Whitehaven News 5th Feb 2019 , CALLS are growing to make Calder Hall the first nuclear reactor in the UK
to be decommissioned. Nuclear officials say that if decommissioning is
delayed, the asbestos in the reactor will pose a risk to workers, while
maintenance costs will become ‘unsupportable’.

Council bosses are ramping up the pressure on the Government to fast-track the dismantling of the world’s oldest industrial-scale nuclear power station based at
Sellafield. The authority’s nuclear board will be asked today to delegate
authority to council chief executive Pat Graham and the nuclear
portfolio-holder councillor David Moore to develop a detailed case for
accelerated decommissioning.

Councillors agreed at the end of last year
that the UK’s first industrial-scale power station to be built should
also be the first to be cleaned up. Calder Hall is one of 11 reactor sites
around the country and the Nuclear Decommissioning Authority is now
reviewing the “timing and sequence” of its nationwide clean-up
operation.

At present the defuelling of Calder Hall is due to be finished
in 2019/20, and would not enter a care and maintenance (C&M) status until
2034. The argument for tackling the Sellafield-based reactor first includes
the continuing risk it poses to workers and the public. The report said:
“As the oldest Magnox reactor, the deterioration of the building fabric
and the potential for significant quantities of asbestos to be present pose
risk to workers. The cost borne by the taxpayer associated with maintaining
the building in a safe state for a long period of care and maintenance
could be significant and could increase over time to meet future regulatory
requirement.”

The report concludes that the reactor could deteriorate to
the point that the cost of keeping it compliant with environmental
regulations becomes “unsupportable”. The accelerated clean-up of Calder
Hall could also create jobs to offset some of the 3,000 “surplus roles”
expected at Sellafield over the next four to five years.
https://www.whitehavennews.co.uk/news/17410498.calls-to-make-calder-hall-first-nuclear-reactor-in-uk-to-be-decommissioned/

Advertisements

February 7, 2019 - Posted by | decommission reactor, UK

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: