Yet again, France’s nuclear regulator delays ruling on safety of Flamanville reactor
French nuclear regulator delays Flamanville ruling to autumn
ASN again delays ruling on safety of Flamanville reactor
* Postpones ruling to “autumn” from “end of summer”
* Will issue provisional ruling in July, then seek input (Adds new ASN statement)
Reuters, By Geert De Clercq PARIS, May 30 French nuclear regulator ASN said on Tuesday it will “probably” issue a final ruling in the autumn on whether the reactor that utility EDF is building in Flamanville is safe for use, in the latest delay in the process.
The ASN said in 2015 it had discovered excessive carbon concentrations in the cover and bottom of the Flamanville reactor vessel, which can weaken the mechanical resilience of the steel and its ability to resist the spreading of cracks.
Since then, Areva, which designed the EPR reactor, EDF and the ASN have been testing whether weak spots could jeopardise the safety of the reactor.
The regulator’s green light about the reactor vessel is crucial for EDF and Areva, as European Union antitrust authorities have made it a precondition for their approval of EDF’s planned takeover of Areva’s reactor unit.
The ASN has repeatedly postponed deadlines for ruling on the safety of reactor vessel.
And in what will be another delay, an ASN spokesman said in an email that the regulator now expected a “firm position probably in (the) autumn”……
Earlier on Tuesday, the ASN said it expected to receive technical reports about the reactor vessel by the end of next month. It will analyse these and then draft a provisional ruling on Flamanville, which will be made public in early to mid-July. It will then invite feedback on this ruling from the public, civil society, local authorities and the companies involved.
With the Flamanville reactor vessel welded in place in 2013 and covered by thousands of tonnes of concrete since then, taking out the vessel would delay the reactor startup by several years and cost billions of euros.
EDF has repeatedly said it is confident the ASN will find the vessel fit for operation……
The Flamanville reactor is years behind schedule and billions over budget, but EDF CEO Jean-Bernard Levy said this month EDF plans to load fuel in the reactor before end-2018. Construction in Flamanville started in 2007 and the plant was supposed to go online in 2012, but EDF has announced new delays and cost overruns every few years. The company said in 2015 the reactor would cost 10.5 billion euros ($12 billion), up from an initial budget of 3 billion. ($1 = 0.8948 euros) (Editing by Mark Potter/Alexander Smith) http://www.reuters.com/article/edf-flamanville-asn-idUSL8N1IW4N6
1 Comment »
Leave a reply to artiewhitefox Cancel reply
-
Archives
- December 2025 (277)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Nuclear reactors will come back to bite the people who built them. They have a limited life span. The worst possible by products come from nuclear reactors. People are self destructive.