EDF says French nuclear reactor delayed another year to 2017 ,
* New one-year delay adds up to 10-year building period
* EDF says Areva unable to deliver key ingredients in time
* EDF still committed to EPR for UK Hinkley Point project (Adds EDF quote, background)
PARIS, Nov 18 (Reuters) – French utility EDF announced a new one-year delay for its Areva-designed EPR nuclear reactor in Flamanville, France, which it now expects to be connected to the grid in 2017, a decade after construction started.
EDF said the delay was due to Areva’s difficulties with ensuring a timely delivery of certain pieces of equipment, such as the lid and internal structure of the reactor vessel. It also said Areva had briefed it on a steam generator welding defect.
Construction on the Flamanville EPR reactor started in 2007 and it had initially been scheduled to be connected to the electricity grid in 2012, but it has been delayed repeatedly…….Four EPRs are under construction worldwide, one in France, one in Finland and two in China, but the Finnish and French projects have been plagued by billion euro cost overruns and multiyear delays.
Construction on the first EPR in Olkiluoto, Finland started in 2005 and it had originally been scheduled to go live in 2009, but it is now expected that will occurr in late 2018, almost a decade later than originally planned. Construction will have lasted 13 years, if it is not delayed again……..
Last month, European Union competition authorities gave the green light for state subsidies to EDF’s 16 billion pound project to build two EPR reactors in Hinkley Point C in southwest Britain, which are expected to start producing power from 2023……..http://in.reuters.com/article/2014/11/18/edf-nuclear-idINL6N0T85BN20141118
No comments yet.
-
Archives
- March 2023 (223)
- February 2023 (379)
- January 2023 (388)
- December 2022 (277)
- November 2022 (335)
- October 2022 (363)
- September 2022 (259)
- August 2022 (367)
- July 2022 (368)
- June 2022 (277)
- May 2022 (375)
- April 2022 (377)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS
Leave a Reply