Sizewell C nuclear project suffers setback after road building delayed.

Galliford Try replaced as key contractor following disagreement about cost
of work. Construction of two key access roads for Britain’s Sizewell C
nuclear power station has been delayed, and the main contractor replaced,
in a setback at one of the UK’s biggest infrastructure projects.


The delay threatens to prolong disruption around the Suffolk construction site
and comes as Sizewell C seeks to demonstrate that it can avoid the delays
and cost overruns that have plagued its sister project, Hinkley Point C in
Somerset.

The main contractor for the access roads, construction group
Galliford Try, has been replaced after failing to agree with Sizewell C on
the cost of the work. Galliford had been awarded a contract worth between
£150mn and £200mn to build the Sizewell Link Road and Two Village Bypass,
designed to carry construction traffic to the £38bn nuclear plant while
diverting heavy goods vehicles away from nearby villages.

 FT 25th Aug 2026,
https://www.ft.com/content/7a83b577-8d67-4435-9798-1e53d7fad4e9

August 28, 2026 - Posted by | business and costs, UK