South Africa’s nuclear company Eskom runs out of money for assessing environmental impact of nuclear energy

nuclear-costs1flag-S.AfricaEskom runs out of money for assessing environmental impact of nuclear energy  SOUTH AFRICA enca.com  23 May 2015 JOHANNESBURG – Government says nuclear power in South Africa is going ahead. Earlier this week Energy Minister Tina Joematt-Peterson said that procurement deals would be signed with prospective partners by the end of 2015.

In the next ten years, government plans to introduce 9600MWs of nuclear energy.

But signing procurement deals is one half of the process. The other half of the process has stalled.

The second version of the environmental impact assessment (EIA) for the site proposed for Nuclear 1, at Thyspunt in the Eastern Cape is not complete.

During a question and answer session in Parliament in March Minister of Public Enterprises Lynne Brown in a written reply said that Eskom had run out of money to complete the report.

“It was put on hold during 2013/14 due to funding constraints in Eskom.  In 2014, additional funds were approved and the finalisation of the Draft Environmental Impact Report (revision 2) was initiated,” noted the reply.

Eskom said this version of the report is due to be released to the public in May 2015 for comment but the Minister of Public Works says this has been put on hold due to the limited funding.

In the Nuclear Energy Policy of 2008,  Eskom was designated as owner operator for nuclear plants in South Africa. The Department of Energy says this means that Eskom is responsible for applying and obtaining various permits including EIA and nuclear licenses.

Eskom has already spent R35 million on the report, which was funded by the income generated from tariffs.

“Eskom, in terms of the electricity regulations, is allowed to budget for and spend money on activities that are deemed prudent for the development of generation project,” noted the power utility in a statement.

However, in 2014 Eskom had to reprioritise its expenditure, “The funding of the EIA was cut in favour of other projects and activities deemed more essential in nature

Costs for the EIA’s specialist studies are now being managed on an individual study and activity level. Still outstanding is the biodiversity offset study, public participation meetings and some still need to go through the independent phase review.

Eskom says this final stage is vital, “This phase of independent review is necessary to ensure that all issues raised have been addressed in an independent and transparent manner.”

The Department Energy says even though it’s not directly involved in the EIA process it is watching Eskom’s progress on the issue……

  • Others watching the process are the Thyspunt Alliance, a group opposing the development in the Eastern Cape.

    Trudi Malan said they are working with their own experts to verify the findings of Eskom’s report, “The problem with the Eskom EIA is that their experts only spend three of four days on the site, when we actually need more information,” she said.

    The first draft of the EIA was thrown out because incorrect methodology was used to do the assessment……..http://www.enca.com/south-africa/eskom-has-no-money-complete-environment-impact-assessment-nuclear-energy-project-site 

May 25, 2015 - Posted by | business and costs, South Africa

1 Comment »

  1. Reblogged this on wyrdsis.

    wyrdsis's avatar Comment by wyrdsis | May 26, 2015 | Reply


Leave a reply to wyrdsis Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.