Will Westinghouse be able to complete any of its nuclear projects?

Westinghouse files for bankruptcy in blow to nuclear power, NYT, 30 Mar 17 “……..Bankruptcy will make it harder for Westinghouse’s business partners to collect money they are owed by the nuclear-plant maker. That mostly affects the American power companies for whom it is building reactors, analysts say. Now, it is unclear whether the company will be able to complete any of its projects, which in the United States are about three years late and billions over budget.

The power companies — Scana Energy in South Carolina and a consortium in Georgia led by Georgia Power, a unit of Southern Company — would face the possibility of new contract terms, long lawsuits and absorbing losses that Toshiba and Westinghouse could not cover, analysts say. The cost estimates are already running $1 billion to $1.3 billion higher than originally expected, according to a recent report from Morgan Stanley, and could eventually exceed $8 billion over all.

Dennis Pidherny, a managing director at Fitch Ratings who is sector head of the United States public power group, said that it was possible that the company’s bankruptcy filing could terminate the contracts and that it could be difficult for the utilities to find another builder to take them over.

“There’s still quite a bit of work that needs to be completed,” he said. “The biggest challenge there is quite simply finding another suitable contractor who can complete the contract and have it completed at a quote-unquote reasonable cost.”

That is, if they are constructed at all. Stan Wise, chairman of the Georgia Public Service Commission, said the utilities developing the Alvin W. Vogtle generating station in the state would have to evaluate whether it made sense to continue.

“It’s a very serious issue for us and for the companies involved,” Mr. Wise said. “If, in fact, the company comes back to the commission asking for recertification, and at what cost, clearly the commission evaluates that versus natural gas or renewables.”

In a statement on Wednesday, Toshiba said Westinghouse and affiliated companies were “working cooperatively” with the owners to arrange for construction to continue. In recent days, the affected companies issued statements saying they were monitoring the situation and exploring their options, as did the Energy Department, which has authorized $8.3 billion in federal loan guarantees for the Georgia project.

“We are keenly interested in the bankruptcy proceedings and what they mean for taxpayers and the nation,” said Lindsey Geisler, a Department of Energy spokeswoman. “Our position with all parties has been consistent and clear: We expect the parties to honor their commitments and reach an agreement that protects taxpayers, promotes economic growth, and strengthens our energy and national security.”https://www.nytimes.com/2017/03/29/business/westinghouse-toshiba-nuclear-bankruptcy.html?_r=0

Advertisements

March 31, 2017 - Posted by | business and costs, USA

No comments yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: