Ministry of Defence’s poor management of contracts for nuclear infrastructure projects

MPs slam MoD’s ‘utter failure’ to improve contract management as nuclear project costs soar

Civil Service World  by Beckie Smith on 18 May 2020 

‘The department knows it can’t go on like this,’ says PAC chair   The Ministry of Defence’s poor management of contracts has left taxpayers picking up the bill after nuclear infrastructure projects have swelled beyond their planned time and budget, a public spending watchdog has found.

The Public Accounts Committee found three nuclear infrastructure projects had together gone £1.45bn over budget and were each between 1.7 and 6.3 years because of problems with their contracts’ design and management.

The committee’s inquiry examined three projects: the building of a nuclear warhead assembly and disassembly facility, known as MENSA, at AWE Burghfield; the Rolls Royce-owned and operated Core Production Capability facilities at Raynesway, where the department is upgrading facilities for nuclear reactor core production; and the BAE Systems-owned Barrow shipyard facility to allow modular build of Dreadnought-class submarines.

The MoD was unable to explain why it had made repeated mistakes designing and managing the contracts – which represent the three biggest nuclear infrastructure projects it is managing – despite being warned about the same issues in the past, PAC said in a report last week.

The MPs said that both PAC and the National Audit Office had been warning of similar contracting mistakes for more than 30 years. The MoD had also “failed to learn lessons from comparable projects in the civil nuclear sector and in the United States”, they added.

The PAC report followed a NAO finding in January that “inherent uncertainties of early designs [in the three contracts] do not incentivise site operators, or their sub-contractors, to negotiate and share risks, increasing risks for the department”.

“It is therefore disappointing to see that in their early days the department made the same mistakes, also experienced by others, as were made more than 30 years ago,” the NAO report said.

The ministry said it “immensely regretted” the waste of money but admitted costs could keep rising because the contracts had left the government to assume financial risk……. https://www.civilserviceworld.com/articles/news/mps-slam-mods-utter-failure-improve-contract-management-nuclear-project-costs-soar

May 19, 2020 - Posted by | politics, UK

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: