Wylfa nuclear project in Wales – construction started before design completed; taxpayers at risk

Times 29th April 2018, New nuclear power plants are likely to blow their budgets and arrive late unless their designs are completed before construction starts, a report has warned. Ministers, wary of cost hikes and delays, are wrestling with how to financially support replacements for ageing coal-fired and nuclear plants across the UK.

Hitachi is trying to strike a deal with ministers to build a £10bn-plus plant at Wylfa on Anglesey, where taxpayers are likely to take a stake.

Researchers at Energy Technologies Institute found that most high-cost projects had started construction with incomplete designs, whereas work on low-cost plants had begun only once design and planning had been finalised.

The falling cost of renewable power such as offshore wind and solar has posed more questions about the financial viability of nuclear projects.
https://www.thetimes.co.uk/edition/business/alarm-rings-over-rising-nuclear-power-plant-bills-pqh8v0rkr

Advertisements

April 30, 2018 - Posted by | business and costs, politics, UK

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s

%d bloggers like this: