Nuclear regulator OKs additional 20-yr operation for aging reactors
The Takahama Nuclear Power Plant’s No. 1 and 2 reactors (from left in the front row) and No. 3 and 4 reactors (from left in the back row) are pictured in this photo taken from a Mainichi helicopter in Takahama, Fukui Prefecture, on June 15, 2016.
TOKYO (Kyodo) — Japan’s nuclear regulator on Monday approved an additional 20 years of operation for two aging reactors on the Sea of Japan coast that will become the first such reactors to resume operation under new rules introduced after the Fukushima nuclear meltdown.
The Nuclear Regulation Authority granted its approval of Kansai Electric Power Co.’s plan to continue the operation of its No.1 and No.2 reactors at the Takahama nuclear plant in Fukui Prefecture, both of which are over 40 years old.
The rules, tightened after the 2011 nuclear disaster at Tokyo Electric Power Co.’s Fukushima Daiichi plant, set the maximum length of operation for nuclear reactors at 40 years in principle but also stipulate that their operations can be extended for an additional 20 years if the NRA allows.
Since December 2014, Kansai Electric has been checking on degradation of the two reactors in a stricter manner than regular checkups to obtain approval for extending their operations.
After confirming there were no abnormalities, the utility applied in April last year for an NRA screening.
In order for the reactors to resume operation, the company needed to complete three procedures by July 7. The two reactors had already passed a test for compatibility with the new rules and received approval for a construction plan that detailed equipment design. The only remaining test was for measures against the degradation of the reactors.
In the screening, preventing long electric cables from catching fire and covering the containment vessels with concrete were raised as issues to be addressed, and the company submitted a plan to complete such necessary measures by October 2019.
The reactors are therefore expected to resume operations after these steps have been completed.
The No.1 reactor began operating in November 1974, while the No. 2 reactor did so in November the following year. Both reactors have been suspended since regular checkups in 2011.
http://mainichi.jp/english/articles/20160620/p2g/00m/0dm/070000c
No comments yet.
-
Archives
- May 2022 (242)
- April 2022 (378)
- March 2022 (405)
- February 2022 (333)
- January 2022 (422)
- December 2021 (299)
- November 2021 (400)
- October 2021 (346)
- September 2021 (291)
- August 2021 (291)
- July 2021 (257)
- June 2021 (210)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Fuk 2022
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS
Leave a Reply