nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

Chile getting extreme UV radiation with increased risk of skin cancers

Rising UV radiation prompts skin cancer fears in Chile http://www.news24.com/Green/News/Rising-UV-radiation-prompts-skin-cancer-fears-in-Chile-20141124 Santiago – Cancer experts in Chile are warning people to limit their exposure to the sun as dangerously high levels of ultraviolet radiation are expected over the next few months.

A recently released report indicates the a hole in the ozone layer, which is normally situated over Antarctica, is moving towards the South American country.

Chilean’s might have to stay indoors this summer as experts warn that the country will be blasted by extremely high levels of ultraviolet radiation.

According to a study from Chile’s national cancer corporation, or Conac, the massive hole in the ozone layer above Antarctica is moving closer towards the South American country.

Conac’s Doctor Ernesto Gramsch says the rise in radiation levels is alarming. In October, UV levels were 175 higher than they were in October of last year, which was 10 or 15% higher than the year before that. So this year it’s been a little higher, almost 30% higher than in previous years.”

Gramsch says that rise is also due to shifts in climatic wind patterns which have thinned out ozone gases over Chile in recent years. And with less protection from harmful UV rays, the number of skin cancer cases are on the rise.

Dr Cecilia Orlandi says she has seen the number of patients double since 2000.

“The number of skin cancer cases has been increasing, which yes, we can detect at a fairly early stage. But cancers from epithelioma basal cells and squamous cells have been increasing as well, and those are directly related to exposure to ultraviolet rays A and B”, Said Orlandi.

Outside Chileans are bracing for a harsh summer.

But according to a recent United Nations report, a ray of hope is slowly emerging. Moves to tackle climate change have resulted in the ozone layer finally starting to recover, with estimates that it will be back at 1980 levels by 2050.

November 26, 2014 Posted by | health, SOUTH AMERICA | Leave a comment

Pickering nuclear power station has radioactive leak

Radioactive leak at Pickering nuclear station, Caledon Enterprise, 26 Nov 14 
Heavy water contained inside reactor; no impact to public, environment 
Pickering News Advertiser

PICKERING — Thousands of litres of radioactive heavy water leaked in a reactor at the Pickering nuclear station Friday.

The incident happened in Unit 7, which was undergoing a scheduled maintenance outage, at about 4 p.m. on Nov. 21.

A valve on the moderator system opened inside the reactor building, Ontario Power Generation reported on Twitter….. 6,900 litres of heavy water leaked……http://www.caledonenterprise.com/news-story/5154334-updated-radioactive-leak-at-pickering-nuclear-station/

November 26, 2014 Posted by | Canada, incidents | Leave a comment

Call for independent Radiation Monitoring in Cumbria and Lancashire

‘Nuclear Madness’ Protest at Carlisle Railway Station  http://mariannewildart.wordpress.com/2014/11/24/nuclear-madness-protest-at-carlisle-railway-station/

100 people also stopped to sign a letter to Cumbria and Lancashire County Council regarding the lack of independent radiation monitoring .

Radiation Free Lakeland  The letter says:

Dear Cumbria and Lancashire County Council,Dear Cumbria and Lancashire County Council,

RADIATION RELEASES TO THE ENVIRONMENT

The North West’s environment used to be independently monitored by the council run Radiation Monitoring in Lancashire, RADMIL.

RADMIL was stopped a few years ago due to council cuts.  The Environment Agency often leaves monitoring and reporting to the nuclear industry

The nuclear industry and government’s new build plan includes:

Manufacture of fuel for new reactors. This begins with uranium hexafluoride shipped to Ellesmere Port, then to Capenhurst, Near Chester. Then on to Preston’s Springfields plant. Proposed new nuclear build on greenfields in Cumbria would also mean escalating radioactive releases from fuel manufacture.

This means radioactively polluting the River Ribble and Clifton Marsh Landfill in Lancashire. And in Cumbria increasing releases to the Irish Sea, Lillyhall landfill and previously nuclear free areas!   Nuclear materials are routinely sent by train and road and even by plane.

Given this escalation in radioactive emissions we urge you to reinstate regular and frequent independent radiation monitoring in Cumbria and Lancashire 

November 26, 2014 Posted by | opposition to nuclear, UK | Leave a comment

Tepco starts filling cable trench with cement as it pumps out radioactive water

Nov 26, 2014 

Tokyo Electric Power Co. started work Tuesday to fill an underground trench at the disaster-stricken Fukushima No. 1 nuclear power plant with cement while pumping up radioactive water inside at the same time.

The power company reported the beginning of the cement-pouring work for the cable trench for reactor 2 at a meeting in Iwaki, Fukushima Prefecture, with government representatives on measures to deal with increasing radioactive water at the power station.

Tepco expects to finish the work by the end of next March. The company will begin next month pouring cement in reactor 3′s trench, hoping to complete the work also by the end of March.

The trenches for the two reactors are estimated to hold 11,000 tons of radioactive water in total. The water is believed to be causing the pollution of groundwater under the seaside section of the power plant.

On Tuesday, Tepco injected 80 cu. meters of cement in the reactor 2 trench in an operation that lasted two and a half hours from around 9:30 a.m. The trench holds radioactive water that has flowed from the reactor’s turbine building.

At first, Tepco planned to stop the flow by freezing water inside the joints between the turbine building and the trench so that it can entirely remove the radioactive water from there.

But Tepco could not fully freeze the water or block the flow. So, the firm switched to the current plan to inject cement in and remove the radioactive water from the trench simultaneously.

Source: Japan Times

http://www.japantimes.co.jp/news/2014/11/26/national/tepco-starts-filling-cable-trench-cement-pumps-radioactive-water/#.VHVI88m-mKF

November 26, 2014 Posted by | Japan | | Leave a comment

Fukushima I NPP: Plan C Also Failed in Plugging Reactor 2 Trench… Now What?

November 24, 2014

Plan D of Course!

But first, recall that Plan A was to install freezing pipes at the head of the trench leading from Reactor 2 turbine building to create an ice plug so that the extremely contaminated water that had been sitting in the trench since the very beginning of the nuclear accident could be pumped out. TEPCO started the work in April this year.

That failed. The ice plug didn’t quite form.

Then recall that Plan B was to dump tons (literally) of ice and dry ice in the trench near the freezing pipes to lower the temperature of the water around the freezing pipes so that the ice plug would finally form. Workers dumped ice all day and all night, in the high ambient radiation right at the trench. That was in hot August. Try to freeze the trench with ice in hot August.

R2trenchice7-24-2014-3That also failed. Dry ice clogged the pipe, and the ice plug didn’t quite form, and TEPCO admitted there was water still coming into the trench from the turbine building. The water sitting in the turbine building comes from the reactor building after it cools the molten core somewhere in the building, and it is warm.

So TEPCO came up with Plan C.

What was Plan C? It was to fill the gap between the incomplete ice plug and the turbine building wall with fillers. TEPCO chose the combination of grout and concrete. A plug of ice, grout and concrete was formed. Sort of.

From TEPCO’s document uploaded at Nuclear Regulation Authority’s site on 11/21/2014, the plug – pink and light green in the diagram is grout (different types), dark green is concrete:

R2trenchPlanC

That failed, just as I predicted.

TEPCO finally admitted on November 17 that it was a failure after pumping out some 200 tonnes of this highly contaminated water on November 17 and seeing that the water level in the trench didn’t go down as much as they had calculated. The water was still coming in from the turbine building, and the groundwater was probably seeping in.

But not to worry. TEPCO has Plan D, and it has been already approved by Nuclear Regulation Authority.

So what is Plan D? To fill the trench with cement while pumping out the water that gets displaced (in theory) by the cement.

(Do you want to bet whether that is going to fail?)

From Mainichi English (11/18/2014), from the original Japanese article on 11/17/2014:

An effort to stop contaminated water from flowing into a trench at the crippled Fukushima No. 1 Nuclear Power Plant failed to completely halt the flow, announced Tokyo Electric Power Co. (TEPCO), the plant’s operator, on Nov. 17.

A TEPCO representative said, “We believe we have not completely stopped the water. Groundwater may also be entering the trench. We will closely analyze the changes in water level in the trench.”

TEPCO says that when around 200 tons of contaminated water was removed from the trench, the water level in the trench should have fallen by around 80 centimeters if the point of leakage between the plant’s No. 2 reactor turbine building and the trench had been fully sealed. However, the water level only fell by 21 centimeters, so TEPCO determined that the leak must be continuing.

While the water remains in the trench, TEPCO cannot create a planned underground wall of frozen soil around the No. 1 through 4 reactor buildings to stop water leakages.

And this image from Tokyo Shinbun (11/21/2014):

R2trench11212014

and reference to Plan D:

トンネルから汚染水を少しずつ抜きながら、水中で薄く広がる特殊なセメントを流し込んでトンネルをふさぐ方法への切り替えを提案する

(TEPCO) will propose (to Nuclear Regulation Authority) a new method of plugging the trench by pouring in the special cement that spread thin and wide in the water while removing the contaminated water in the trench gradually.

Special cement?

TEPCO says in the document (page 9) they submitted to NRA that it will be a mixture of cement, fly ash and underwater-inseparable admixtures (セメント、フライアッシュおよび水中不分離混和剤などの配合調整). They will use the tremie concrete placement method.

(Do you want to bet whether that is going to fail?)

The NRA meeting on November 21, 2014 was funny without participants intending to be funny, from what I read in the tweets by people watching the meeting.

At one point, Commissioner Fuketa exasperatedly asked TEPCO representatives, “So what was the point of trying to freeze the water? Was freezing even necessary at all?

The answer was no. TEPCO’s Shirai admitted (according to the tweet by @jaikoman on 11/21/2014) that there was a talk inside TEPCO that the ice plug was not necessary.

So why did they do it, and why did NRA approve it?

No one knows and no one is held accountable, while workers had to set up freezing pipes, then to pour ice, dry ice, grout, concrete, and to pump this highly contaminated water over the past 8 months in high radiation exposure. TEPCO hasn’t disclosed the radiation exposure for the workers.

Source: EXSKF

http://ex-skf.blogspot.nl/2014/11/fukushima-i-npp-plan-c-also-failed-in.html

November 26, 2014 Posted by | Japan | | Leave a comment