Nuclear power costs – from the CATO Institute – a reality check for those who imagine nuclear as a climate solution.
Nuclear Power Costs, CATO Institute, By Peter Van Doren, 26 Mar, 21,
“………………… In the Spring issue of Regulation I review a recent paper that documents the history of nuclear power plant construction in the United States and the increase in costs. From 1967 through 1978, 107 were constructed. Rather than costs going down over that time because of learning by doing, plant costs more than doubled with each doubling of cumulative U.S. capacity. The problem was declining “materials deployment productivity”—that is, the amount of concrete and steel that workers put together per unit time.
About 30 percent of the productivity reduction stems from nuclear regulatory safety concerns. According to the authors:
While our analysis identifies the rebar density in reinforced concrete as the most influential variable for cost decrease, changes to the amount and composition of containment concrete are constrained by safety regulations, most notably the requirement for containment structures to withstand commercial aircraft impacts. New plant designs with underground (embedded) reactors could allow for thinner containment walls. However, these designs are still under development and pose the risk of high excavation costs in areas or at sites with low productivity.
The sources of the other 70 percent of productivity slowdown were construction management and workflow issues, including lack of material and tool availability, overcrowded work areas, and scheduling conflicts between crews of different trades. Craft laborers, for example, were unproductive during 75 percent of scheduled working hours.
Plant builders attempted to address these problems by increasing the use of standardized prefabricated modules that could be shipped to site and installed. These were employed in later reactors, but whatever advantages they provided did not improve aggregate productivity.
Since the 1990s, two nuclear projects have begun construction in the U.S. Both are two‐reactor expansions of existing generating stations. The VC Summer project in South Carolina was abandoned in 2017 with sunk costs of $9 billion, and the Vogtle project in Georgia is severely delayed. Recent estimates place the total price of the Vogtle expansion at $25 billion, almost twice as high as the initial estimate of $14 billion, and costs are anticipated to rise further.
These problems are not unique to the United States. Projects in Finland and France also have experienced cost escalation, cost overrun, and schedule delays, which I also described ten years ago.
The paper provides an important reality check for those who believe nuclear power is an essential component of any strategy to reduce greenhouse gas emissions. https://www.cato.org/blog/nuclear-power-costs
No comments yet.
-
Archives
- January 2026 (259)
- December 2025 (358)
- November 2025 (359)
- October 2025 (376)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS





Leave a comment