Nuclear power costs – from the CATO Institute – a reality check for those who imagine nuclear as a climate solution.



Nuclear Power Costs,  CATO Institute, By Peter Van Doren, 26 Mar, 21
,

“………………… In the Spring issue of Regulation I review a recent paper that documents the history of nuclear power plant construction in the United States and the increase in costs. From 1967 through 1978, 107 were constructed. Rather than costs going down over that time because of learning by doing, plant costs more than doubled with each doubling of cumulative U.S. capacity. The problem was declining “materials deployment productivity”—that is, the amount of concrete and steel that workers put together per unit time.

About 30 percent of the productivity reduction stems from nuclear regulatory safety concerns. According to the authors:

While our analysis identifies the rebar density in reinforced concrete as the most influential variable for cost decrease, changes to the amount and composition of containment concrete are constrained by safety regulations, most notably the requirement for containment structures to withstand commercial aircraft impacts. New plant designs with underground (embedded) reactors could allow for thinner containment walls. However, these designs are still under development and pose the risk of high excavation costs in areas or at sites with low productivity.

The sources of the other 70 percent of productivity slowdown were construction management and workflow issues, including lack of material and tool availability, overcrowded work areas, and scheduling conflicts between crews of different trades. Craft laborers, for example, were unproductive during 75 percent of scheduled working hours.

Plant builders attempted to address these problems by increasing the use of standardized prefabricated modules that could be shipped to site and installed. These were employed in later reactors, but whatever advantages they provided did not improve aggregate productivity.

Since the 1990s, two nuclear projects have begun construction in the U.S. Both are two‐reactor expansions of existing generating stations. The VC Summer project in South Carolina was abandoned in 2017 with sunk costs of $9 billion, and the Vogtle project in Georgia is severely delayed. Recent estimates place the total price of the Vogtle expansion at $25 billion, almost twice as high as the initial estimate of $14 billion, and costs are anticipated to rise further.


These problems are not unique to the United States. Projects in Finland and France also have experienced cost escalation, cost overrun, and schedule delays, which I also described ten years ago.

The paper provides an important reality check for those who believe nuclear power is an essential component of any strategy to reduce greenhouse gas emissions. https://www.cato.org/blog/nuclear-power-costs

March 27, 2021 - Posted by | Uncategorized

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: