Legal case begins against Sizewell C nuclear project.

 High Court hearing for Sizewell C legal challenge campaigners. Campaigners
who have issued a legal challenge against the building of nuclear power
plant Sizewell C have a High Court hearing starting on Wednesday 22 March.


Together Against Sizewell C will argue that the environmental impacts of
securing a permanent water supply of two million litres per day at the
proposed site in Suffolk were never assessed.

As a result, the government
cannot guarantee the date the nuclear power plant will open, which means it
has no way of knowing for sure that the plant’s contribution to climate
change is enough to override the environmental harm it will cause.

Together Against Sizewell C will also make the case that no alternatives to nuclear
power, including renewables, were considered when the Secretary of State
for Energy, then Kwasi Kwarteng, gave the go ahead for the building of
Sizewell C on 20 July 2022. He rejected the recommendation of the Examining
Authority which ruled in February 2022 that unless the outstanding water
supply strategy could be resolved and sufficient information provided to
enable the Secretary of State carry out his obligations under the Habitats
Regulations, there was no case for a development consent order.

 Leigh Day 20th March 2023

https://www.leighday.co.uk/news/news/2023-news/high-court-hearing-for-sizewell-c-legal-challenge-campaigners/

Advertisement

March 23, 2023 - Posted by | legal, UK

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: