USA Energy Dept must pay $1million daily for MOX facility failure, and non removal of plutonium wastes

Aiken Standard 7th Jan 2018, South Carolina’s $1million daily penalty tally against the Department of
Energy started over Jan. 1, and state leaders said they will pursue payment of the daily penalty as well as claims for penalties accrued in 2016 and 2017.

According to federal law, the DOE was required to finish the Mixed Oxide Fuel Fabrication Facility at the Savannah River Site in Aiken County by 2014, or remove at least one metric ton of plutonium from the state by Jan. 1, 2016. When the Energy Department failed to meet those deadlines, a $1 million daily penalty was instated. The penalties add up to a maximum of
$100 million annually for each of the first 100 days of the year. When the fees reach the maximum mark, state leaders said residents can expect to see a claim follow quickly thereafter.
https://www.aikenstandard.com/news/clock-resets-for-m-a-day-fine-against-doe-for/article_160b5366-f258-11e7-acdd-9b750ce012c1.html

Advertisements

January 10, 2018 - Posted by | Legal, USA, wastes

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: