The shutdown of Oyster Creek Nuclear Station- is it best to hand the waste management to Holtec?

After the Shutdown: Oyster Creek Nuclear Generating Station Oyster Creek is done producing nuclear energy. Now comes the hard part: cleaning up five decades of radioactive waste. New Jersey Monthly, By Ian T. Shearn | | January 14, 2019 “……..At noon this past September 17, operators shut down the Oyster Creek turbine. Three minutes later, two “scram” buttons were simultaneously pushed, inserting 122 control rods into the reactor core and aborting the nuclear reaction inside the vessel. After nearly a half-century of operation, the nation’s oldest active nuclear power plant went offline for good.

That began the onerous task of decontaminating and dismantling the plant—a process known as decommissioning. The shutdown also created severe financial angst among local officials, who had grown dependent on Oyster Creek’s tax revenue. And it offered the latest painful reminder that the United States lacks a plan to deal with a growing stockpile of radioactive nuclear waste. 

The shutdown left New Jersey with three operating nuclear reactors, which produce 37 percent of the state’s electricity. With the emergence in recent years of cheap and abundant natural gas, along with a growing appetite for renewable energy, plants like Oyster Creek have lost their competitive edge. The nuclear age is on the wane in the United States, at least in the commercial energy sector. Today, there are 60 active U.S. nuclear plants with 98 reactors, down from a high of 112 operational plants in 1991. Only two reactor plants are under construction.

Oyster Creek’s license was to expire in 2029. But in 2010, the state Department of Environmental Protection ordered the plant to build cooling towers to protect Barnegat Bay from its warm-water discharges. After estimating the cost at more than $800 million, Exelon Corp., the current owner/operator, reached an agreement to close the plant in 2019. That was advanced to 2018 in part to manage costs.

A CHANGE IN PLANS

Shortly after the shutdown, plant employees began the process of cooling down the reactor and removing all nuclear fuel for storage in the plant’s used-fuel pool, a bath of highly purified, chemically balanced, fresh water. The 40-foot-deep pool—with reinforced concrete walls 2-feet thick—contains 2,430 fuel assemblies, more than half of the spent fuel that has accumulated over five decades.

Exelon estimated decommissioning would take 60 years. Its method, a process known as SAFSTOR, includes waiting for the radiation—both in the fuel pool and the reactor—to diminish naturally over decades, reducing the contamination risk for workers dismantling the facility. That plan changed dramatically last summer when Exelon reached an agreement to sell the plant to Holtec International, which has a technology campus in Camden, and proposes to complete the task in less than eight years by expediting the transfer of the spent fuel from the pool to dry storage casks before its radiation has appreciably decayed. Holtec and Exelon have asked the U.S. Nuclear Regulatory Commission for an expedited approval of the sale by May 1,  prompting concern among environmentalists. 

“What’s the big hurry?” asks Janet Tauro, board chair of Clean Water Action NJ. “Holtec may be the best thing in the world, but we’re talking about 1.7 million pounds of nuclear waste.” Lacey Township, the Sierra Club and Concerned Citizens of Lacey have asked the NRC to hold a public hearing. Tauro and Clean Water Action New Jersey have asked the state attorney general for a review of the Exelon/Holtec deal.

“The NRC will try to complete a review of the application by May 1,” says NRC spokesman Neil Sheehan.  “But we have made it clear to Exelon and Holtec that achieving that will be contingent upon us receiving the information we need.” That could include information about technical aspects of the decommissioning and adequacy of funding for the project.

Exelon and Holtec officials are nonetheless optimistic the deal will be approved on their timetable. Soon, the nuclear license and the 700-acre property would be transferred to Holtec—along with control of a nearly $1 billion decommissioning trust fund generated by utility ratepayers over decades. Holtec would assume all liability for the spent nuclear fuel—and any potential accidents.

Jeff Tittel, director of the New Jersey Sierra Club, says he’s fine with the expedited decommissioning schedule. “It’s very doable and it’s been done many times throughout the country,” he notes. But he would like to see the storage site for the nuclear waste elevated and upgraded to withstand potential flooding or a terrorist attack. According to an AP report, the Sierra Club and several community groups also say the $1 billion fund is insufficient for cleanup and storage.

Tittel is “most concerned,” however, about the transfer of Oyster Creek’s ownership from Exelon, an industry behemoth with deep pockets, to Holtec, a relatively small limited-liability company, which will subcontract the work to an even smaller subsidiary. “If there is some kind of accident, there will be no one to hold accountable,” he says. 

Kris Singh, who holds more than 90 patents, mostly related to nuclear energy, founded Holtec in 1986. His company has emerged as an industry leader in the management of spent nuclear fuel. Its dry-cask technology is used at 116 nuclear power plants around the world, including 65 in the United States. Those casks would be used to store Oyster Creek’s spent fuel.

But Singh’s company lacks experience in cleaning up closed nuclear plants. That’s why it teamed with a Canadian engineering firm, SNC-Lavalin, to form Comprehensive Decommissioning International (CDI). Holtec has also reached agreements to purchase nuclear plants in Massachusetts and Michigan and perform expedited decommissioning there. The Massachusetts deal is awaiting NRC approval, and the Michigan deal will be submitted at a later date. 

“CDI, headquartered in Camden, has been established to bring the expertise of both companies together to ensure safe, rapid, and economic nuclear plant decommisioning,” says Holtec marketing and communications specialist Caitlin Marmion.

What’s in it for Holtec? The company would, in effect, hire itself and its subsidiary to clean up the site by drawing fees from the decommissioning fund. Holtec also would purchase its own storage casks for the cleanup. And once the cleanup is done, it can profit from the sale of the 700-acre Oyster Creek site.

SOUNDING THE ALARM

Paul Gunter, a longtime environmental activist, policy analyst and nuclear-reactor watchdog for the advocacy group Beyond Nuclear, has been following activities at Oyster Creek for decades. He is calling for a thorough inspection of the plant’s GE Mark 1 reactor before it’s disposed of, citing its well-documented design flaws and a long history of modifications and retrofits. The reactor came under intense international scrutiny in 2011, after three of the same reactors melted down at the Fukushima Daiichi Nuclear Power Plant in Japan. 

Holtec’s decommissioning plan “is like burying a body without an autopsy,” says Gunter. He notes that 21 GE Mark 1 reactors remain operational in the United States. (Holtec’s Marmion points out that the company’s plans to dismantle and dispose of the reactor are “in accordance with regulatory requirements.”)

Gunter is also alarmed by Holtec’s partnership for the decommissioning work. SNC-Lavalin, Gunter says, currently faces federal corruption charges in Canada. Equally disturbing, he says, the company is “barred from doing any contractual work with the World Bank until 2023—again because of global corruption.”

SNC-Lavalin has had a legal cloud over its head since 2015 (the same year it began collaborating with Holtec) when allegations surfaced that former employees paid $150 million in bribes to officials in Libya to influence government policy and win contracts. In one case, a former SNC-Lavalin vice president is awaiting trial on charges he made bribes to the Gaddafi regime. In a separate case, a former SNC-Lavalin vice president of construction pleaded guilty in July to using a forged document following a widespread corruption investigation involving the construction of a super-hospital in Canada.  And in May, Canadian authorities filed charges against SNC-Lavalin after a multiyear probe related to illegal political contributions.

“Is this the company we want to be handling a $1 billion trust fund?” asks Gunter……..

The decommissioning project is not the only joint venture between Holtec and SNC-Lavalin. The two companies are also collaborating on the design and production of a small, nuclear and modular reactor, called SMR-160, at Holtec’s Technology Campus in Camden. The reactor is planned for operation by 2026.

Last February, Holtec signed an agreement in Camden that calls for the state-run nuclear operator in Ukraine to adopt the SMR-160 technology to meet its energy needs. Shortly after, Holtec announced that Ukraine may also become a manufacturing hub for SMR-160 components.

“Holtec is poised to….reinvigorate nuclear power for a world in dire need of a weather-independent and carbon-free source of energy,” CEO Singh told World Nuclear News at the time………….  https://njmonthly.com/articles/politics-public-affairs/after-the-shutdown-oyster-creek-nuclear-generating-station-forked-river/

January 15, 2019 - Posted by | USA, wastes

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: