Uncertainty over future costs of Vogtle Nuclear Station
Budget on Georgia nuclear plant level, uncertainty remains, WT, By RAY HENRY – Associated Press – Friday, August 28, 2015 ATLANTA (AP) – Georgia Power reported Friday the cost to build a nuclear plant was holding steady, but there’s significant uncertainty whether those numbers will stick.
The Southern Co. subsidiary owns a 46 percent stake in two new reactors under construction at Plant Vogtle, near Augusta. The utility now expects to spend roughly $7.5 billion to finish the project, or about 22 percent more than originally expected. The budget released Friday declined slightly from the company’s last financial filing in February. If they hold, the level spending figures would be welcome news for investors and customers. By law, Georgia Power’s customers will ultimately pay for construction costs unless state regulators object and force losses onto shareholders. However, project watchdogs say multiple problems could still raise costs.
The nuclear plants under construction in Georgia and South Carolina were approved before natural gas prices plummeted. As it became cheaper to build gas-fired plants, major power companies scrubbed plans to build nuclear reactors nationwide. If it wants to grow, the nuclear industry must prove it can build without the construction delays and cost overruns common years ago.
So far, the proof is lacking. The companies designing and building the plant, Westinghouse Electric Co. and Chicago Bridge and Iron Co., announced a new construction schedule this year that pushed back the completion of the first reactor in Georgia to June 2019, followed by the second reactor a year later. That means the construction effort is now running about three years behind schedule.
Even that latest schedule has slipped by three months……..Utilities in South Carolina building an identical nuclear plant have run into similar delays and cost overruns. South Carolina Electric & Gas Co. reported this month that its share of costs had increased by roughly $1.1 billion. http://www.washingtontimes.com/news/2015/aug/28/budget-on-georgia-nuclear-plant-level-uncertainty-/
Radiation exposure to Fukushima workers and the community
Fukushima today: A first-person account from the field and the conference table, Bulletin of the Atomic Scientists, 26 Aug 15 Subrata Ghoshroy “……….the building containing the failed reactors has radiation levels as high as 4,000 to 5,000 milliSieverts per hour (400,000 to 500,000 millirems per hour), making even the operation of robots difficult. In fact, two power company robots had to be abandoned while inside the depths of the plant. And some spots, such as inside the primary containment vessel, went as high as 9.7 Sieverts per hour (970,000 millirems per hour). In addition, it has not been possible to precisely locate the melted core. (Another conference speaker, Jun Tateno, who was a former research scientist with the Japanese Atomic Energy Research Institute, accused the government of suppressing voices from the scientific community that were critical of the safety of power plants. He said that we have reached a situation in which we do not even know how much plutonium is in the core.) In the meantime, huge amounts of water must be pumped in to keep the reactors cool; this liquid then mixes with ground water, contaminating it as a result.
The picture is not much better when it comes to the land. In an effort to decontaminate residential areas, radioactive soil is being dug up from approximately 1,000 sites. The government wants to consolidate this contaminated material in semi-permanent storage sites in the “difficult-to-return zones” in Futaba and Okuma towns. Local residents, meanwhile, fear that these could turn into permanent repositories of radioactive material……….
We were told that most workers did not wear dosimeters to record their cumulative radiation dose. There was good money to be made in decontamination work. They did not want to know.
But if one does the math, what the workers and their supervisors were ignoring—or were being told to ignore—could be significant. If a person spent one week working at this part of a supposedly safe parking area for 8 hours per day, then he or she would have been exposed to 40 microSieverts per day. And if that person was there for a 5-day workweek, then over the course of a single week that person would have been exposed to 200 microSieverts. In a year, that person could receive 10 milliSieverts, a significant dose. Of course, scientists are rightly cautious of such “anecdotal” evidence; our Geiger counter readings could have been off, or the machine calibrated incorrectly, or some other source of error introduced—though I doubt it because it had earlier read the background correctly. But the result of such quick and dirty, back-of-the-envelope calculations for what is supposedly a low-risk parking area, well away from the restricted hot zones, do give one pause—especially as the ongoing lack of dosimeters means that no one really knows a given individual’s cumulative dose. The amount of exposure to a thing that you cannot see, hear, smell, taste, or feel sneaks up on you. Even when you think you are safe, you are not.
If nothing else, the fact that a simple, random spot-check registered so highly is an eye-opener, and counter to what has been officially portrayed. ……..An important item seemed to lie further down in the article, which noted: “However, the health ministry said the number of workers surveyed is different from the total number of cleanup personnel reported by the Environment Ministry, which could mean the association failed to record radiation doses of all individuals working around the Fukushima plant.”
No wonder there has been public distrust and charges of a lack of clarity about the radiation clean-up operation, as can be seen in the title of a 2013 Guardian newspaper article: “Life as a Fukushima clean-up worker—radiation, exhaustion, public criticism.”Even when the approximately 7,000 workers involved in the clean-up do wear dosimeters, that is no guarantee of accuracy; there have been reports of a Tokyo Electric Power Company executive who tried to force clean-up workers to manipulate dosimeter readings to artificially low levels by covering their devices with lead shields………http://thebulletin.org/fukushima-today-first-person-account-field-and-conference-table8683#.Vd6Rj7YbwEs.twitter
France’s new nuclear power – not successful at home, so they might try to sell it off to Czech Republic
French foreign minister: EDF to consider participating in building new Czech nuclear reactors US News 23 Aug 15 PRAGUE (AP) — French Foreign Minister Laurent Fabius says his country’s company will consider participating in developing the Czech Republic’s nuclear program.
The Czech government has recently approved a long-term plan to increase the country’s nuclear power production. As part of the plan, the government wants to build one more reactor at the Temelin nuclear plant and another at the Dukovany plant, with an option to build yet another reactor at each plant…..Speaking to reporters after meeting Czech counterpart Lubomir Zaoralek on Sunday, Fabius said it will be state-controlled utility Electricite de France that will be part of a public tender to build the reactors. http://www.usnews.com/news/business/articles/2015/08/23/france-to-consider-helping-czech-nuclear-program
Escalating costs, expanding timelines, cast doubt on the future of modular nuclear construction
Fitch: ‘Failure’ of new nuke construction means fewer plants https://www.snl.com/InteractiveX/Article.aspx?cdid=A-33617164-10551 , Thursday, August 20, 2015 By Matthew Bandyk The troubled construction of new nuclear reactors in Georgia and South Carolina will likely chill the pursuit of more nuclear plants in the U.S., although recent actions by the U.S. EPA and the Department of Energy could improve the outlook over time, according to an analysis by Fitch Ratings.
As a result, there will be less new nuclear to replace the increasing number of retiring plants. Fitch said that the U.S. Energy Information Administration’s forecast of nuclear generation falling by 10,800 MW by 2020 might be too conservative if more plants retire due to local political pressure and the need for costly upgrades.
The nuclear projects at the Vogtle and V.C. Summer plants, the first new nuclear generation built in the U.S. in decades, use the Westinghouse Electric Co. LLC AP1000 reactor design, which promised to be cheaper and more efficient to build than past nuclear plants that saw spiraling cost overruns during construction. In particular, Westinghouse touted the “modern, modular” construction technique in which major plant components would be built off-site as modules, allowing pieces of the project to be completed in parallel and in turn speeding up construction.
But “the recent failure of modular construction to deliver lower prices and shorter timelines will likely keep a cap on U.S. nuclear development into the midterm,” Fitch analysts said in a statement Aug. 20. The Vogtle and Summer projects are each running about three years behind schedule and are now expected to cost a few billion dollars more than originally estimated.
The blame for much of the delays has been centered on subpar work on the modules at facilities like Chicago Bridge & Iron Co. N.V.‘s Lake Charles fabrication facility in Louisiana. CB&I has since shifted work to other facilities, and monitors of the Vogtle project recently reported that the module work has “improved significantly.” But the contractors continue to miss their own deadlines and there is still risk of more delays, the same monitors said.
In addition, four AP1000 reactors under construction in China are also seeing rising costs and delays, Fitch noted.
One of the best hopes for the U.S. nuclear industry comes from the EPA’s recently finalized Clean Power Plan, according to Fitch. The rule allows new nuclear plants and capacity uprates at existing plants to generate credits that states can use to reduce their CO2 emissions levels and comply with the rule. In addition, the DOE continues to try to lower the financing costs for the nuclear industry through loan guarantees. Last year the DOE said it is accepting applications from nuclear developers for $12.5 billion in loan guarantees.
Both the EPA and DOE efforts could “yield growth factors longer term,” Fitch said.
Nuclear plant Vogtle – another cost increase approved – now up to $2.97 billion
Georgia energy regulators approve 12th Plant Vogtle construction update http://www.bizjournals.com/atlanta/blog/capitol_vision/2015/08/georgia-energy-regulators-approve-12th-plant.html?utm_source=Sailthru&utm_medium=email&utm_campaign=Issue:%202015-08-19%20Utility%20Dive%20Newsletter&utm_term=Utility%20Dive
Commissioners voted unanimously to approve $169 million the utility reported spending on the project during the last half of last year. That brings Georgia Power’s cumulative construction and capital costs to date to $2.97 billion.
In approving the 12th semi-annual update Georgia Power has submitted to the PSC since the construction of two additional nuclear reactors at the plant south of Augusta, Ga., was authorized in 2009, the commission rejected requests from environmental and consumer advocacy groups concerned that a 39-month delay in the project’s scheduled completion is driving up customer costs.
Commissioner Stan Wise argued Atlanta-based Georgia Watch’s request that the PSC consider the costs of achieving the same additional electric generating capacity with wind and solar projects as an alternative to nuclear expansion was inappropriate.
“It’s not going to change anything we do at Vogtle,” he said. “Wind and solar are going to run their own course, like any product does.”
The commission voted in 2013 to postpone consideration of who should pay for cost overruns at Plant Vogtle – Georgia Power’s shareholders or its customers – until after the first of the two new nuclear reactors goes into service. Under a revised timetable Georgia Power submitted last winter, that won’t come until 2019.
Hinkley Point C Nuclear scam – UK tax-payers fund Chinese investors

Tory privatisation scams (2): the Hinkley Point C nuclear payola guaranteed by UK taxpayers for Chinese investors http://www.michaelmeacher.info/weblog/2015/08/tory-privatisation-scams-2-the-hinkley-point-c-nuclear-payola-guaranteed-by-uk-taxpayers-for-chinese-investors/
Just how bad a deal this is is shown by the fact that Hinkley will provide just 3 gigawatts of capacity, yet for the same price gas-fired turbines could provide about 50 gigawatts, onshore wind 20 and offshore wind 10. The plant will not open till 2023 at the earliest, well past the date of the most acute energy shortage at the end of this decade. And it will cost as much as the combined bill for Crossrail, the London Olympics and the revamped Terminal 2 at Heathrow – beat that for the most expensive white elephant of modern times!
It’s an anachronistic behemoth from the bygone age of energy dinosaurs when the world is rapidly moving towards distributed power via renewable energy. It’s far too costly, and is it even needed? First there is the UK’s declining demand for power, currently falling at a rate of 1% a year as energy-saving measures steadily take effect. Then there is the expected threefold jump in the UK’s Interconnection capacity with continental Europe by 2022 which increases the ability to import cheaper supplies. And third there is the litany of setbacks in price overruns and huge delays that have afflicted Finland, France and China over EDF’s European Pressurised Reactor which is the same type as is planned for Hinkley Point.
However nothing distracts the Tory nose from a good old-fashioned financial fix behind the scenes, especially when in this case it plays to their abhorrence of UK State involvement in meeting a public need. So Cameron is off to Beijing in October to sign a final deal wit the Chinese president from which only Chinese investors will gain at UK taxpayer expense.
Japan exposing hundreds of young men to radiation – in the cause of promoting the nuclear industry
the level of radiation is so high that my biggest humanitarian concern is that – if the Japanese push to get these plants dismantled quickly – they will burn out hundreds and hundreds of young men. It’s usually young men because that’s how the construction trade is, needlessly. My point is, walk away for a hundred years, then come back in a hundred. By waiting a hundred years you’re reducing the radiation exposure to a significant, young virile gene pool that in my opinion doesn’t deserve to be exposed right now.
There’s a very real human cost to thousands of construction workers who are being exposed and will be exposed. But they have to show the Japanese that they’re dismantling that site because if the Japanese don’t believe it can be cleaned up they won’t let the other plants start back up.
It’s a show. This is all about showing the Japanese that it’s not too bad, and we can run our other forty or so plants fine, trust us. It’s definitely symbolic for the Japanese, but the real reason is the banks want their money back.
This Expert Claims the Japanese Government’s Fukushima Clean Up Is Just “a Show” http://linkis.com/www.vice.com/en_uk/r/5UnqS August 12, 2015 by Thomas Marsh The past couple of weeks have seen two stories draw our attention back to the Fukushima Daiichi nuclear disaster of March 2011, in which three nuclear reactors melted down after the plant was hit by a tsunami. Radioactive material was released in what was the biggest and most disastrous nuclear incident since Chernobyl in 1986.
One story concerned some pictures of deformed daisies near the Fukushima Daiichi site, which trended online for a while and got everyone all hot under the collar about radiation, until it was established that they occur all the time in nature. So no need to worry about that.
The other was a video released by Arnie Gundersen, a former nuclear industry executive and engineer who’s declared Fukushima “the biggest industrial catastrophe in the history of mankind”. In it, he claimed that 23,000-tankers of water contaminated with radioactive isotopes have leaked into the Pacific from the Fukushima Daiichi site since 2011 and will continue to do so for decades – at a rate of three hundred tonnes a day. So maybe start worrying again.
Sure enough, a recent report by the Tokyo Electric Power Company (TEPCO) claimed that concentrations of radioactive isotope Strontium-90 have reached record highs in certain areas of the Pacific Ocean around Fukushima, with levels spiking by about 1,000 percent in three months. Continue reading
Total lifetime costs of Vogtle nuclear station estimated at $65 billion and rising
Vogtle: at $65 billion and counting, it’s a case study of nuclear power’s staggeringly awful economics, Green World, Michael Mariotte August 2, 2015 Georgia is one state that you would think would be wary of nuclear power economics. The first two reactors at Georgia Power’s Vogtle site, which came online in the late 1980s, were a record 800% over budget.
That is a number that is almost impossible to grasp. Nothing goes 800% over budget–in the real world, projects get cancelled well before reaching that point……
Sane people do not let projects get 800% over budget. Unless, perhaps, if someone else is putting up the money. And that’s exactly what happened with the first two Vogtle reactors–the overruns were pushed on to ratepayers; Georgia Power had to eat some small portion of them, but basically ratepayers were forced to pick up the tab.
And in a case of history repeating itself as predicted–as farce–that’s exactly what is happening with the two Vogtle reactors under construction now.
When the project was announced, and when the utilities building the project first applied for taxpayer loans to help finance the project, Southern Company (Georgia Power’s parent) said the two reactors would cost about $14 billion and would be online in 2016 and 2017.
That was back around 2008. Vogtle got its taxpayer loan promise in February 2010 and its construction permit in February 2012. Three and a half years later, Vogtle is more than three years behind schedule–39 months behind, in fact.
And the cost of building Vogtle has, not surprisingly, gone up. Way up. Right now, it’s somewhere around $16 billion and rising fast–the over-budget portion caused by the delays alone is $2 million per day. And as you can see from the photo at the top of the page, taken last Thursday, construction still has quite a long way to go.
Georgia Power already has run through half of its federal loan money, paid for by all U.S. taxpayers, not just Georgia ratepayers. Some of the rest of the taxpayer loan (the loans totaled more than $8 billion) was received later by the other partners, so perhaps they haven’t run through their share yet.
In any case, the supposed point of getting the loan, and of charging ratepayers for construction costs as they are incurred (a concept called Construction Work in Progress, barred in most states), and of building the reactors in the first place, was to save ratepayers money. That’s what Southern Company says anyway.
And they run off numbers and argue that building Vogtle, even with the overruns and delays, will save ratepayers $3 billion compared to building a gas-powered plant, which probably would already be operational, by the way, except that neither it nor Vogtle actually are needed.
But those numbers, despite the utility’s protestations, no longer add up……..
If one–or both–of the reactors gets cancelled before operation, then the negative benefits grow even more. Unless the cancellation occurs before too much more money is spent–then cancellation would turn into a net benefit for the ratepayers by avoiding the costs that have not yet been incurred. Sure, Georgia Power might take a hit and a lot of money that already has been spent would be wasted. But at least ratepayers could breathe easier……..
The economics of nuclear construction are just too staggeringly awful. But it gets worse. Because, as former PSC Commissioner Baker said, the total lifetime cost of Vogtle, including construction, is now estimated at $65 billion–a number too high for “staggering” to apply anymore……
the $65 billion number doesn’t include decommissioning and radioactive waste disposal costs, both of which will be added to ratepayers’ bills–and probably the rest of us taxpayers as well when the amount collected proves to be too small, as is the case with every other reactor in the country.
Meanwhile, utilities across the country, including Georgia Power, are buying solar power for 5 cents kilowatt/hour and less. And, unlike Vogtle, where the costs keep rising, solar’s price keeps falling…..http://safeenergy.org/2015/08/03/vogtle-at-65-billion-and-counting/
UK energy analysts unhappy with super costly Hinkley nuclear project

Planned Hinkley Point nuclear power station under fire from energy industry, Guardian, Nils Pratley and Sean Farrell, 10 Aug 15 Energy analyst says that for same price as Hinkley Point C, providing 3,200MW of capacity, almost 50,000MW of gas-fired power capacity could be built. Hinkley Point, the planned £24.5bn nuclear power station in Somerset, is under intensifying criticism from the energy industry and the City, even as the government prepares to give the final go-ahead for the heavily subsidised project.
The plant, due to open in 2023, will cost as much as the combined bill for Crossrail, the London 2012 Olympics and the revamped Terminal 2 at Heathrow, calculated Peter Atherton, energy analyst at investment bank Jefferies. He said that, for the same price as Hinkley Point C, which will provide 3,200MW of capacity, almost 50,000MW of gas-fired power capacity could be built.
“This level of new gas build would effectively replace the entire thermal generation fleet in the UK – much of which is old and inefficient – with brand new, highly efficient, low carbon, gas generation,” said Atherton.
Doubts about Hinkley Point have deepened after a detailed report by HSBC’s energy analysts described eight key challenges to the project, which will be built by the state-backed French firm EDF and be part-financed by investment from China.
These challenges include: declining demand for power in the UK, currently falling at 1% a year as energy-saving measures take effect; a three-fold jump in the UK’s interconnection capacity with continental Europe by 2022, massively increasing the country’s ability to import cheaper supplies; and “a litany of setbacks” in Finland, France and China for EdF’s European Pressurised Reactor (EPR) model, the same type as planned for Hinkley Point.
HSBC’s analysts described the EPR model as too big, too costly and still unproven, saying its future was bleak. They also pointed out that wholesale power prices have fallen by 16% since November 2011 when the government agreed a “strike price” for Hinkley Point’s output – effectively a guaranteed price of £92.50 per megawatt hour, inflation-linked for 35 years and funded through household bills. “With the problems encountered by France’s EPR model and a strike price likely to be double the UK wholesale price at the scheduled 2023 time of opening of the proposed Hinkley C EPR, we see ample reason for the UK government to delay or cancel the project,” they said…….. http://www.theguardian.com/environment/2015/aug/09/planned-hinkley-point-nuclear-power-station-energy-industry
Smart economics: Germany’s decision to phase out nuclear power
Why Germany’s decision to phase out nuclear power is smart economics , REneweconomy, By Erik Gawel & Sebastian Strunz on 4 August 2015 London School of Economics
Germany has made a formal commitment to phase out the use of nuclear power by 2022. Erik Gawel and Sebastian Strunz write on the implications of the strategy for Germany’s future energy mix and whether the approach adopted in the country could function as a model for other European states. They argue that while the target is undeniably challenging, long-term it is economically sensible and feasible to phase out both fossil fuels and nuclear energy in favour of renewables.
Political responses to climate change and other negative consequences of conventional energies within Europe (e.g. oil spills, radioactive waste, open pit coal mining) are highly diverse. While the UK is promoting nuclear as a carbon-free energy source, for instance, Germany has embarked on a completely different path with its plan to phase out nuclear energy altogether. What is the background of Germany’s phase-out decision and how sensible is it from an economic point of view?
In order to fully answer this question, several aspects need to be acknowledged. First, the phase-out is no impulsive reaction to the Fukushima incident, which came out of the blue. Germany’s powerful anti-nuclear movement dates back to the 1970s; it bred the Green Party which entered the Parliament in 1983 and ascended to the government in 1998 by forming a coalition with the Social Democrats. In 2000 this centre-left coalition put a nuclear phase-out into law for the first time. The early 2020s were identified as the target date for a nuclear free energy system. While subsequent revisions of the law have changed the specifics, the currently stipulated year for the last plant to be shut down, 2022, is well in line with this original perspective. Thus, the phase-out project has always been crafted as a long-term and step-wise process.
Second, the Fukushima disaster effectively killed the narrative that nuclear power was necessary as a ‘bridging technology’ toward a renewables-based energy system. While conservatives had previously argued in line with this logic (and the government led by Chancellor Merkel in 2010 diluted the first phase-out law from 2000 by extending the running times of nuclear plants), they reversed their position after Fukushima. The most immediate consequence of Merkel’s shift on nuclear was the prompt shutdown of seven nuclear power plants in spring 2011. Due to overcapacities, this drop has neither proven to be problematic for the security of supply (contrary to the conservatives’ claims before 2011) nor has it led to an enduring increase of wholesale prices or a requirement to import foreign nuclear power. In fact, Germany is still a net exporter of electricity.
Third, Germany is not alone in phasing out nuclear power. As can be seen from Table 1, [in original] there are several countries in Europe that do not rely on nuclear power or have also declared their intention to stop nuclear energy production. While some of the countries without nuclear are smaller EU member states, it is noteworthy that Italy, another highly industrialised economy and member of the G7, has never used nuclear power. The highly diverse picture of nuclear energy in Europe becomes complete when the huge differences in nuclear-shares among countries are considered, as well as the fact that countries such as Poland intend to enter this form of energy………..
Is nuclear power a necessary part of a future energy mix?
All things considered, is nuclear power necessary for decarbonising the energy supply while also ensuring security of supply? The German experience shows that renewable energies may contribute major shares of the electricity supply – without jeopardising energy security in a highly industrialised economy and even under challenging natural frame conditions in Germany for renewables, provided that there is a long-term transition perspective and a stable political consensus.
Moreover, it may be questioned whether the long-term risks associated with nuclear power really fit the requirements of any sustainable energy system which demands being more than simply carbon-free. But even apart from such sustainability issues, the apparent need for heavy subsidies to render new nuclear plants economically viable undercuts the claim that nuclear is cheaper than renewable energy sources, even in terms of financial costs only. On the contrary, a recent Prognos study estimates that “new wind and solar can provide carbon-free power at up to 50 per cent lower generation costs than new nuclear”. Accounting for backup requirements in times without wind or sun, a combined system of wind, solar and gas is still 20 per cent cheaper than a system of nuclear and gas.
Sure enough, Germany has to cope with the side-effects of the transition (e.g. current rises in retail electricity prices) and interactions with other developments (e.g. increasing electricity production from lignitemainly due to high gas prices and the record low emission allowance prices). Yet, nuclear energy is rarely an inevitable part of decarbonising energy provision. Until now, Germany’s political consensus is very solid in this respect – and while the transition effort is indeed challenging, this does not diminish its merits from an economic point of view: in the long run, it seems both sensible and feasible to phase out fossil and nuclear energies in favour of renewables, thus treading a long but well-considered path towards comprehensive sustainability of energy provision, including long-term cost-effectiveness.
Source: This article was first published at the LSE’s Europblog http://reneweconomy.com.au/2015/why-germanys-decision-to-phase-out-nuclear-power-is-smart-economics-49500
Top bank advises UK government to delay or cancel Hinkley nuclear project
Too expensive…Not needed…top bank report hits out at plans for £25bn Hinkley C nuclear plant, This is Money, By NEIL CRAVEN FOR THE MAIL ON SUNDAY, 2 August 2015 Plans for Britain’s first nuclear reactor in almost 30 years have come under sustained attack from politicians and City bankers.
A report from a top bank this weekend warned that the cost of the £25billion Hinkley Point C plant was ‘becoming harder to justify’. HSBC concluded: ‘We see ample reason for the UK Government to delay or cancel the project.’
And former Tory Energy Secretary Lord Howell of Guildford – the self-described ‘pro-nuclear’ architect of a drive into nuclear power under Margaret Thatcher – has told the House of Lords that the reactor plan in Somerset was ‘one of the worst deals ever for British households and British industry’.
He added that he would ‘shed no tears if it was abandoned’.
Plans for Hinkley Point C have been controversial from the start with the Government guaranteeing what many saw as a sky high price electricity generated at the site.
The Department of Energy and Climate Change shrugged off HSBC’s report and the criticism seems unlikely to stop the nuclear plan. The Secretary of State for Energy, Amber Rudd, said on Friday that Britain could sign a deal as early as October during a visit by China’s President Xi Jinping.
EDF announced on the same day that it had chosen preferred suppliers for £1.3billion worth of work linked to the new plant.
But with the chorus of disapproval growing louder the Government and nuclear industry are set to be under huge pressure throughout the project to prove it is value for money for British energy users.
Key to the criticisms levelled by HSBC’s analysts is that the electricity produced by the reactor is likely to be too expensive, as European wholesale prices are expected to fall along with demand for energy from UK users. It warned of ‘huge difference between UK forward prices and the Hinkley price’.
Among HSBC’s eight key concerns is that the reactor will be economically unviable due in part to a rising number of electricity grid links with the Continent providing a ready source of cheaper supply.
At the same time it said projections by National Grid to 2025 all point to flat or declining demand. HSBC said its demand estimates are for a fall of one per cent a year.
HSBC also highlighted the ‘bleak’ future of large nuclear reactors which have a history of escalating costs and sliding deadlines. ……..
The Austrian and Luxembourg governments launched a legal complaint last month, followed by a challenge from ten German and Austrian green energy firms.
The complainants say the UK Government’s subsidies may reach £76 billion and are in breach of European rules relating to state aid. Some observers say the dispute could lead to delays of six years.: http://www.thisismoney.co.uk/money/news/article-3182406/Too-expensive-Not-needed-bank-report-hits-plans-25bn-Hinkley-C-nuclear-plant.html#ixzz3hhFWKFaE
Scottish firms warned that their reputation at stake, if involved in Hinkley nuclear build
French energy giant EDF yesterday announced its preferred bidders for the UK’s first such facility in more than 20 years. The list includes three Scottish firms – the Weir Group, Doosan Babcock and Clyde Union Pumps – which will find out in the coming months if they have been successful.
But Dr Richard Dixon, director of Friends of the Earth Scotland, told The National: “With one false start already, active legal action in Europe and a spectacular history of cost overruns and missed deadlines, getting involved with the nuclear industry is a huge reputational risk.”
He added: “Scottish engineering firms should be helping us exploit our huge potential in renewable energy rather than chasing the nuclear dream.”……..The EU approved the project last year after the Government agreed a subsidy contract with EDF, but the development is far from certain, with a challenge by Austria to the subsidy and green groups pondering a legal challenge.
Negotiations between the French company and potential investment partners have yet to result in a final decision.
Scottish Green MSP Patrick Harvie said: “This announcement is a reminder that the UK Conservative Government is in denial about the disastrous economics of new nuclear. Scottish consumers face paying to line the pockets of multinationals like EDF who have been promised double the current market price of power for the next 35 years. And that doesn’t take into account the … toxic waste legacy that this deal will simply add to.” http://www.thenational.scot/news/nuclear-contract-will-be-toxic-for-your-reputation-scots-firms-warned.5852
South Africa facing a R1-trillion nuclear financial disaster
R1-trillion nuclear plans are simply “disastrous” for SA http://businesstech.co.za/news/energy/94677/r1-trillion-nuclear-plans-are-simply-disastrous-for-sa/ 31 July 15 Government’s R1-trillion nuclear build plans are going to turn South Africa’s energy crisis into a jobs crisis, according to the Democratic Alliance.
Earlier in July, the Department of Energy signed two memoranda of understanding with Russian state nuclear energy corporation Rosatom to implement several joint projects for education in the nuclear power industry.
Energy Minister Tina Joemat-Pettersson said that South Africa will start a nuclear build programme in 2015, in a bid to generate an additional 9,600MW of electricity.
The country will have as many as nine new nuclear power plants by 2030, with government pegging the total cost to build these at R500 million – though energy experts have stated R1 trillion was more realistic, and would likely increase.
In a statement issued on 31 July, DA leader Mmusi Maimane said the nuclear deal will drag the country’s economy back, and will cost thousands of South Africans their jobs.
