Huge costs of decommissioning Britain’s ”Magnox” nuclear failities just keep going up

UK spending watchdog warns on costs of cleaning up old nuclear plants
Decommissioning charge has risen by £3bn since 2017 and there remains ‘inherent uncertainty’ over final bill, NAO finds,
Nathalie Thomas in Edinburgh,  SEPTEMBER 11 2020,  Estimates of the cost to clear up 12 of the UK’s earliest nuclear power sites have increased by nearly £3bn since 2017 and there remains “inherent uncertainty” over the final bill, the country’s public spending watchdog has warned.

The National Audit Office on Friday published its latest report into the long-running saga around the decommissioning of two research sites and 10 early nuclear power stations in Britain, which came to be known as the “Magnox” plants due to the magnesium alloy that was used to cover the fuel rods inside their reactors.
 The spending watchdog also found that the costs to the taxpayer of a botched 2014 tender process to outsource the decommissioning to the private sector was £20m higher than when it last investigated three years ago. Cleaning up the Magnox sites, which were built before privatisation and include Hunterston A in Scotland and Hinkley Point A in Somerset, has turned into a costly and torturous affair.
In 2016 the High Court ruled the 2014 competition for a 14-year contract to decommission the sites — which had been awarded to Cavendish Fluor Partnership, or CFP, a joint venture between UK-based Babcock International and Fluor of the US — had been “fudged” by the Nuclear Decommissioning Authority, a body attached to the Department for Business, Energy and Industrial Strategy.
 A year later ministers, acting on legal advice, terminated the arrangement with CFP nine years early and renegotiated a shorter contract that ran until the end of August 2019. Decommissioning of the sites was then brought in-house by the NDA  .
The NAO’s previous probe in 2017 into the decommissioning concluded that the failed Magnox contract had cost the taxpayer £122m in settlements with unsuccessful bidders, legal costs and staff time. In its latest report on Friday, the watchdog found the NDA had, in addition, agreed to pay up to £20m to exit the contract early, although it praised the authority for renegotiating the agreement under “the challenging circumstances”.
The watchdog also revealed that NDA estimates for the cost of getting all the Magnox plants “cleared and safely enclosed” had increased by up to £2.7bn to as much as £8.7bn since 2017. It added that costs are “likely to be subject to further change, largely because of the inherent uncertainties involved in cleaning up the UK’s nuclear sites”. Once the reactors and waste stores are sealed, the sites are kept secure for a period potentially as long as 80 years for radiation levels to decay. In 2014, the same costs had been estimated at £3.8bn..  …….. https://www.ft.com/content/6f313c84-d314-4160-b124-a68c4e85be09

September 17, 2020 - Posted by | business and costs, UK, wastes

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: