Systemic failures in France’s Flamanville nuclear project

Challenges 8th June 2018 [Machine Translation] EPR plant in Flamanville: does EDF really control its
construction site? While China has inaugurated its first EPR reactor,
delays are accumulating on the site of the EPR Flamanville in the Channel.
Defects noted at the end of March on strategic welds will further postpone
the opening of the plant “at least a few months” according to the Nuclear
Safety Authority.

In Flamanville, we are facing systemic failures. It is no
longer a matter of simple problems that add up to each other. It is in
these terms that Mycle Schneider, an independent Canadian expert and
co-author of an annual report on the nuclear industry, draws the alarming
report of the Flamanville shipyard. On May 31, EDF announced a delay of
several months in the construction of the EPR plant due to welding defects
on pipes. A new setback that will delay the commissioning of the plant. And
this is mainly due to a long series of problems since the launch of the
project in December 2007.
https://www.challenges.fr/entreprise/centrale-epr-de-flamanville-edf-maitrise-t-elle-vraiment-son-chantier_592774

Advertisements

June 13, 2018 - Posted by | France, politics

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: