nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

Taiwan doesn’t know what to do with radioactive trash, so decommissioning of 1st nuclear power plant is delayed

Decommissioning of 1st nuclear power plant facing major delay Focus Taiwan 2018/12/03 Taipei, Dec. 3 (CNA) By Elizabeth Hsu Taiwan is scheduled to begin decommissioning the first reactor of its oldest nuclear power plant in New Taipei on Dec. 5 after 40 years of service, but the deadline will not be met because of questions over how to deal with the plant’s nuclear waste.

The plan to decommission the two reactors in the Jinshan Nuclear Power Plant included the construction of an outdoor storage yard at the plant site for the dry storage of spent nuclear fuel.

The facility was built in 2013 but has yet to pass a New Taipei government inspection needed to obtain an operating permit, leaving the decommissioning process in limbo.

Hsu Tsao-hua (徐造華), a spokesman for Taiwan Power Company (Taipower), which runs Taiwan’s three nuclear power plants, said that if the storage facility cannot be used, the 816 fuel rods still in the Jinshan plant’s first reactor will have to stay where they are, and the plant’s safety equipment will have to be kept running.

Though the company has planned an indoor storage facility, it will take at least 10 years to build, which could delay the decommissioning process by at least a decade, Hsu warned………..

The thorny spent fuel storage and EIA review issues that will cause the Jinshan plant to miss the scheduled deadline come down to politics, and at least to some extent to the New Taipei  government’s attitude on the issue.

New Taipei Mayor Eric Chu (朱立倫) of the opposition Kuomintang (KMT) has declared that his city “can never be the permanent storage place for nuclear waste.”

His position has been at odds with the general stance of his party, which advocates the use of nuclear power as the country moves toward its ultimate goal of becoming a nuclear-free homeland. ……

“Nuclear waste represents pain in the heart of New Taipei (citizens),” said Hou, after the city has co-existed with two nuclear power plants for nearly four decades.

He also argued that nuclear waste should never be stored in a heavily populated city, and he urged the central government and Taipower to find a permanent storage location as soon as possible, a mission the utility has struggled with for years.

New Taipei is the most populous city in Taiwan with a population of 3.99 million as of November, government statistics show.

Even if the decommissioning of the Jinshan power plant were to start on time, it would still be a long process.

Under Taipower’s plan, it would involve eight years to shut the plant down, 12 years to dismantle it, three years to inspect its final condition and two years to restore the land. http://focustaiwan.tw/news/aeco/201812030020.aspx

Advertisements

December 4, 2018 - Posted by | decommission reactor, Taiwan

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: