Premium Times Nigeria, August 12, 2018, Kemi Busari  Seven months after PREMIUM TIMES published an investigation on the sorry state of Nigeria’s Nuclear Technology Centre, some abandoned projects within the centre have been completed.

Following the report of security loopholes in the investigation, the management of the Nigeria Atomic Energy Commission (NAEC) which oversees the centre also contracted a private firm to provide security for the centre.

In the two-part series published by PREMIUM TIMES in January, three projects were designated as abandoned as work had stopped on them.

Read first and second part of the investigation.

Identified as uncompleted were the centre’s recreational and educational facility, instrumentation laboratory and waste management plant.

In the report, some workers of the centre complained of idleness due to the inadequate facilities

The report also beamed a search light on the porous security at the centre which is partly due to the management’s insensitivity to the centre’s peculiar needs and a failed surveillance project………..

Waste Management
Meanwhile, works have continued on the radioactive waste management facility at the centre.

Awarded at over N400 million in 2009, a building that was supposed to serve as the radioactive waste management facility was overgrown with weed when this reporter first visited September 2017.

Waste management plants and equipment comprise various devices and machines used for treating, converting, disposing and processing wastes from various sources.

The construction of low/medium radioactive waste management facility was awarded at the contract sum of N401.4 million to Commerce General Limited and so far, N312 million has been paid to the contractor, the Nigeria Atomic Energy Commission (NAEC) said in response to a Freedom of Information request.

During the last visit, PREMIUM TIMES reporter observed the presence of the contractor at the site of the facility.

The management of NAEC did not respond to multiple inquiries on the rationale for redesign of the facility.

One of the staff members told this newspaper that the redesigning is unavoidable to correct the flaws of the contractor that first worked on the project.

He expressed optimism at the prospect of the facility.

“A lot of hazards will be reduced once it’s completed. As it is now, the country does not have a place to properly dispose our nuclear wastes. If it is completed and put to use, these hazards will be reduced. There is much to be benefitted if completed.”

Improved Security
………..But the level of security is not enough as expected of a nuclear technology centre says a staffer.

“The security is better but it’s not commensurate with what we expect in a nuclear environment. We commend the management for getting these people but they should give them orientation and we need armed security.

“There are differences. Before, if you come here, you won’t see anybody (at the gate). But now, it’s no longer like that. Even at weekends, you’ll meet them and policemen too. They are new and we feel that security of such places as this should be saddled with people that have at least basic educational level on nuclear technology,” he concluded. https://www. premiumtimesng.com/news/ headlines/279786-after- premium-times-report- contractors-complete- abandoned-projects-at- nigerias-nuclear-technology- centre.html

Advertisements

August 13, 2018 - Posted by | business and costs, Nigeria

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: