nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

On costs of decommissioning Fort Calhoun nuclear plant, and on security

Q&A session on Fort Calhoun nuclear plant focuses on cost of decommissioning, security, By Cole Epley / Omaha World-Herald staff writer, Jun 1, 2017 

OPPD’s plan to fund dismantling and cleanup of its Fort Calhoun nuclear plant is expected to be sufficient to cover the cost, and the now-closed plant will retain its 24-hour armed security force even after the last building is no longer needed.

That was the message from federal regulators to Omaha Public Power District ratepayers and members of the public Wednesday night at a meeting on decommissioning the reactor. The plant, which closed in October, is 20 miles north of Omaha.

Questions about security — both in terms of armed guards and spent nuclear fuel left on site — and the cost of tearing down and cleaning up the plant were among issues addressed during a question-and-answer session at the Doubletree Hotel in downtown Omaha.

 Representatives from the Nuclear Regulatory Commission and OPPD fielded questions for about an hour following a general overview of the decommissioning process……

Decommissioning the plant is expected to cost about $1.5 billion in 2016 dollars. By the time the work is completed in some 60 years, the inflation-adjusted cost is expected to be roughly $3 billion…….

Within five years, OPPD will be pulling spent fuel from the storage pool inside one of the buildings and putting it in concrete casks on site. Because the U.S. has no functioning long-term storage site for spent nuclear fuel, the Fort Calhoun site will hold spent fuel in the above-ground casks indefinitely. At least as long as the fuel is there, security guards will be there, the public was told Wednesday.

Significant demolition isn’t expected until the 2050s, once much of the radioactivity at the site has decayed.

Doug Broaddus, head of the NRC branch that oversees plants like Fort Calhoun that are transitioning from operating to decommissioning, said utilities that fall short of the money needed to close their plants generally look to the same place.

June 2, 2017 Posted by | decommission reactor, USA | Leave a comment

With UK terror threat raised, decommissioning continues as normal at Dounreay nuclear site

Decommissioning continues as normal at Dounreay under heightened response rate, John O’Groat Journal, 26 May 17,   DOUNREAY said decommissioning work is continuing as normal as the UK terror threat level has been raised to critical.

Prime Minister Theresa May announced on Tuesday night the threat level was raised from severe to critical, the highest possible level after the Manchester Arena bombing on Monday night.

Critical level means an attack is expected imminently in the UK.

A spokeswoman at Dounreay has announced the site is operating at a heightened response rate but work continues as normal.

She said: “Security at Dounreay and other sites owned by the Nuclear Decommissioning Authority is kept under continuous review.

“The site is continuing to operate at a “heightened” response state and decommissioning work is continuing as normal….http://www.johnogroat-journal.co.uk/News/Decommissioning-continues-as-normal-at-Dounreay-under-heightened-response-rate-24052017.htm

May 27, 2017 Posted by | decommission reactor, safety, UK | Leave a comment

German energy groups turn to lucrative business of decommissioning nuclear power stations

Dismantling nuclear: German power firms sell new skills,http://www.reuters.com/article/us-toshiba-accounting-nuclearpower-decom-idUSKBN1850GP 9 May 17, By Christoph Steitz | FRANKFURT\  Energy groups E.ON and EnBW are tearing down their nuclear plants at massive cost following Germany’s decision to abandon nuclear power by 2022, but they are seeking to turn a burden into business by exporting their newfound dismantling skills.

Germany is the only country in the world to dump the technology as a direct consequence of Japan’s Fukushima disaster in 2011, a decision that came as a major blow to the two energy firms which owned most of Germany’s 17 operational nuclear stations.

E.ON and EnBW have already shut down five plants between them and must close another five by 2022. Not only are they losing a major profit driver – a station could earn 1 million euros ($1.1 million) a day – but are also facing combined decommissioning costs of around 17 billion euros.

This tough new reality has nonetheless forced them to rapidly acquire expertise in the lengthy and complex process of dismantling nuclear plants – presenting an unlikely but potentially lucrative business opportunity in a world where dozens of reactors are set to be closed over the next 25 years.

They say their skills are attracting the interest of international customers. Continue reading

May 10, 2017 Posted by | decommission reactor, Germany | Leave a comment

Concern that Plymouth’s representatives will have little say in decommissioning process of the Pilgrim Nuclear Power Plant.

Nuclear Decommissioning Citizens Advisory Panel strategizes with selectmen, Wicked Local, Plymouth – The state’s Nuclear Decommissioning Citizens Advisory Panel will hold its first meeting in Plymouth on May 24, but there is already concern that that Plymouth’s representatives on the panel will have little say in the decommissioning process of the Pilgrim Nuclear Power Plant.

Based on the numbers alone, Plymouth’s interests should be well represented on the panel……..

Their basic mission, Grassie said, was to meet four times a year, advise the governor, general court and the public on the issues, “serve as a conduit of communications and encourage public involvement” and receive and issue reports.

Meanwhile, Grassie said, Entergy would hold its own meetings, including with the NRC, and making decisions including, as happened with the recently closed Entergy-owned Vermont Yankee nuclear plant, selling the decommissioning function to a separate entity altogether……..

The basic priorities that town officials and panelists will take are, however, becoming clear.

Because of safety concerns the town does not want spent fuel to be left in the pool inside the reactor building. Fortunately Entergy likely doesn’t want that either because, when the spent fuel is out of the pool they can dramatically reduce on-site staff and, therefore, reduce their management costs as well.

The town does not want spent fuel stored forever on site permanently. Unfortunately there is neither a temporary or permanent national spent fuel storage facility available at this time.

In the event that spent fuel in dry cask storage remains on site for the foreseeable future the town wants to be fairly compensated.

The town does not want to see the decommissioning fund used to pay for other costs associated with the continued presence of radioactive materials at the site. That has been happening at Vermont Yankee, where the decommissioning fund has been used to pay the tax payments charged by the host community……

The town wants the rights to the so-called “1,500 acres,” the largely pristine buffer around the plant that stretches from the waterfront around the plant, to the top of the Pine Hill.

The town wants a lot but the question on the minds of the panel members right now is simple: How can they influence the process effectively toward those goals?……..http://plymouth.wickedlocal.com/news/20170506/nuclear-decommissioning-citizens-advisory-panel-strategizes-with-selectmen

May 10, 2017 Posted by | decommission reactor, USA | Leave a comment

Failure of legal attempt to halt shutdown of Indian Point Nuclear Station

Indian Point lawsuit dead before arrival, Rye City Review, May 5, 2017  by James Pero A lawsuit seeking to halt the shutdown of a long controversial nuclear power plant located at Indian Point in Buchanan is dead on arrival after staunch opposition from Westchester County’s Democratic lawmakers.

Last week, the Board of Legislators’ Democratic caucus voted to kill the lawsuit, proposed by County Executive Rob Astorino, a Republican, earlier this month, before it was even sent to committee, and well short of a vote by the full Legislature, which is required by law.

“Instead of engaging in a wasteful lawsuit where both sides are funded with taxpayer money, the best approach is to work with all of the affected communities on how to mitigate the economic, social, and environmental impacts of Indian Point closing,” said Democratic Majority Leader Catherine Borgia, of Ossining……..

County Democrats say they plan to host community meetings with affected residents and stakeholders in Indian Point as a part of their own initiative.

To lessen the economic impact on workers at the plant, Cuomo has floated a potential transition into the renewable energy sector for workers laid off by the plant’s closure.

Details of what the decommissioning process will look like will continue to be hashed out by a recently formed task force, which consists of both state and local lawmakers as well as various officials from Cuomo’s administration. http://www.ryecityreview.com/lead-stories/indian-point-lawsuit-dead-before-arrival/

May 10, 2017 Posted by | decommission reactor, USA | Leave a comment

Nuclear Decommissioning makes every other disaster in the post-war period pale into insignificanc

nuClear News No.94 April 2017  The UK Government has been forced to pay nearly £100m in a settlement with two US companies – Energy Solutions and Bechtel – for mishandling the way it awarded a £6.1bn nuclear decommissioning contract. Ministers have ordered an inquiry headed by the former boss of National Grid to find out why the procurement process was so flawed. Labour said the payout showed “dramatic levels of incompetence”. The Nuclear Decommissioning Authority (NDA) will also terminate the contract it awarded for cleaning up the UK’s old Magnox reactor sites nine years early. The sites include Bradwell, Chapelcross, Hinkley A and Hunterston A. (1)

The High Court ruled last summer that the NDA had “manipulated” and “fudged” the tender process. It meant that the wrong company won the work to decommission 12 UK nuclear sites (10 Magnox sites plus Harwell and Winfrith). The move opens the door for other bidders to attempt to reclaim their bid costs, which could run to an additional £50m. The contract was awarded in 2014 to Cavendish Fluor Partnership, a joint venture between the UK’s Babcock International and Texas-based Fluor. However, the consortium cannot be asked to take on the extra work because that could increase potential compensation claims by companies that wrongly lost out in the tender. Some industry sources have complained that the government plumped for an unrealistically low bid for the work at the outset. Another losing bidder, UK Nuclear Restoration Ltd, which is a consortium of Amec Foster Wheeler, Atkins and Rolls-Royce, said that the settlement “raises serious concerns” about the procurement process and that it has raised the implications of the judgment with the government and the NDA. (2)

Former National Grid chief executive Steve Holliday has been appointed to lead an independent inquiry into what went wrong. The inquiry will look at how the mistakes were made and by who, how the litigation was handled, and the relationship between the NDA and the government departments. Holliday will publish an interim report in October. The government now has the daunting task of starting a new tendering process for the 12 sites, as the deal with Cavendish Fluor Partnership (CFP) will end early, in September 2019 instead of 2028. (3)

Babcock said in a statement the CFP, in which it has a 65% stake, has come to a mutual agreement with the NDA to bring to an end the contract at the end of August 2019, having operated the contract for a full five years. Babcock said it had become apparent that the work that needs to be done is now materially different in volume from that specified in the NDA’s tender, and this puts the contract at risk of a legal challenge. What those material differences are remains a mystery.

The Business Secretary, Greg Clark, said: “It has become clear to the NDA through this consolidation process that there is a significant mismatch between the work that was specified in the contract as tendered in 2012 and awarded in 2014, and the work that actually needs to be done. The scale of the additional work is such that the NDA board considers that it would amount to a material change to the specification on which bidders were invited in 2012 to tender.” (4)

The failure of the contract award process was “inevitable” according to nuclear power expert Dr Paul Dorfman, from University College London’s Energy Institute. “They were set up to fail and have failed because the understanding of costs and complexity to nuclear decommissioning is changing all the time,” he said. “Magnox reactors were thrown up in a rush to give electricity too cheap to meter and create plutonium and there was no thought of how they would be decommissioned. Each Magnox reactor is bespoke so decommissioning each one is different with its own complexities and challenges. The more we learn about dealing with the ‘back end’ of nuclear power, the more we see how complex and costly it is.” (5)

Stop Hinkley Spokesperson Roy Pumfrey said: “Why should anyone believe that this astonishing level of incompetence will suddenly end when we start to build new reactors? Just because Hinkley Point C is not a Magnox reactor doesn’t just suddenly make the industry competent.” (6)

The Daily Telegraph declared today “if we could, we would stop this madness … In committing to new nuclear, we seem to have joined a runaway train, with no hope of getting off. Has not the time finally arrived for a fully fledged rethink of the merits of Britain’s nuclear energy strategy?” (7)

Roy Pumfrey continued: “We agree – it is time to stop this madness. The UK’s nuclear decommissioning costs have increased from £55.8 billion in 2008 to £117.4 billion at the last count. Although EDF is required to set aside funds for decommissioning Hinkley Point C, this is only up to an agreed limit. The taxpayer will be on the hook for the all too predictable shortfall.”

Chris Huhne, former energy secretary for the coalition government, said the remit for the enquiry by Steve Holliday was not broad enough and it needed to look at the total cost of nuclear decommissioning. “It is a complete mess, it’s deeply embarrassing but it’s actually I’m afraid only the latest in a long line of embarrassments,” Huhne told BBC Radio 4. “We’re not even scraping the surface with the problem that this legal case has exposed.” Huhne, who was energy secretary between 2010 and 2012 and left the before the contract was awarded, said the cost of decommissioning the UK’s old nuclear fleet had increased £107bn in the last five years to £161bn. “In terms of industrial strategy this makes every other disaster in the post-war period pale into insignificance.” He said the problem stemmed from how early reactors stations were complex bespoke constructions made without consideration to how they would later be disassembled. “We ordered a whole series of Savile Row suits rather than a bunch of work-a-day Marks & Spencer suits… Every single one of those reactors is different. Even the fuel rods in every single one of those reactors are different – crazy.” (8) Huhne called on the government not to allow subsidies for new reactors. That was the coalition government policy. It should be the policy again but the government seems to be relenting – it’s opening the door to exactly a repetition of the sort of disaster that we see today. (9) http://www.no2nuclearpower.org.uk/nuclearnews/NuClearNewsNo94.pdf

April 8, 2017 Posted by | decommission reactor, politics, UK | Leave a comment

EDF’s nuclear decommissioning – financial problems

Another month in UK’s failing new nuclear programme nuClear News No.94 April 2017 EDF Finances A French Parliamentary report from the National Assembly’s Commission for Sustainable Development and Regional Development says the clean-up of French reactors will take longer, be more challenging and cost much more than French nuclear operator EDF anticipates. Whereas Germany has set aside €38 billion to decommission 17 nuclear reactors, and the UK Nuclear Decommissioning Authority estimates that clean-up of UK’s 17 nuclear sites will cost between €109‒250 billion over the next 120 years, France has set aside only €23 billion to decommissioning its 58 reactors. In other words France estimates it will cost €300 million per gigawatt (GW) of generating capacity to decommission a nuclear reactor, Germany estimates €1.4 billion per GW and the UK estimates €2.7 billion per GW.

EDF says it wants to set aside a €23 billion fund to cover decommissioning and waste storage for an estimated €54 billion final bill ‒ and the difference between these two figures will be closed through the appreciating value of its equities, bonds and investments ‒ in other words, ‘discounting’. Unfortunately, recent experience has taught us that markets can go up and down over time ‒ especially the very long-time periods involved in radioactive waste management. But for a company that has huge borrowings and an enormous debt of €37 billion, €23 billion is a large sum of money to find. Any significant change in the cost of decommissioning would have an immediate and disastrous impact on EDFs credit rating ‒ something that the debt-ridden corporation can simply not afford. EDF is already in financial trouble. Along with bailing out collapsing AREVA, EDF also has to bear the huge financial burden of the failing reactor newbuild at Flamanville. It will also have to pay for extending the life of France’s existing nuclear power stations (to 2025), at a cost of €55 billion.

On top of all this the French authority tasked with disposal of all the countries vast and increasing waste burden (Andra) has recently ramped up the estimated cost for the planned national nuclear waste repository at Cigéo, to €25 billion ‒ and EDF must pay for most of Cigéo’s construction. Although €5 billion more than EDF anticipated, it still seems a gross underestimation, and the costs are likely to rise considerably. (21) http://www.no2nuclearpower.org.uk/nuclearnews/NuClearNewsNo94.pdf

April 8, 2017 Posted by | business and costs, decommission reactor, France, politics | Leave a comment

Demolition of McCluskey Room at Hanford’s Plutonium Finishing Plant

Workers demolish site of nuclear mishap in Washington state , San Franciso Chronicle, NICHOLAS K. GERANIOS, ASSOCIATED PRESS, March 30, 2017,  SPOKANE, Wash. (AP) — Workers at the Hanford Nuclear Reservation in Washington state have finished demolishing the site of a famous nuclear accident during the Cold War that exposed a man to the highest dose of radiation from the plutonium byproduct americium ever recorded, the U.S. Department of Energy announced Thursday.

The McCluskey Room was named for Harold McCluskey, who in 1976 survived the horrifying accident and died 11 years later of unrelated causes after becoming known as the Atomic Man.

 A contractor recently demolished the room — the first of four main buildings that made up the Plutonium Finishing Plant complex that will be torn down.

“Completing demolition on this building was years in the making and is both historic and a significant risk reduction,” said Tom Teynor, project director for the Department of Energy.

Hanford, located in southeastern Washington, began making most of the plutonium for the nation’s nuclear arsenal during World War II.

Plutonium production has ended and the site is now engaged in a massive cleanup of nuclear waste. That work is expected to take decades and cost tens of billions of dollars.

One of the most heavily contaminated portions of the site — half the size of Rhode Island — is the Plutonium Finishing Plant, where plutonium was converted into hockey puck-shaped disks and shipped to factories where nuclear weapons were assembled…….http://www.sfchronicle.com/news/us/article/Workers-demolish-site-of-nuclear-mishap-in-11039438.php

March 31, 2017 Posted by | decommission reactor, USA | Leave a comment

Nuclear decommissioning debacle is costly for Britain

UK nuclear decommissioning debacle costs government nearly £100m
Business secretary orders inquiry into flawed tendering process for dismantling old reactors at 12 sites as US firms get paid for out of court settlement,
Guardian, , 27 Mar 17, The government has been forced to pay nearly £100m in a settlement with two US companies for mishandling the way it awarded a £6.1bn nuclear decommissioning contract.

Ministers have ordered an inquiry headed by the former boss of National Grid to find out why the procurement process was so flawed. Labour said the payout showed “dramatic levels of incompetence”.

The government body tasked with decommissioning old reactors will also terminate the contract it awarded for cleaning up a dozen of the UK’s old nuclear sites nine years early……..

The government now has the daunting task of starting a new tendering process for the 12 sites, as the deal with Cavendish Fluor Partnership will end early, in September 2019 instead of 2028…….

The contract is being terminated early because the NDA underestimated the scale of the decommissioning required to clean up the Magnox sites, which form part of the UK’s first generation of nuclear power stations.

The share price of Babcock International Group, which has a stake in the Cavendish Fluor Partnership, has fallen by more than 3% since the government announcement…….

The NDA has an annual budget of £3.1bn, two thirds of which is spent on Sellafield in Cumbria, which stores most of Britain’s nuclear waste. https://www.theguardian.com/business/2017/mar/27/uk-nuclear-decommissioning-debacle-costs-government-100m

March 29, 2017 Posted by | decommission reactor, UK | Leave a comment

Decommissioning San Onofre Nuclear Generating Station

Trump’s budget could help get rid of the nuclear waste along the San Onofre coastline http://www.latimes.com/business/la-fi-nuclear-waste-20170320-story.html Rob Nikolewski
 A sense of momentum is building about finding a way to deal with the massive amounts of radioactive waste from nuclear power plants, including Southern California’s San Onofre Nuclear Generating Station.
Last week’s Trump administration “skinny budget” proposal, which calls for boosts in defense spending but cuts in domestic funding and federal agencies, found $120 million for starters to “initiate a robust interim storage program” while also looking at reviving the Yucca Mountain nuclear waste repository in Nevada.

Decommissioning San Onofre Nuclear Generating Station

“These investments would accelerate progress on fulfilling the federal government’s obligations to address nuclear waste, enhance national security and reduce future taxpayer burden,” a note said in the section reserved for the U.S. Department of Energy. (The Energy Department’s budget came in for a 5.6% reduction.)

A president’s budget proposals are ultimately subordinate to what Congress decides. But David Victor, chairman of the SONGS Community Engagement Panel, said the appropriation for nuclear waste may be one of the only topics in the current political environment that can generate support from members of both parties.

There are 3.6 million pounds of nuclear waste sitting along the coastline at the San Onofre plant, part of the 76,000 metric tons of spent fuel at sites nationwide.

“There’s a lot of Trump’s proposed budget that horrifies me, in particular around cutting funding for science and energy, but [long-term nuclear storage] is an area where I think the nation is now starting to make some progress,” Victor said.

Rep. Darrell Issa (R-Vista), who has introduced a bill called the Interim Consolidated Storage Act, said he thinks the chances for funding the White House nuclear waste proposal are “extremely good.”

“You have an active group of members, some of whom are Democratic members, who have a vested interest” in moving legislation forward, Issa said. “And … the fingerprints of whoever wanted to force it out would show all over.”

“As a budget line item it’s not a bad number at all,” Issa said in a telephone interview from Washington. “It’s sufficient to do the feasibility of these sites.”

Consolidated interim storage sites are designed to be built in isolated locations where multiple nuclear facilities could deposit their waste.

Two potential interim storage locations have been discussed — one in western Texas and another in eastern New Mexico.A company in Andrews, Texas, has filed an application to accept 5,000 metric tons of nuclear material. The district is represented by Republican Rep. Mike Conaway, who has co-sponsored Issa’s bill.

Getting the massive nuclear waste repository at Yucca Mountain, located about 100 miles from Las Vegas, back on track assuredly would involve a battle on Capitol Hill.

Democrats as well as Republicans from Nevada blasted the Trump proposal. “Washington needs to understand what Nevada has been saying for years: We will not be the nation’s nuclear waste dump,” said Sen. Dean Heller (R-Nev.).

The federal government spent about $15 billion to build the facility at Yucca Mountain to house nuclear waste from sites across the country. But then-Sen. Harry Reid (D-Nev.) led the fight to shut the repository down, and in 2010 President Obama suspended licensing for the site.

Yucca Mountain was scheduled to open in 2017.

While taking a tour of San Onofre last month with Issa, Rep. John Shimkus (R-Ill.), who is chairman of the House subcommittee that reviews nuclear sites, was asked if Yucca Mountain was coming back onto the bargaining table.

“It’s never been off the table,” Shimkus said.

Issa’s bill would be paid for by using part of the federal government’s Nuclear Waste Fund, which is worth upward of $40 billion and was funded by ratepayers in areas powered by nuclear plants.

A 2014 court order stopped the federal government from taking fees from electricity customers because, with Yucca Mountain sidelined, the government had no place to send nuclear waste.

“We’re paying a lot of money for the privilege of not having a solution that we were obligated to have,” Issa said. “It’s not free. It’s going to cost every taxpayer money until there’s a working solution.”

But even if Congress adopts a plan roughly similar to the White House proposal, there are a series of practical and regulatory hurdles to clear.

For example, sites such as San Onofre, which closed in 2013, would still need to place some of their spent fuel into canisters. Then federal law would need to be changed to install a reliable funding mechanism for interim sites, and a strategy would need to be adopted in order to move the waste from one place to another.

“There is still a long way to go,” Victor said. “We could have troubles on any of those fronts, but I think what’s encouraging is that on every single one of those fronts, we’re starting to see progress.”

Millions of people live within 50 miles of San Onofre, which hasn’t produced electricity since January 2012 after a steam generator leaked a small amount of radiation.

Southern California Edison is the majority owner of the plant, which is in the process of being decommissioned.

Edison officials said they were heartened by the news of $120-million proposal.

“We are pleased to see funding proposed to restart the Yucca licensing process, and continue to also support interim storage proposals that would enable [Southern California Edison] to move San Onofre’s used fuel to an off-site location,” spokeswoman Maureen Brown said

March 27, 2017 Posted by | decommission reactor, USA | Leave a comment

Global nuclear industry heading towards a decommissioning crisis

Lobbyists debate responses to the nuclear power crisis, Online opinion, .By Jim Green – , 27 March 2017The Era of Nuclear Decommissioning (END)  “……….The ageing of the global reactor fleet isn’t yet a crisis for the industry, but it is heading that way. The assessment by the ‘Environmental Progress’ lobby group that 151 GW of worldwide nuclear power capacity could be shut down by 2030 is consistent with figures from the World Nuclear Association (132 reactor shut-downs by 2035), the International Energy Agency (almost 200 shut-downs between 2014 and 2040) and Nuclear Energy Insider (up to 200 shut-downs in the next two decades)

It looks increasingly unlikely that new reactors will match shut-downs. Another 20 years of stagnation is possible, but only if China continues to do the heavy lifting. And if China’s nuclear program slows, worldwide nuclear decline is certain.

Perhaps the best characterisation of the global nuclear industry is that a new era is approaching – the Era of Nuclear Decommissioning (END). Nuclear power’s END will entail:

  • a slow decline in the number of operating reactors (unless growth in China can match the decline elsewhere);
  • an increasingly unreliable and accident-pronereactor fleet as ageing sets in;
  • countless battles over lifespan extensions for ageing reactors;
  • many battles over the nature and timing of decommissioning operations;
  • many battles over taxpayer bailouts for companies and utilities that haven’t set aside adequate funding for decommissioning;
  • more battles over proposals to impose nuclear waste repositories on unwilling or divided communities; and
  • battles over taxpayer bailouts for companies and utilities that haven’t set aside adequate funding for nuclear waste disposal.

Nuclear power is likely to enjoy a small, short-lived upswing in the next couple of years as reactors ordered in the few years before the Fukushima disaster come online. Beyond that, the Era of Nuclear Decommissioning sets in, characterised by escalating battles ‒ and escalating sticker-shock ‒ over lifespan extensions, decommissioning and nuclear waste management.

In those circumstances, it will become even more difficult than it currently is for the industry to pursue new reactor projects. A positive feedback loop could take hold and then the industry will be well and truly in crisis………http://onlineopinion.com.au/view.asp?article=18929&page=0

March 27, 2017 Posted by | 2 WORLD, decommission reactor | Leave a comment

1 reactor at Fukushima No. 2 plant, others – not certain

TEPCO to decommission 1 reactor at Fukushima No. 2 plant, mulling fate of 3 others http://mainichi.jp/english/articles/20170317/p2a/00m/0na/024000c

March 17, 2017 Posted by | decommission reactor, Fukushima continuing, Japan | Leave a comment

Pulling down nuclear reactors now looks like the only viable area for the nuclear industry

money-in-wastes-2

Nuclear Power Is In Crisis As Cost Overruns Cripple Industry Giants, New Matilda.,  By  on February 26, 2017  “………‘Rapidly accelerating crisis’

Shellenberger has recently written cataclysmic assessments of nuclear power’s “rapidly accelerating crisis” and a “crisis that threatens the death of nuclear energy in the West“.

Likewise, Dan Yurman says that a “sense of panic is emerging globally” as Toshiba exits the reactor construction industry. He adds: “After nine years of writing about the global nuclear industry, these developments make for an unusually grim outlook. It’s a very big rock hitting the pond. Toshiba’s self-inflicted wounds will result in long lasting challenges to the future of the global nuclear energy industry. Worse, it comes on top of the French government having to restructure and recapitalize Areva, its state-owned nuclear power corporation, so that it can complete two 1650 MW EPR reactors that are under construction in Europe and to begin work on the Hinkley project the UK.”

Ironically, Westinghouse, the villain in Toshiba’s demise, may have made the best strategic decision of all the nuclear utilities. In 2014, Westinghouse announced plans to expand and hopefully triple its nuclear decommissioning business. Decommissioning is undoubtedly a growth area.

The average age of the global reactor fleet now stands at 30 years. The World Nuclear Association anticipates 132 reactor shut-downs by 2035. The International Energy Agency anticipates a “wave of retirements of ageing nuclear reactors” and an “unprecedented rate of decommissioning” ‒ almost 200 shut-downs between 2014 and 2040. Up to 200 reactors are set to go offline in the next two decades according to a recent Nuclear Energy Insider article……… https://newmatilda.com/2017/02/26/nuclear-power-is-in-crisis-as-cost-overruns-cripple-industry-giants/

February 27, 2017 Posted by | 2 WORLD, decommission reactor | Leave a comment

Japan’s Nuclear Regulation Authority approves closure of Monju nuclear reprocessing reactor by next April

monju-plant-in-tsuruga-fukui-prefectureNuclear watchdog approves scrapping Monju reactor  https://www3.nhk.or.jp/nhkworld/en/news/20161228_19/ Japan’s Nuclear Regulation Authority has approved the government’s decision to scrap the Monju prototype fast-breeder nuclear reactor. The education, science and technology ministry briefed the NRA on Wednesday about the government’s decision last week about the troubled reactor in Fukui Prefecture on the Sea of Japan coast.

NRA Chairman Shunichi Tanaka said the decision is in line with the recommendation it made in November last year.
In it, the NRA urged an overhaul of a research and development project involving the reactor. It said scrapping the reactor would be an option unless a new operator were found for it.

The ministry also told the NRA on Wednesday that it will draw up a basic plan for decommissioning the reactor by next April.

It added that to eliminate possible safety risks soon, it will instruct reactor operator Japan Atomic Energy Agency to remove nuclear fuel from the reactor in about 5 and half years.

Tanaka asked the ministry to oversee the decommissioning process to ensure safety. He said the NRA will study whether relevant laws should be amended to step up regulation. He added that it may also set up an expert team to monitor the process.

December 30, 2016 Posted by | decommission reactor, Japan, reprocessing | Leave a comment

The lengthy process for decommissioning Palisades (or any) nuclear power station

DecommissioningDecommissioning Palisades nuclear plant a lengthy process, NRC says http://www.mlive.com/news/kalamazoo/index.ssf/2016/12/decommissioning_palisades_nucl.html  COVERT, MI — When nuclear plants open, they are required to provide for their eventual closing.

Entergy Corp., owner of the Palisades nuclear plant in Covert Township near South Haven, had set aside  $384.16 million in 2014, according to the most recent report submitted to the Nuclear Regulatory Commission in 2015. (The next report, due in 2017, will show the numbers for 2016.).

Entergy Corp announced Thursday that it plans to close the Palisade plant in October 2018.

Viktoria Mitlyng, spokesperson for the NRC Midwestern Region near Chicago, said Entergy has 30 days from Thursday’s announcement to formally notify the NRC of its intentions.

Closing nuclear plants is a complicated process with “lots of moving parts,” she said. “Our role as a nuclear safety regulator, is to oversee that process, including the removal of all fuel from the reactor to a “spent fuel pool” withing the facility, to its eventual placement, for an indefinite period, in dry cask storage.”

 The dry cask storage is within the plant’s protected perimeter but not within the building itself, she said.

Throughout the process, Mitlyng said, the NRC requires that security is maintained and that detailed safety protocols are The very last phase of decommissioning requires that radiation levels in the area meet NRC requirements for decommissioning.

There is not yet a site, nationally, for long-term storage of spent fuel, an ongoing policy issue in which the NRC is not involved, Mitlyng said.

Until such a facility is planned – “and there is nothing on the drawing board at this point as far as we know,” she said — spent fuel remains in dry cask storage on site.

The storage is monitored by the NRC.

During final decommissioning, plant is taken apart — all radioactive systems are removed — and the plant has 60 years to get to final phase where the decommissioning is complete and meets NRC requirements.

After the plant is totally decommissioned, only the dry cask storage remains.

Some companies perform decommissioning activities themselves, others hire another company to take down the plant. If that is done, though, the license must be transferred, with NRC approval, Mitlyng said. The NRC also monitors the status of the decommissioning fund, which cannot be used for any other operations, she said.

“I want to emphasize that our responsibility as the Nuclear Regulatory Commission is to ensure that a plant is safe, whether in operation or during decommissioning,” she said. “We have inspections for all stages of that process to assure that it is done in a way to protect people.”

Safety requirements do not change, whether a plant is operational or closing, Mitlyng said. “There is no change in the NRCs posture, none at all.”

December 9, 2016 Posted by | decommission reactor, USA | Leave a comment