nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

UK taxpayers forked out £122million for failed nuclear decommissioning deal

Nuclear Authority’s failure to carry out decommissioning deal cost taxpayer £122million
Energy Voice  by Reporter – 12/10/2017 Fundamental failures in awarding a £6.2 billion deal to decommission the UK’s ageing fleet of Magnox nuclear power stations cost the taxpayer £122 million, an official report has found.

The National Audit Office said the saga raised “serious questions” about the Nuclear Decommissioning Authority’s (NDA) understanding of procurement regulations.

The NDA ran a competitive procurement exercise for decommissioning services at 12 nuclear sites, resulting in the award of a 14-year contract for up to £6.2 billion, but the High Court found it had wrongly decided the outcome of the process.

The NDA agreed to settle claims in March 2017, the same month as the Government set up an inquiry into the Magnox contract.

Energy Solutions unsuccessfully bid for the contract, and later issued legal claims against the NDA for damages.

The High Court found that, had the NDA applied its evaluation criteria correctly, the winning bidder, Cavendish Fluor Partnership (CFP), would have been excluded from the competition.

The NDA agreed to settle legal claims with Energy Solutions and its consortium partner at the time of the bid, Bechtel, at a cost of £97.3 million.

It also spent £13.8 million on legal and external advisers, while in-house staff time cost £10.8 million.

Amyas Morse, head of the National Audit Office, said: “The NDA’s fundamental failures in the Magnox contract procurement raise serious questions about its understanding of procurement regulations; its ability to manage large, complex procurements; and why the errors detected by the High Court judgement were not identified earlier…….https://www.energyvoice.com/otherenergy/nuclear/153035/nuclear-authoritys-failure-carry-decommissioning-deal-cost-taxpayer-122million/

October 14, 2017 Posted by | decommission reactor, UK | Leave a comment

Scrutiny on Vermont Yankee’s radioactive clean-up plans

State troubled by Vermont Yankee rubble plan, Vt Digger, By Mike Faher, Oct 1 2017 BRATTLEBORO – State regulators and anti-nuclear activists are taking a stand against a proposal to reuse large amounts of Vermont Yankee’s concrete as fill when the plant is decommissioned.

The latest objections to the so-called “rubblization” plan come from the Vermont Agency of Natural Resources and the state Public Service Department. Officials want to know whether concrete from the retired nuclear plant is safe for burial on the Vernon property.

“We want to feel comfortable … that the material is truly clean,” said Chuck Schwer, director of the agency’s Waste Management and Prevention Division…….

The restoration of the Vermont Yankee site appears to be the biggest point of contention. At issue is how much NorthStar, after satisfying the NRC’s radiological cleanup requirements, will safely restore the site for future reuse……..

even after decommissioning, Vermont Yankee’s spent fuel will remain on site under 24-hour security surveillance until the federal government develops a central repository for high level nuclear waste.

“I wouldn’t say you wouldn’t be able to live there. I’m just not sure people would want to,” State said.

Whatever the property’s future, NorthStar’s plan to bury rubble on site is coming under intense scrutiny……..

Schwer told the advisory panel that, contrary to Entergy’s claims, the full extent of radiation contamination at Vermont Yankee remains a mystery. And officials say it’s not yet clear how NorthStar will address contamination before crushing and burying the concrete.

Schwer wrote in testimony filed with the utility commission that if tainted concrete is buried, “there is the potential that residual contamination could remain undetected below the surface, spread over time and pose a risk to public health and the environment.”…… https://vtdigger.org/2017/10/01/state-troubled-vermont-yankee-rubble-plan/#.WdFrqI-CzGg

October 2, 2017 Posted by | decommission reactor, USA | Leave a comment

V.C. Summer Nuclear Project Disarray – a $9 Billion Nuclear Scrapyard

$9 Billion Nuclear Scrapyard: New Aerial Photos of SCE&G’s Abandoned V.C. Summer Nuclear Project Reveal Disarray

Reactor Building and Components Left Unprotected; Most Cranes Removed, Friends of the Earth, 27 Sept 17  COLUMBIA, S.C. – Newly obtained aerial photographs of the abandoned V.C. Summer nuclear reactor construction site reveal that there is no protection of installed reactor components from the weather. (See notes on original  for links to photos.)

The photos provided to Friends of the Earth are being released in the middle of the political firestorm in South Carolina about the terminated project. It has become clear that South Carolina Electric & Gas (SCE&G) and its partner, Santee Cooper, withheld key information for years about the faltering project and were finally forced to simply walk away from on-going construction with no site shut-down plan in place.

The photos of the debacle, on which $9 billion was wasted, confirm that when work was abruptly halted on July 31, no preparation had been made to protect buildings and key components associated with reactor units 2 and 3. One existing reactor, visible in the photos, has operated at the site since 1982.

The photos, taken on September 18, reveal that nuclear reactor modules installed inside the open containment vessels are exposed to the weather. The partially finished ‘shield buildings,’ in which the reactors are located, lack roofs and sit fully exposed to the elements. Construction was only about 37% complete when the work was halted and had been continuing at a snail’s pace.

“Almost two months after the project was halted the V.C. Summer reactor construction site still looks like it was abruptly abandoned with no shut-down plan,” said Tom Clements, senior adviser to Friends of the Earth. “Not only was SCE&G grossly negligent during construction of the project, but the photos of the site reveal that the company also exhibited imprudent behavior in abandoning the project without proper closure plans. The forlorn site looks like a nuclear ghost town best suited for a Hollywood movie set,” added Clements. (Duke Energy’s abandoned nuclear reactor project in Cherokee County, South Carolina, was used as a set for the science fiction film The Abyss in 1989.)

Years of weathering will ravage the unprotected reactor components and partially constructed shield buildings and turbine buildings, according to Friends of the Earth. The turbine buildings, located adjacent to the reactors, sit without roofs and with open walls. A large number of white tent-like temporary buildings are visible and, according to information provided by site workers to Friends of the Earth, protect unused components. The short lifespan of the shelters will necessitate long-term plans if components are to be retained and not sold off.

The photos were taken by High Flyer, an anonymous pilot who for years has provided photos of V.C. Summer. The photos were taken in compliance with regulations of the Federal Aviation Administration and have been provided to Friends of the Earth for distribution in the public interest, including for regulators and law enforcement investigators. The photos can be used with credit to High Flyer (e.g. Courtesy of High Flyer © 2017). SCE&G has not provided photos of the abandoned site……… https://foe.org/9-billion-nuclear-scrapyard-new-aerial-photos-scegs-abandoned-v-c-summer-nuclear-project-reveal-disarray/

September 30, 2017 Posted by | decommission reactor, politics, USA | Leave a comment

Britain terminates nuclear decommissioning contract for Cavendish Fluor Partnership (CFP)

Reuters 29th Sept 2017, Britain’s Nuclear Decommissioning Authority (NDA) has given a notice of
termination to Cavendish Fluor Partnership (CFP) for its management and
decommissioning of the country’s 12 Magnox nuclear power reactors and
research sites, it said on Friday.

The termination notice was effective
from Sept. 1 and allows for a 24-month notice period, ending CFP’s
contract on Aug. 31, 2019.

CFP – a joint venture between British firm
Cavendish Nuclear, a subsidiary of Babcock International, and U.S. company
Fluor Inc. – was awarded the contract in 2014. But earlier this year the
government said there was a “mismatch” between the work specified in
the contract and the work that actually needed to be done.
http://uk.reuters.com/article/britain-nuclear/uk-nuclear-authority-gives-notice-to-end-cfps-magnox-decommissioning-contract-idUKL8N1MA129?rpc=401&

September 30, 2017 Posted by | business and costs, decommission reactor, politics | Leave a comment

Closed since 1977, Dounreay Fast Reactor at last being emptied of radioactive fuel elements

BBC 12th Sept 2017, Work has begun on the “challenging” task of removing radioactive fuel
elements stuck inside the most famous of Dounreay’s reactors. Closed since
1977, the Dounreay Fast Reactor is known for its dome-shaped exterior.
Almost 1,000 fuel elements have been in the reactor for years after the  work to remove them was halted because they were swollen and jammed in.

New technology has now been developed to make it possible to remove them. It
could take three years to complete the job at the nuclear power site near
Thurso in Caithness. Once all the elements have been removed work can begin
on dismantling the reactor.
http://www.bbc.co.uk/news/uk-scotland-highlands-islands-41245375

September 14, 2017 Posted by | decommission reactor, UK | Leave a comment

More money in nuclear decommissioning than in running nuclear power?

Swiss utility BKW jumps into nuclear plant dismantling business, Reuters, 7 Sept 17  Reuters Staff

  •  DfN already works with BKW at Muehleberg station
  • GE, Hitachi and Veolia also looking at decommissioning business

By John Miller ZURICH, Sept 7 (Reuters) – Swiss utility BKW AG bought a small German nuclear services company on Thursday, joining firms including GE that are banking on rising revenue from the decommissioning of European nuclear plants.

BKW, which plans to dismantle its own Muehleberg nuclear station after shuttering it in 2019, bought Dienstleistungen fuer Nukleartechnik GmbH (DfN). Its services include verifying that components removed from nuclear facilities are no longer radioactive.

Other companies, including Finland’s Fortum, privately held U.S.-based Bechtel and the GE Hitachi Nuclear Energy alliance, are also seeking to benefit from plant decommissioning in Sweden as well as Germany.

Germany decided to exit nuclear power by 2022 following the Fukushima disaster in Japan in 2011.

Similarly, energy groups E.ON and EnBW, which are now tearing down their German nuclear plants, are seeking to parlay newfound dismantling expertise by offering similar services elsewhere in the world…….https://www.reuters.com/article/bkw-nuclearpower-dismantling/swiss-utility-bkw-jumps-into-nuclear-plant-dismantling-business-idUSL8N1LO4R1

September 9, 2017 Posted by | decommission reactor, Switzerland | Leave a comment

A historic chimney is set for demolition at Sellafield.

A historic chimney is set for demolition at Sellafield. The Primary
Separation Plant Chimney Stack was built in the 1950s to provide
ventilation for surrounding buildings.

It is now one of the biggest risks at Sellafield because it does not meet modern safety standards. Demolishing
a 61-metre chimney in the middle of Europe’s most complex, congested
nuclear site is a challenge. Explosives are not an option and there is no
space for a crane so engineers have spent the last seven months getting a
self-climbing platform to the top of the chimney metre by metre so they can
begin demolition.

Demolishing this chimney will cost more than £60m. The
Nuclear Decommissioning Authority which oversees Sellafield says the
complexity of this one project demonstrates why cleaning up this site is so
expensive. £2bn was spent at Sellafield last year alone.  http://www.itv.com/news/border/2017-08-29/historic-sellafield-chimney-ready-for-demolition/

September 1, 2017 Posted by | decommission reactor, UK | Leave a comment

USA nuclear ship closed 45 years ago – but still no funds to decommission it

Aboard the NS Savannah, America’s first (and last) nuclear merchant ship, Years after shutdown, Savannah still waits for funding for its reactor decommissioning. Ars Technica, SEAN GALLAGHER – 7/26/2017  Constructed at a cost of $46.9 million ($386.8 million in 2016 dollars) and launched on July 21, 1959, the Savannah was the world’s first nuclear cargo ship and the second nuclear-powered civilian ship (coming just two years after the Soviet nuclear icebreaker Lenin). Owned by the US Maritime Administration (MARAD) and operated by commercial cargo companies, for nearly a decade she carried cargo and passengers around the world. She also acted as a floating herald for America’s seemingly inevitable, cool Atomic Age future. Savannah boasted all the latest conveniences, including one of the world’s first microwave ovens.

July 28, 2017 Posted by | decommission reactor, USA | Leave a comment

Doubts about the Vermont Yankee nuclear cleanup plan

ANTI-NUCLEAR GROUP DOUBTS VERMONT YANKEE CLEANUP PLAN, VTDIGGER,JUL. 9, 2017, 4:17 PM BY MIKE FAHER BRATTLEBORO – The company that wants to buy Vermont Yankee hasn’t properly assessed the plant for radiological contamination and “cannot know” the true cleanup cost, a Brattleboro anti-nuclear group contends.

The New England Coalition, in new filings with the Nuclear Regulatory Commission, seeks to intervene in the federal review of Vermont Yankee’s proposed sale to NorthStar Group Services.

One of the coalition’s biggest concerns mirrors worries that have been previously expressed by Vermont officials: that NorthStar could run into unforeseen problems and run out of money before finishing decommissioning.

NorthStar “cannot reasonably assure that it has adequate financial resources to own and operate Vermont Yankee for the purpose of decommissioning and fuel storage,” wrote Ray Shadis, a New England Coalition technical adviser…….

NorthStar has promised to clean up the majority of the site no later than 2030. That would make the property available for redevelopment much sooner, but some have expressed skepticism about the company’s ability to follow through.

That sentiment has spilled over to the NRC’s review of NorthStar’s plans.

In documents filed last month with the Atomic Safety and Licensing Board – an independent judicial body of the NRC – Vermont officials declared there is “significant risk” in NorthStar’s proposal due to “numerous, thus-far-unanalyzed health, safety and environmental concerns.”

State officials focused on financial issues, arguing that unexpected contamination, complications related to long-term spent fuel storage, and other issues could drastically drive up decommissioning costs.

Like Vermont officials, the New England Coalition is asking the Atomic Safety and Licensing Board for intervention status and a hearing in connection with the Vermont Yankee license transfer. The coalition offers two main contentions.

First, Shadis says the license transfer application is incomplete because it does not offer any environmental impact statement or “any substantive and reliable information about the varieties, quantities, depth and extent of radiological contamination.”

Shadis is critical of what he calls the NRC’s “tunnel vision” approach to NorthStar’s application.

He says the scope of NorthStar’s decommissioning proposal is far greater than a standard license transfer application. Instead, NorthStar is pitching “an untested method of managing decommissioning under new and unanalyzed circumstances.”……..https://vtdigger.org/2017/07/09/anti-nuclear-group-doubts-vermont-yankee-cleanup-plan/

July 17, 2017 Posted by | decommission reactor, USA | Leave a comment

Who wants to host the nuke carcass…?

http://www.fairewinds.org/newsletter-archive//oegf127i8zwvkcg5koxzivdipspzk9, June 22, 2017Demystifying Nuclear Power, Atomic Power and a Just Transition for ‘Host Communities’   By Maggie Gundersen &Ben Shulman-Reed, Atomic power plants are shutting down faster than they are being built.  These reactors conceptualized in the 1960s are failing because they are old and they are being closed because they are not competitive with renewables and therefore economically unfeasible.  People around the world understand that a Fukushima-like disaster can happen anywhere, anytime.  The nuclear power industry that dreams of building a new nuke every twelve days for the next 35 years) – totaling 1000 new rectors by 2050) are facing the harsh reality that atomic energy is not needed and is no longer wanted.

In the United States (U.S.), where largest amount of atomic power reactors in the world are located, Pilgrim in Massachusetts, Indian Point outside New York City, Oyster Creek in New Jersey, Diablo Canyon in California, and most recently Three Mile Island in Pennsylvania have recently announced their intent to close in the near future. While the shutdown of American nukes is good for our economy as well as the planet’s environment, decommissioning is a costly and complicated process that takes a toll on the local communities that hosted these giant facilities. When a nuclear power reactor shuts down, an incredible amount of work must be done to ensure a just, smooth financial transition for the local economy and also to create long-term viable storage for its toxic radioactive waste, which the U.S. Government has failed to provide. In addition to hosting the physical radioactive carcass of the power reactor for decades, the local community must restructure its economy to make it more diverse and self-sufficient as well as creating a more healthy and sustainable energy future.

Unfortunately, the usually small and economically stifled cities and towns, often referred to as ‘host communities’ to these atomic power reactors are not always given a voice at the table when it comes to deciding plans for their future – yet they are the true stakeholders. Fairewinds has continuously monitored and reported upon the challenges and defects of the Vermont Yankee atomic reactor and the lack of stakeholder respect given to its Windham County host. When it came time to close reactor in 2014, the Vermont Legislators and State Officials found themselves having to stand up to both Entergy (Vermont Yankee’s parent corporation), and the Nuclear Regulatory Commission (NRC) the alleged federal regulator for the nuclear power industry, for the Vermont’s own State’s rights and for the rights of all Vermont citizens.

Vermont is still negotiating the terms of the decommissioning process for Vermont Yankee – the state’s lone nuclear power plant and is becoming a leading example for nationwide regarding how to advocate for a smooth and just transition from atomic power operations to decommissioning and dismantlement. Vermont is seeking a just transition that will protect all the stakeholders, not only the profit interests of the power plant’s corporate owners.

The real question for all nuclear power plant host communities is: who is protecting and advocating for the rights of the ratepayers, for the level of decontamination at the site, nearby aquifers and watersheds, and an orderly economic transition for all the people in the impacted surrounding communities? The Nuclear Regulatory Commission (NRC), while the controlling interest in radiological standards and decommissioning processes on each site, does not examine or consider any of these critical human rights issues.  All the environmental justice and human rights issues of assuring ongoing open access to clean air, safe water, and uncontaminated food from the remaining carcass of a shutdown atomic power reactor falls upon local and state governments throughout the US. Vermont is leading the way in creating an open and transparent process for local communities to self-advocate in creating a safer and more transparent decommissioning process and transition to a safe and permanently uncontaminated dismantlement of these highly radioactive nukes.

By opening a wide dialogue as we all advocate for an open and transparent decommissioning process, we believe the U.S. can shed its title of founding nuclear energy and instead become a global leader in cleaning up the mess we started. By following Vermont’s of paying close attention to the interests of our local governments, ratepayers and host communities, we all will begin to achieve just and safe transitions from the glut of toxic radioactive nuclear power plant carcasses coming our way as atomic power continues to become economically unviable.

It is Fairewinds’ goal to help communities work together to achieve a safer transition in their energy futures by shifting energy paradigms to an economically feasible and environmentally compatible model for the health and survival of our species and our planet.

June 23, 2017 Posted by | decommission reactor, USA | Leave a comment

South Korea’s  Kori No. 1 nuclear reactor shut down

Korea’s oldest nuclear reactor ceases operation, http://www.koreaherald.com/view.php?ud=20170618000190   By Kim Da-sol (ddd@heraldcorp.com), Kori No. 1, South Korea’s oldest nuclear reactor located in Busan, ceased operation Sunday at midnight after four decades.

Its operator Korea Hydro and Nuclear Power Co. said that it cut the power supply Saturday and began the cooling-down process of the reactor. It was officially decommissioned, with the temperature of the reactor gradually dropping to 90 degrees Celsius, from its normal operation at 300 degree Celsius, the KHNP said. Officials will then relocate the spent nuclear fuel stored inside the rector to a liquid sodium-cooled reactor for reprocessing.

The actual dismantling of the facilities is expected to start no later than 2022. The KHNP expects that at least 634 billion won ($559 million) is required for the dismantling. They also need to submit a dismantlement plan within five years for the NCCS’ approval.

The state-run Nuclear Safety and Security Commission, which approved earlier this month the permanent shutdown of Kori No. 1, said it will continue to check the safety management of the suspended reactor on a regular basis until the dismantlement.

Following the government’s approval in 2007, Kori No. 1’s operation was extended by 10 years after a 30-year run.

Some experts oppose the planned reprocessing of nuclear waste, saying the technology, though effective in reducing the volume of waste, could complicate waste disposal by creating different types of radioactive waste.

Under President Moon Jae-in, the South Korean government aims to close all nuclear power plants by shutting down aged facilities and eventually phasing out the rest over the next 40 years.

June 19, 2017 Posted by | decommission reactor, South Korea | Leave a comment

The risky jobs of closing down 200 nuclear reactors around the world

Here’s what dismantling a nuclear reactor involves: Robots, radiation, risk  IEA says about 200 nuclear reactors around the world will be shut down over the next quarter century http://www.business-standard.com/article/international/here-s-what-dismantling-a-nuclear-reactor-involves-robots-radiation-risk-117061200298_1.html   Reuters  |  Muelheim-Kaerlich, Germany June 12, 2017 As head of the nuclear reactor, Thomas Volmar spends his days plotting how to tear down his workplace. The best way to do that, he says, is to cut out humans.

About 200 nuclear reactors around the world will be shut down over the next quarter century, mostly in Europe, according to the Energy Agency. That means a lot of work for the half a dozen companies that specialise in the massively complex and dangerous job of dismantling plants.

Those firms — including Areva, Rosatom’s Engineering Services, and Toshiba’s — are increasingly turning away from humans to do this work and instead deploying robots and other new technologies.

That is transforming an industry that until now has mainly relied on electric saws, with the most rapid advances being made in the highly technical area of dismantling a reactor’s core — the super-radioactive heart of the plant where the nuclear reactions take place.

The transformation of the sector is an engineering one, but companies are also looking to the new technology to cut time and costs in a competitive sector with slim margins.

Dismantling a plant can take decades and cost up to 1 billion euros ($1.1 billion), depending on its size and age. The cost of taking apart the plant in will be about 800 million euros, according to sources familiar with the station’s economics.

Some inroads have already been made: a programmable robot arm developed by has reduced the time it takes to dismantle some of the most contaminated components of a plant by 20-30 per cent compared with conventional cutting techniques.

For and rival Westinghouse, reactor dismantling is unlikely to make an impact on the dire financial straits they are mired in at present as it represents just a small part of their businesses, which are dominated by plant-building.

But it nonetheless represents a rare area of revenue growth; the global market for decommissioning services is expected to nearly double to $8.6 billion by 2021, from $4.8 billion last year, according to research firm MarketsandMarkets. Such growth could prove important for the two companies should they weather their current difficulties.

“We’re not talking about the kind of margins is making on its iPhone,” said Thomas Eichhorn, head of Areva’s German dismantling activities. “But it’s a business with a long-term perspective.”

When reactors were built in the 1970s, they were designed to keep radiation contained inside at all costs, with little thought given to those who might be tearing them down more than 40 years later.

First, engineers need to remove the spent nuclear fuel rods stored in reactor buildings — but only after they’ve cooled off. At this took about two years in total. Then peripheral equipment such as turbines need to be removed, a stage has begun and which can take several years.

Finally, the reactor itself needs to be taken apart and the buildings demolished, which takes about a decade. Some of the most highly contaminated components are cocooned in concrete and placed in iron containers that will be buried deep underground at some point.

Robots under water

While the more mundane tasks, including bringing down the plants’ outer walls, are left to construction groups such as Hochtief, it’s the dismantling of the reactor’s core where more advanced skills matter — and where the use of technology has advanced most in recent years.

Enter companies such as Areva, Westinghouse, Nukem Technologies, as well as GNS, owned by Germany’s four operators. They have all begun using robots and software to navigate their way into the reactor core, or pressure vessel.

“The most difficult task is the dismantling of the reactor pressure vessel, where the remaining radioactivity is highest,” said Volmar, who took charge of the RWE-owned plant two years ago. “We leave this to a specialised expert firm.”

The vessel — which can be as high as 13 metres and weigh up to 700 tonnes — is hidden deep inside the containment building that is shaped like a sphere to ensure its 30-centimetre thick steel wall is evenly strained in case of an explosion.

The 2011 Fukushima disaster and the Chernobyl accident of 1986 are imprinted in the world’s consciousness as examples of the catastrophic consequences of the leakage of radioactive material.

France’s recently won the contract to dismantle the pressure vessel internals at Vattenfall’s 806 megawatts (Mw) Brunsbuettel in Germany, which includes an option for the Swedish utility’s 1,402 MW Kruemmel site.

There, the group will for the first time use its new programmable robot arm. It hopes this will help it outstrip rivals in what is the world’s largest dismantling market following Germany’s decision to close all its last nuclear plants by 2022, in response to the Fukushima disaster.

operates under water because the liquid absorbs radiation from the vessel components — reducing the risk of leakage and contamination of the surrounding area. The chamber is flooded before its work begins.

Areva’s German unit invests about 5 per cent of its annual sales, or about 40 million euros, in research and development, including in-house innovation such as  By comparison, the world’s 1,000 largest corporate R&D spenders, on average, spent 4.2 per cent last year, according to PwC.

The robot arm technology helped beat by winning tenders to dismantle pressure vessel internals at EnBW’s Philippsburg 2 and Gundremmingen 2 blocks, industry sources familiar with the matter said.

and both declined to comment. — whose US business filed for bankruptcy in March — did not respond to repeated requests for comment. Time and money

Britain’s OC Robotics has built the LaserSnake2, a flexible 4.5-metre snake arm, which can operate in difficult spaces and uses a laser to increase cutting speeds — thus reducing the risk of atmospheric contamination. It was tested at the Sellafield nuclear site in west Cumbria last year.

This followed France’s Alternative Energies and Atomic Energy Commission (CEA), whose laser-based dismantling technology generates fewer radioactive aerosols — a key problem during cutting — than other technologies.

The complexity of the dismantling process is also giving rise to modelling software that maps out the different levels of radiation on plant parts, making it easier to calculate the most efficient sequence of dismantling – the more contaminated parts are typically dealt with first – and gives clarity over what safety containers will be needed to store various components.

GNS, which is jointly owned by E.ON, RWE, and Vattenfall, is currently helping to dismantle the German Neckarwestheim 1 and Philippsburg 1 reactors, using its software to plan the demolition.

The company also hopes to supply its software services for the dismantling of PreussenElektra’s Isar 1 reactor, which is being tendered, and aims to expand to other European countries.

“Two things matter: time and money,” said Joerg Viermann, head of sales of waste management activities at 

“The less I have to cut, the sooner I will be done and the less I will spend.”

June 14, 2017 Posted by | 2 WORLD, decommission reactor, Reference | 1 Comment

Japan’s struggle to decommission Fukushima nuclear reactors

Japan struggling to decommission Fukushima nuclear reactors http://pulsenews.co.kr/view.php?sc=30800023&year=2017&no=395464 , By Hwang Hyung-gyu, 2017.06.13 It appears that much has changed at the Fukushima Daiichi Nuclear Power Plant in Japan since the worst nuclear disaster since Chernobyl six years ago. The ongoing restoration work evidently made progress, but decommissioning is still an uphill battle – posing as a lesson for South Korea as it has recently decided to retire the country’s first nuclear reactor and phase out of commercial nuclear power.

All ordinary visitors, including reporters, must wear a protective gear such as two layers of socks, gloves, a helmet, a filter mask covering the mouth and nose, a safety vest and rubber shoes before approaching a point just 80 meters away from the crippled power station. A hazmat suit which had been required just six months ago was no longer recommended as the radiation level was lowered.

The passage route to the first reactor was flanked by gigantic storage tanks that hold contaminated water.

Reactors still showing skeletal steel frames and roof debris remind a 17-meter-high tsunami which flooded the facility on March 11 in 2011 and caused a hydrogen explosion, bringing the plant to a complete standstill.

Molten fuel rods were completely retrieved from the reactor Unit 4, but progress is much slow in Unit 2, where an internal survey is not even started. The six-year clean-up work for the four nuclear reactors was only a fraction of time.

Tokyo Electric Power Co. (Tepco), the operator of the plant, has deployed 7,000 workers including its own staff to the site. Their first priority is to tackle the influx of contaminated groundwater. Workers erected a cutoff wall and pumped out upstream groundwater, but still, about 100 to 150 tons of contaminated water is generated every day, according to Tepco. The amount of the contaminated water in storage tanks reaches nearly 1 million tons. It has not yet been decided how to treat the water.

The operation for complete decommissioning is a long way to go. It will take 30 years to finish the job, including the treatment of contaminated water, said Yuichi Okamura, Tepco communication manager.

The Japanese government is going all out to develop advanced robot and drone technology to accurately grasp the internal situation of the reactors to support decommissioning.

June 14, 2017 Posted by | decommission reactor, Japan | Leave a comment

Permanent shutdown of unit 1 of South Korea’s Kori nuclear power plant

World Nuclear News 9th June 2017, The permanent shutdown of unit 1 of the Kori nuclear power plant has been approved by the South Korea’s nuclear safety regulator. The unit – the country’s oldest operating reactor unit – will be taken offline on 19 June.

Kori 1 is a 576 MWe pressurized water reactor that started commercial operation in 1978. A six-month upgrading and inspection outage at Kori 1 in the second half of 2007 concluded a major refurbishment program and enabled its relicensing for a further ten years. A subsequent relicensing process could have taken Kori 1 to 2027, but Korea Hydro & Nuclear Power (KHNP) announced in August 2015 that it had withdrawn its application to extend the unit’s operating licence. In June last year, the company applied to decommission the reactor.  http://www.world-nuclear-news.org/C-Final-shutdown-approaches-for-Koreas-oldest-reactor-0906175.html

June 12, 2017 Posted by | decommission reactor, South Korea | Leave a comment

Planning for new phase in getting rid of Dounreay – UK’s 1950s nuclear reactor complex

BBC 7th June 2017 A planning application is being prepared for a new phase in the decommissioning of the Dounreay nuclear power complex in Caithness.
Buildings on the experimental nuclear energy site, which dates to the 1950s, are being emptied of radioactive material and demolished. Starting in 2018, the planned next stage would involve dismantling reactors.

New temporary buildings would also need to be built to aid the new phase. The new buildings would include facilities for handling the clean up and demolition of areas of the site called the Silo and The Shaft. Also included are plans for restoration and landscaping work to restore areas of land to close to how they looked before the construction of Dounreay. The phase would take the site near Thurso to what is called its interim end state. Dounreay Site Restoration Limited has notified Highland Council that it expects to submit the planning application later this year.
http://www.bbc.co.uk/news/uk-scotland-highlands-islands-40188815

June 10, 2017 Posted by | decommission reactor, UK | Leave a comment