According to the party, the details behind government’s nuclear plans show that the undertaking is unaffordable.
“Whichever funding model is chosen, you can rest assured that it will be paid for by the South African taxpayer, and that we can expect substantial tariff increases over many years.”
These higher prices would price the poor out of electricity usage, and would result in energy-heavy industries – like mining and manufacturing – shedding more jobs, said the DA.
“For a government that claims to be pro-poor – and for a country where 5.2 million people cannot find work and a further 2.4 million have given up looking – this is unfathomable.”
Maimane pointed to a number of flaws in the scheme:
- Even if government’s estimate of R500 million was correct, South Africa cannot afford to build the nuclear reactors. This would result in private-public partnerships being formed, which would be reflected in current and future electricity prices increasing, as citizens would have to pay.
- South Africa lacks the capacity and skills to operate eight nuclear power stations. We lack the capacity and skills to run the one we already have, said Maimane.
- The project goes against the government’s own National Development Plan, which urges caution on nuclear, pointing rather towards gas, wind, and solar energy as a primary source of power.
To date, government has not provided solid details on the nuclear build plans.
“Until the government tells us how much the nuclear deal will cost, how we plan to pay for it, and how they intend to choose the preferred bidder, we cannot begin to entertain the notion of going down this path.”
The DA leader said that, while the party does not oppose nuclear power, the current plan is “not right” for the country, and it will do anything in its power to block the deal.
The end of the line for AREVA’s model of “birth to grave” nuclear processes
As losses mounted, so did Areva’s debt, which reached six billion euros at the end of the first half of 2015.
The sale of the nuclear reactor unit to EDF marks the end of Areva’s formerly profitable full-service model, which offered clients all aspects of development ranging from conception and construction to fuel procurement and waste treatment.
France sells major nuclear stake http://www.iol.co.za/business/international/france-sells-major-nuclear-stake-1.1893029#.VbqVMvOqpHw July 30 2015 Paris – Atomic energy giant Areva on Thursday agreed to sell a majority stake of its nuclear reactor unit to electricity group EDF as part of a shake-up of the French sector. Continue reading
€7bn needed to keep loss-making nuclear company AREVA alive
Lossmaking Areva needs €7bn capital injection, Ft.com Michael Stothard in Paris, 30 July 15 Struggling French nuclear group Areva on Thursday disclosed it needed a bigger than expected capital injection worth €7bn as the company also unveiled a far-reaching agreement with EDF on asset disposals and other projects.
The two companies — both state-controlled — agreed in principle that EDF will pay €2bn for a 75 per cent stake in Areva’s reactor unit, called Areva NP, in a radical reshaping of the French nuclear industry that has come after months of tense negotiations……..
Following the deal, Areva, which reported a €4.8bn net loss last year, will be reduced to a nuclear fuel company that mines, enriches and then disposes of uranium. The heart of the company — designing, building and servicing nuclear reactors — is being sold off.
Areva said that overall it would need €7bn in capital over the next two years, however, meaning that as much as €5bn will be required from sources other than EDF, the French utility group. Much of these additional funds are likely to come from a government-backed capital raising.
The French government may have to contribute between €4bn and €5bn, far more than the €2bn to €3bn that ministers had hoped for just a few months ago, according to people familiar with the situation, although the exact level of the capital raising was not announced on Thursday.
Areva said it could secure €0.4bn from selling some other assets including Canberra, its nuclear measurements subsidiary, and as much as €1.2bn from other sources of equity financing. This suggested a government-backed capital raising that might be closer to €4bn.
On Thursday the two companies also said they would set up a dedicated company to be 80 per cent owned by EDF and 20 per cent by Areva NP, aimed at improving the design and management of brand new reactors projects.
One of the problems that has weighed on Areva in recent years has been cost overruns at key projects, particularly the Olkiluoto 3 reactor in Finland, which is 10 years behind schedule and prompted the company to take €3.9bn in impairment charges………..http://www.ft.com/cms/s/0/110c0476-368c-11e5-b05b-b01debd57852.html#axzz3hPaCUU5g
-
Archives
- May 2026 (92)
- April 2026 (356)
- March 2026 (251)
- February 2026 (268)
- January 2026 (308)
- December 2025 (358)
- November 2025 (359)
- October 2025 (376)
- September 2025 (257)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


