Serious doubts about UK’s Trident nuclear plan – problems not “manageable or resolvable.”

Times 23rd July 2017,New questions are being raised about the UK’s £41bn programme to replace
its Trident nuclear deterrent after the cost of building the reactors that
will power the submarine fleet soared.

An extra £235m of taxpayers’ money is needed for the £1.465bn scheme to make and maintain the reactor cores
for the navy’s existing nuclear submarines and the four Dreadnought-class
ballistic missile submarines, the first of which is expected to enter
service in 2028.

Last week a government watchdog gave the project a damning “red” warning. The rating – the severest possible – by officials at the Infrastructure and Projects Authority (IPA), which reports to the Cabinet
Office and Treasury, means a successful delivery of the project “appe ars
to be unachievable” under the original budget and that “there are major
issues on project definition, schedule, budget, quality and/or benefits
delivery, which at this stage do not appear to be manageable or
resolvable.” https://www.thetimes.co.uk/edition/news/red-alert-over-trident-reactorcosts-6np7vsr6b

Advertisements

July 26, 2017 - Posted by | UK, weapons and war

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: