SLO, May 27 (Reuters) - Sweden's 1,400 MW Oskarshamn-3 
nuclear reactor, the biggest in the Nordic countries, 
is expected to be back in operation on Tuesday, ramping 
up to full power by June 7, its operator said in a 
market message.
    The other reactor at the same plant, 473-MW 
Oskarshamn-1, is scheduled to restart on Monday, b
ut its output will be kept at approximately 100 MW 
during a testing period lasting two weeks.
    Output from 638 MW Oskarshamn-2 reactor 
has been reduced to 350 MW due to high vibrations 
on turbine valves, and the reduction is to last until
 the start of annual maintenance on June 1.
    Nordic countries have almost half of total installed 
nuclear power capacity offline due to maintenance as of 
early Monday. 
    The following table lists Nordic nuclear units,
 installed and available net capacity in megawatt, 
dates for the end of the outages and planned maintenance 
duration.           
    PLANT      INSTALLED  AVAILABLE  RETURN TO    MAINTENANCE
               CAPACITY   CAPACITY    NORMAL        PLANNED
 SWEDEN                                                
 Forsmark-1       984        984         -       Jul 7-Jul 30
 Forsmark-2      1,120     1,120         -       Aug 11-Aug 24
 Forsmark-3      1,170        0       Jun 15           -
 Oskarshamn-1     473         0       May 27           
 Oskarshamn-2     638        350         -          Jun 1-
                                                April 21, 2013*
 Oskarshamn-3    1,400        0       May 28           
 Ringhals-1       878         0        Jun 1           
 Ringhals-2       865        865         -       Sept 7-Oct 8
 Ringhals-3      1,063      1,063        -      June 20-Aug 10
                                                 Aug 10-Oct 31
 Ringhals-4       939         0       Jun 15           -
 FINLAND                                               -
 Olkiluoto-1      880        880         -             -
 Olkiluoto-2      880         0       Jun 13           -
 Loviisa-1        496        496         -       Aug 18-Sep 4
 Loviisa-2        496        496         -       Sep 7-Sep 25
 TOTAL          12,282      6,254                      
    * - Oskarshamn-2's permission to operate is valid until June
30, 2013. Sweden's nuclear power regulator said its extension
will depend on the reactor's modernisation.
    Sources: Nord Pool Spot, Vattenfall AB, E.ON AG, Fortum Oyj,
Teollisuuden Voima Oyj (TVO)
http://uk.reuters.com/article/2013/05/27/nordic-nuclear-idUKL5N0E80SX20130527

October 2, 2013 - Posted by | Uncategorized

No comments yet.

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.