupancy, and environmental impact.

Dosage levels for “inadvertent” human intrusion were found to meet safety thresholds “in all credible scenarios”. Screening criteria was also met for wildlife and plants in the surrounding area apart from the uppermost stretch of Afon Tafarn-helyg, a tributary of the Afon Dwyryd. Magnox noted its criteria was stricter that NRW’s under which the threshold would be met.

For site occupiers Magnox said a few features, just below ground, might breach its safety guidelines but not NRW’s. It added: “This exceedance is for a configuration that cautiously assumes a 0.15 m (minimum) cap thickness. Moreover such worst-case dose rates would be expected to drop below 0.017 mSv/year after around 100 years beyond the assumed end-state date (2083) and the probability of receiving such a dose is expected to be low.”

In any case radioactivity estimates are expected to decrease prior to demolition as further decommissioning continues. Additional borehole investigations are being conducted this year beneath the ponds complex to get a better understanding of groundwater flows. NRS added: “In short, the proposed disposals will be safe while they are being implemented, for the decades while the site remains under regulatory control, and then afterwards into the indefinite future.”

When considering Magnox’s bid for a permit variation to allow on-site disposal at Trawsfynydd NRW will be consulting with experts in Public Health Wales and the Office of Nuclear Regulation. The process is expected to be “lengthy”.

You can take part in the consultation, and view related documents, here

July 15, 2024 Posted by | decommission reactor, UK | Leave a comment