Construction costs and financing of new nuclear power plants in Switzerland.

Source :
Neu U (2026) Construction costs and financing of new nuclear power plants in Switzerland. Swiss Academies Reports 21 (6)

This report provides a more detailed analysis of the observed development of construction costs for new nuclear power plants and discusses the potential costs of a new plant in Switzerland, as well as the associated uncertainties. Furthermore, it presents current financing models in Europe and the financial risks for the state and the economy associated with such construction.

In addition, current financing models in Europe and
the financial risks associated with construction for the state and the
economy are presented.

[Paul Dorfman says: The report is significant
because, unlike many other cost studies, it derives the risks from real
construction projects and, for the first time, also takes into account the
immense financing costs during the long construction period of a nuclear
power plant. It therefore estimates the expenditures to be 20 to 30 %
higher than estimates that consider only the pure construction costs.
According to the report, these account for around 70 % of the total costs
over the plant’s service life.

 Swiss Academy of Sciences 21st Aug 2026, https://scnat.ch/en/uuid/i/5e8fa25a-bfa9-54ac-b33b-4e5f464f8561-Baukosten_und_Finanzierung_von_neuen_Kernkraftwerken_in_der_Schweiz

August 28, 2026 - Posted by | business and costs, Switzerland