Georgia Power to finalize Vogtle assessments by end of August

 Guru Focus, PR Newswire, ATLANTA, Aug. 4, 2017  Georgia Power expects to complete its comprehensive schedule and cost-to-complete assessment, as well as cancellation cost assessment, for the Vogtle nuclear expansion by the end of the month. The final recommendation is expected to be filed with the Georgia Public Service Commission (PSC) as part of the 17th Vogtle Construction Monitoring (VCM) Report. Once submitted, Georgia Power will work with the Georgia PSC to determine the best path forward for customers…….

Construction work continues at the Vogtle nuclear expansion under a new service agreement with Westinghouse while Georgia Power’s assessments, as well as assessments by Oglethorpe Power, MEAG Power and Dalton Utilities, are finalized…….

Cautionary Note Regarding Forward-Looking Statements
Certain information contained in this communication is forward-looking information based on current expectations and plans that involve risks and uncertainties. Forward-looking information includes, among other things, statements concerning estimated cost and schedule information for Plant Vogtle Units 3 and 4 and other future actions related to Plant Vogtle Units 3 and 4. Georgia Power cautions that there are certain factors that could cause actual results to differ materially from the forward-looking information that has been provided. ……..

Editor’s note:  How’s this for one sentence?  could be a record?

The following factors, in addition to those discussed in Georgia Power’s Annual Report on Form 10-K for the year ended December 31, 2016, and subsequent securities filings, could cause actual results to differ materially from management expectations as suggested by such forward-looking information: the results of Westinghouse’s bankruptcy filing and the impact of any inability or other failure of Toshiba to perform its obligations under its guarantee, including any effect on the construction of Plant Vogtle Units 3 and 4; state and federal rate regulations and the impact of pending and future rate cases and negotiations; the impact of recent and future federal and state regulatory changes, as well as changes in application of existing laws and regulations; current and future litigation, regulatory investigations, proceedings, or inquiries; available sources and costs of fuels; effects of inflation; the ability to control costs and avoid cost overruns during the development construction and operation of facilities, which include the development and construction of generating facilities with designs that have not been finalized or previously constructed; the ability to construct facilities in accordance with the requirements of permits and licenses, to satisfy any environmental performance standards and the requirements of tax credits and other incentives, and to integrate facilities into the Southern Company system upon completion of construction; advances in technology; legal proceedings and regulatory approvals and actions related to Plant Vogtle Units 3 and 4, including Georgia Public Service Commission approvals and Nuclear Regulatory Commission actions; interest rate fluctuations and financial market conditions and the results of financing efforts; changes in The Southern Company’s or Georgia Power’s credit ratings, including impacts on interest rates, access to capital markets, and collateral requirements; the impacts of any sovereign financial issues, including impacts on interest rates, access to capital markets, impacts on foreign currency exchange rates, counterparty performance, and the economy in general, as well as potential impacts on the benefits of U.S. Department of Energy loan guarantees; and the effect of accounting pronouncements issued periodically by standard setting bodies. Georgia Power expressly disclaims any obligation to update any forward-looking information. https://www.gurufocus.com/news/549936/georgia-power-to-finalize-vogtle-assessments-by-end-of-august

Advertisements

August 7, 2017 - Posted by | business and costs, USA

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: