Private Companies Pitch New Ways To Store USA’s piling up nuclear wastes

As Nuclear Waste Piles Up, Private Companies Pitch New Ways To Store It,  NPR, JEFF BRADY  1 May 19, Congress is once again debating how to dispose of the country’s growing inventory of nuclear waste. Sen. John Barrasso, R-Wyo., is proposing legislation that would jump-start licensing hearings for the Yucca Mountain nuclear waste storage site in Nevada. The Trump administration also is asking Congress for money to resume work on that decades old project.But that may not end local opposition or a longstanding political stalemate. And in the meantime, nuclear plants are running out of room to store spent fuel.

Running out of room

The Peach Bottom Atomic Power Station in south-central Pennsylvania illustrates the problem. It’s one of 80 sites, across dozens of states, where nearly 80,000 metric tons of waste from power plants is stored where it was generated, at taxpayer expense.

Spent fuel removed from the Peach Bottom reactor is first stored in racks in a big pool. It’s surrounded by a bright yellow plastic barrier and signs that read “Caution: Radiation Area.”

“They are under about 22 feet of water,” says reactor engineering manager Mark Parrish. “They are continuously being cooled, as they still have some amount of decay heat even after they’ve operated in the reactor.”

The spent fuel stays here for seven to 10 years while it cools.

Once it’s safe to remove the spent fuel from the pool, it’s stored outside in white metal casks that look like big hot water heaters. They are lined up on a concrete base behind razor wire and against a hillside near the power plant.

Currently there are 89 casks at Peach Bottom with room for three more, says Pat Navin, site vice president for Exelon, the company that partially owns and operates the power plant.

“That is 40 years worth of spent fuel stored over there currently and it’s less than the size of a football field,” says Navin. “Probably half a football field.”…….

without a permanent disposal site, Navin says they’re going to run out of room. So they’re expanding the temporary storage to hold all the waste generated through the 60 years the plant is licensed to operate…..

Private companies propose their own storage plans

As the waste piles up, private companies are stepping in with their own solutions for the nation’s radioactive spent fuel. One is proposing a temporary storage site in New Mexico, and another is seeking a license for a site in Texas.

But most experts agree that what’s needed is a permanent site, like Yucca Mountain, that doesn’t require humans to manage it.

“Institutions go away,” says Edwin Lyman, acting director of the Nuclear Safety Project at the Union of Concerned Scientists. “There’s no guarantee the owner will still be around for the duration of time when that waste remains dangerous, which is tens or hundreds of thousands of years.”

A California company says it has a viable plan for permanent storage. Deep Isolation wants to store spent fuel in holes drilled at least 1,000 feet underground in stable rock formations. The company says the waste would be separate from groundwater and in a place where it can’t hurt people.,,,,,,

Regulators require retrieval, because new technology could develop to better deal with the spent fuel. And the public is less likely to accept disposal programs that can’t be reversed, according to the International Atomic Energy Agency.

Proving the waste can be retrieved may be the easy part. The bigger challenge is federal law, which doesn’t allow private companies to permanently store nuclear waste from power plants.

Current law also says all the waste should end up at Yucca Mountain in Nevada. By contrast, Deep Isolation’s technology would store waste at sites around the country, likely near existing nuclear power plants.

“I just don’t see how there would be political support from every other state, other than Nevada, for changing the law, so that spent nuclear fuel could stay in your state forever,” says Lyman.

Despite the law, all that waste in dozens of states is staying put for now. https://www.npr.org/2019/04/30/716837443/as-nuclear-waste-piles-up-private-companies-pitch-new-ways-to-store-it

May 2, 2019 Posted by | USA, wastes | Leave a comment

Even USA’s conservative groups are objecting to subsidising Ohio’s nuclear power stations

May 2, 2019 Posted by | USA, wastes | Leave a comment

U.S. Dept of Energy pledges to remove plutonium from Nevada

Energy Department says it will remove plutonium from Nevada, abc,By SCOTT SONNER, ASSOCIATED PRESS,  Apr 30, 2019,U.S. Energy Secretary Rick Perry is pledging to expedite the removal of weapons-grade plutonium secretly hauled to Nevada last year as the state and Trump administration remain locked in a court battle about whether the shipment was legal.

The Energy Department intends to start removing the highly radioactive material in 2021 and finish by the end of 2026, Perry said in an April 24 letter to U.S. Sen. Catherine Cortez Masto, a Nevada Democrat.

He also assured her in the letter released Tuesday that his department won’t ship any more plutonium from South Carolina to the Nevada Nuclear Security Site north of Las Vegas.

Nevada still is seeking a formal court order preventing any shipments because it says the agency’s track record shows it cannot be trusted. It also has a related case before the 9th U.S. Circuit Court of Appeals.

A federal judge in South Carolina has ordered the U.S. government to remove a metric ton (2,204 pounds) of plutonium from the Savannah River site by Jan. 1, 2020, and haul out an additional 5 metric tons (11,020 pounds) in future years.

Nevada sued in November, accusing the Energy Department of failing to do the necessary environmental reviews before adopting a plan last August to ship the plutonium to the state.

The department disclosed in January that it already had shipped half a metric ton (1,102 pounds) of the material before Nevada sued but kept it secret for national security reasons…….

The Energy Department has said it plans to forward the plutonium to the Waste Isolation Pilot Plant in New Mexico by the “2026-2027 timeframe.” https://abcnews.go.com/Technology/wireStory/energy-department-remove-plutonium-nevada-62738713

May 2, 2019 Posted by | - plutonium, USA | Leave a comment

Nevada Gov. Steve Sisolak reiterates Nevada opposition to Yucca nuclear storage

May 2, 2019 Posted by | opposition to nuclear, politics, wastes | Leave a comment

USA’s Nuclear Regulators look to New Mexico desert For Temporary Waste Storage Facility

May 2, 2019 Posted by | USA, wastes | Leave a comment

Exploitation of foreign workers in Japan’s Fukushima nuclear clean-up

Japan needs thousands of foreign workers to decommission Fukushima plant, prompting backlash from anti-nuke campaigners and rights activists, SCMP  Julian Ryall , 26 Apr, 2019

Activists are not convinced working at the site is safe for anyone and they fear foreign workers will feel ‘pressured’ to ignore risks if jobs are at risk
Towns and villages around the plant are still out of bounds because radiation levels are dangerously high

Anti-nuclear campaigners have teamed up with human rights activists in Japan to condemn plans by the operator of the crippled Fukushima Daiichi nuclear plant to hire foreign workers to help decommission the facility.

Tokyo Electric Power Co (TEPCO) has announced it will take advantage of the government’s new working visa scheme, which was introduced on April 1 and permits thousands of foreign workers to come to Japan to meet soaring demand for labourers. The company has informed subcontractors overseas nationals will be eligible to work cleaning up the site and providing food services.

About 4,000 people work at the plant each day as experts attempt to decommission three reactors that melted down in the aftermath of the March 2011 Great East Japan Earthquake and the huge tsunami it triggered. Towns and villages around the plant are still out of bounds because radiation levels are dangerously high.

TEPCO has stated foreign workers employed at the site must have Japanese language skills sufficient for them to understand instructions and the risks they face. Workers will also be required to carry dosimeters to monitor their exposure to radiation.

Activists are far from convinced working at the site is safe for anyone and they fear foreign workers will feel “pressured” to ignore the risks if their jobs are at risk.

“We are strongly opposed to the plan because we have already seen that workers at the plant are being exposed to high levels of radiation and there have been numerous breaches of labour standards regulations,” said Hajime Matsukubo, secretary general of the Tokyo-based Citizens’ Nuclear Information Centre. “Conditions for foreign workers at many companies across Japan are already bad but it will almost certainly be worse if they are required to work decontaminating a nuclear accident site.”

Companies are desperately short of labourers, in part because of the construction work connected to Tokyo hosting the 2020 Olympic Games, while TEPCO is further hampered because any worker who has been exposed to 50 millisieverts of radiation in a single year or 100 millisieverts over five years is not permitted to remain at the plant. Those limits mean the company must find labourers from a shrinking pool.

In February, the Tokyo branch of Human Rights Now submitted a statement to the UN Human Rights Council in Geneva demanding action be taken to help and protect people with homes near the plant and workers at the site.

“It has been reported that vulnerable people have been illegally deceived by decontamination contractors into conducting decontamination work without their informed consent, threatening their lives, including asylum seekers under false promises and homeless people working below minimum wage,” the statement said. “Much clean-up depends on inexperienced subcontractors with little scrutiny as the government rushes decontamination for the Olympic Games.”

Cade Moseley, an official of the organisation, said there are “very clear, very definite concerns”.

“There is evidence that foreign workers in Japan have already felt under pressure to do work that is unsafe and where they do not fully understand the risks involved simply because they are worried they will lose their working visas if they refuse,” he said……

https://www.scmp.com/news/asia/east-asia/article/3007772/japan-needs-thousands-foreign-workers-decommission-fukushima

April 30, 2019 Posted by | civil liberties, employment, Japan, politics, wastes | Leave a comment

Britain’s costly nuclear submarines – dead but not buried

The Royal Navy Can’t Seem to Figure Out How to Dispose of Old Nuclear Submarines,  National Interest  by Michael Peck 228 Apr 19,

Not an easy problem to solve.  “………Britain has retired twenty nuclear submarines since 1980. None have been disposed of, and nine still contain radioactive fuel in their reactors, according to an audit by Britain’s National Audit Office. These subs spent an average of twenty-six years on active service—and nineteen years out of service.  

“Because of this, the Department [Ministry of Defense] now stores twice as many submarines as it operates, with seven of them having been in storage for longer than they were in service,” the audit states.

Even worse is the price tag. Britain has spent 500 million pounds ($646.4 million) maintaining those decommissioned subs between 1980 and 2017. Full disposal of a nuclear sub would cost 96 million pounds ($112.1 million). As a result, the total cost for disposing of the Royal Navy’s ten active subs and twenty retired vessels would be 7.5 billion pounds ($9.7 billion), NAO calculated.

Dismantling and disposing of a nuclear sub is a complex process. The nuclear fuel must be carefully removed from the reactor using special facilities. Then the submarine itself must be dismantled, again with extra care paid to removing the radioactive parts of the vessel. Just one contractor—Babcock International Group PLC—is “currently the Department’s sole supplier capable of undertaking most of the Department’s defueling and dismantling requirements,” noted NAO. “It owns the nuclear-licensed dockyards and facilities in both Devonport and Rosyth, and also provides aspects of the related projects.”

Fuel removal ceased in 2004 after British nuclear regulators found the removal facilities didn’t meet standards. Yet the Ministry of Defense still lacks a fully-funded plan for defueling.

All of this is taking a toll on a Royal Navy already underfunded and struggling to fund new ships. “The Department pays an estimated £12 million [$15.5 million] a year to maintain and store the nine fueled submarines currently stored in Devonport,” NAO found. “Maintaining fueled, rather than unfueled, submarines also presents additional technical uncertainties and affects dock availability.  ….

Until submarines are prepared, the Department must keep them partially crewed, potentially affecting the Department’s ability to redeploy its personnel.”The plan is to begin defueling subs, beginning with HMS Swiftsure, in 2023. But even then, the Ministry of Defense will have to deal with different subs that have different disposal requirements. “At present, the Department does not have a fully developed plan to dispose of Vanguard, Astute and Dreadnought-class submarines, which have different types of nuclear reactor,” NAO pointed out. “For the Vanguard and Astute-class it has identified suitable dock space which, if used, will need to be maintained.”

Interestingly, the British military gets an exemption when it comes to nuclear waste. “Within the civil nuclear sector, organizations must consider nuclear waste disposal during the design stage of power stations and nuclear infrastructure. The Department does not have a similar obligation.”

Britain isn’t the only nation that has problems disposing of nuclear warships. The Soviet Union sank nineteen nuclear vessels, and fourteen shipborne nuclear reactors, at sea, sparking fears of an environmental catastrophe. Even the U.S. Navy is struggling with how to dispose of nuclear subs and aircraft carriers, such as the decommissioned carrier USS Enterprise.  https://nationalinterest.org/blog/buzz/royal-navy-cant-seem-figure-out-how-dispose-old-nuclear-submarines-54322

April 29, 2019 Posted by | UK, wastes, weapons and war | Leave a comment

USA’s Dept of Energy fails to provide adequate funding for Hanford nuclear clean-up

Hanford Cleanup Plans at Serious Risk, Advisory Board Says  https://www.exchangemonitor.com/hanford-cleanup-plans-serious-risk-advisory-board-says/

BY EXCHANGEMONITOR, 26 Apr 19, Cleanup plans for the Hanford Site in Washington state, along with remediation milestones established under the Tri-Party Agreement, are in “serious jeopardy,” the Hanford Advisory Board said Wednesday in its annual budget advice letter to the Department of Energy.

“The HAB views the combined lack of compliant budget appropriations, the unanticipated problems at Hanford, and the extreme increase in estimated funding levels identified in the lifecycle cost report with great concern,” the board told DOE. Those factors will result in cleanup taking longer and costing more, putting workers, the environment, and the public at increased risk, the letter says.

“They will also result in additional discussion about reducing standards or potentially conducting a lesser quality cleanup,” according to the board.

Unanticipated problems in work at the former plutonium production complex have included the spread of radioactive contamination at the Plutonium Finishing Plant demolition in 2017 and the May 2017 collapse of the older of two PUREX Plant radioactive waste storage tunnels.

The Energy Department has addressed the issues, but the costs and schedule impacts from these and other unanticipated setbacks could compound the challenge of meeting milestones set under the legally binding Tri-Party Agreement on Hanford cleanup, the budget letter said.

The latest Hanford Lifecycle Scope, Schedule and Cost Report, released in January, “is particularly concerning,” the board said. It put the remaining cost of Hanford cleanup and the initiation of long-term stewardship at $323 billion to $677 billion, and said work could continue beyond this century. The amount of funding needed annually would increase to $4 billion starting in fiscal 2020 and later could peak as high as $16 billion in 2088 under the worst-case scenario.

“Receiving appropriation for even the low-range annual funding estimates will be extremely challenging, thereby putting the cleanup mission in further jeopardy,” the letter said.

For fiscal 2020, which begins Oct. 1, DOE is seeking $2.1 billion for the two offices at Hanford. That would be a $400 million reduction from current funding levels.

April 27, 2019 Posted by | politics, USA, wastes | Leave a comment

Decommissioning contracts announced for Dounreay nuclear site in Scotland.

£400m decommissioning contract winners for Scotland nuclear site revealed, Infrastructure Intelligence  Ryan Tute, 24 Apr 19, Dozens of companies and their supply chains have been announced as winners for six decommissioning framework contracts, worth up to £400m, at the Dounreay nuclear site in Scotland.

Dounreay Site Restoration Limited (DSRL), was the site of Britain’s former centre of nuclear fast reactor research and development for 60 years and is set to be demolished and cleaned up.

Initially for up to four years with the possibility of extensions of up to an additional three years, winners will take work at the site, delivered on behalf of the Nuclear Decommissioning Authority (NDA). ……

Full list of winners:

  • AECOM E&C UK; MW Hargreaves; Kier Infrastructure and Overseas; Morson Projects; NIS; NSG Environmental; Squibb Group; Westinghouse Electrical Company UK
  • Dounreay Decommissioning Framework (DDF) Alliance; Cavendish Nuclear; BAM Nuttall; KDC Contractors; JGC Engineering and Technical Services
  • Dounreay Wood Alliance (DWA); Wood; Aquila Nuclear Engineering; GD Energy Services; Orano Projects
  • Jacobs UK; Atkins
  • Nuclear Decommissioning Ltd (NDL); James Fisher Nuclear; REACT Engineering; Shepley Engineers; WYG Engineering; JBV Demolition; RPS Consulting Services
  • Nuvia; Graham Construction; Oxford Technologies; Thompson of Prudhoe    http://www.infrastructure-intelligence.com/article/apr-2019/%C2%A3400m-decommissioning-contract-winners-scotland-nuclear-site-revealed

April 25, 2019 Posted by | UK, wastes | Leave a comment

Wastes from other nuclear stations could be dumped at Hinkley Point A

Somerset Live 23rd April 2019 Fears ‘skips of nuclear waste’ could be transported through Bridgwater to be stored at Hinkley Point A. Dozens of skips full of nuclear waste could
soon be transported through Bridgwater from other parts of the UK. Magnox
Ltd currently operates the Hinkley Point A site near Stogursey, which
includes a small area where nuclear waste is stored before being moved
elsewhere for processing. Currently, only waste which is generated on the
Hinkley site can legally be stored there. But the company is putting
forward plans to allow waste from other nuclear power stations to be
transported to Hinkley by road – via Bridgwater.

https://www.somersetlive.co.uk/news/somerset-news/fears-skips-nuclear-waste-could-2788091

April 25, 2019 Posted by | UK, wastes | Leave a comment

Germany launches public meetings, in search of nuclear waste repository solution

Public info event kicks off search for nuclear waste repository  https://www.cleanenergywire.org/news/public-info-event-kicks-search-nuclear-waste-repository

Nuclear phase-out, Clean Energy Wire , 24 Apr 19  The next stage of the search for a final repository for Germany’s nuclear waste is launched today with a series of public information events in major German cities, the Federal Office for the Safety of Nuclear Waste Management (BfE) says. Following protests, exploration of a site in Gorleben was terminated, and a multi-stakeholder commission proposed a new search starting with a “blank map” and aiming to find a suitable site by 2031. The procedure was approved as law by parliament in 2017. The new rules prioritise citizens’ participation and transparent research processes. Researchers from the Federal Company for Radioactive Waste Disposal (BGE) are currently analysing geological data from all German states.
Germany will have to store around 28,100 cubic metres of high-level radioactive waste by 2080, for up to several million years. The search will focus on possible storage sites in rock salt, clay rock and crystalline granite, but experience at sites like Gorleben has shown that no community is particularly keen on living next to nuclear waste storage.

April 25, 2019 Posted by | Germany, wastes | Leave a comment

UK is stuck with 20 dead nuclear submarines – what to do with them?

April 23, 2019 Posted by | UK, wastes, weapons and war | Leave a comment

Japan Atomic Power looks to big business cleaning up dead nuclear plants

Japan Atomic Power considers launching unit that specializes in scrapping nuclear plants  https://www.japantimes.co.jp/news/2019/04/16/national/japan-atomic-power-considers-launching-unit-specializes-scrapping-nuclear-plants/#.XLzjyDAzbGg KYODO, APR 16, 2019

Japan Atomic Power Co. is considering setting up a subsidiary specializing in the scrapping of retired nuclear reactors at domestic power plants, sources close to the matter said Tuesday.

Japan Atomic Power, a wholesaler of electricity generated at its nuclear plants, is planning to have U.S. nuclear waste firm EnergySolutions Inc. invest in the reactor decommissioning service unit, which would be the first of its kind in Japan, the sources said.

The Tokyo-based electricity wholesaler, whose shareholders are major domestic power companies, will make a final decision by the end of this year, they said.

The plan is to support power companies’ scrapping of retired reactors using Japan Atomic Power’s expertise in decontaminating and dismantling work, in which it has been engaged in since before the 2011 nuclear disaster at Tokyo Electric Power Company Holdings Inc.’s Fukushima No. 1 complex, according to the sources.

The plan comes as a series of nuclear reactor decommissioning is expected at power companies in the country. Since stringent safety rules were introduced after the Fukushima disaster, 11 reactors, excluding those at the two Fukushima plants of Tepco, are slated to be scrapped.

Nuclear reactors are allowed to run for 40 years in Japan. Their operation can be extended for 20 years, but operators will need costly safety enhancement measures to clear the Nuclear Regulation Authority’s screening.

Decommissioning a reactor with an output capacity of 1 million kilowatts is said to take about 30 years and cost around ¥50 billion. Typically, some 500,000 tons of waste result from scrapping such a reactor, and 2 percent of the waste is radioactive.

Japan Atomic Power first engaged in decommissioning a commercial reactor in 2001 at its Tokai plant in eastern Japan. It has been conducting decommissioning work at its Tsuruga nuclear power plant in western Japan since 2017.

It is also providing support to Tepco for the decommissioning of reactors at the Fukushima No. 1 plant.

EnergySolutions, founded in 2006, has engaged in scrapping five reactors in the United States.

Japan Atomic Energy and EnergySolutions have had previous business ties, and the Japanese company has sent some employees to the Zion nuclear station in Illinois, where the U.S. partner has been conducting decommissioning work since 2010.

April 22, 2019 Posted by | business and costs, Japan, wastes | Leave a comment

Britain’s Nuclear Free Local Authorities (NFLA) notes that over 70 Welsh councils formally reject hosting nuclear waste dump

NFLA 18th April 2019  The Nuclear Free Local Authorities (NFLA) notes that over 70 Welsh unitary, county, city, town and community councils have passed resolutions formally opposing taking any interest in hosting a deep underground radioactive waste repository.

The figure was noted at a joint meeting in Menai Bridge organised by the NFLA Welsh Forum in conjunction with the groups PAWB, CADNO and CND Cymru. At a presentation provided by the NFLA Secretary, he noted that there had been real anger and frustration raised across Welsh and Northern Irish Councils in particular to the request made by the UK
Government for considering hosting a large deep underground repository to store over 60 years of higher activity radioactive waste, as well as possibly additional waste should new nuclear power stations ever be built.

Even in England, a number of nuclear site Councils have indicated their public opposition to hosting a repository. NFLA have noted some of these issues in its response to RWM regarding its consultation on how any  proposed sites will be evaluated.

http://www.nuclearpolicy.info/news/over-70-welsh-councils-reject-deep-underground-radioactive-waste-repository/

April 22, 2019 Posted by | opposition to nuclear, UK, wastes | Leave a comment

U.S. Department of Energy seeks new certification for its Waste Isolation Pilot Plant

Exchange Monitor 18th April 2019 , The Department of Energy is seeking another five-year certification from
the Environmental Protection Agency for its Waste Isolation Pilot Plant
near Carlsbad, N.M. The WIPP Land Withdrawal Act requires DOE to seek
recertification every five years to ensure the site’s compliance with
federal radioactive waste disposal requirements, according to an executive
summary of the application.

The package provides new data on the
underground repository, its waste inventory, and key changes since the last
update. The site was first certified for permanent disposal of transuranic
waste in 1998. The Environmental Protection Agency can “modify, revise,
or suspend” the certification, EPA supervisory environmental scientist
Thomas Peake said Tuesday during a two-day meeting in Washington, D.C., of
the National Academies’ Nuclear and Radiation Studies Board.

https://www.exchangemonitor.com/epa-recertification-sought-wipp-2024/?printmode=1

April 22, 2019 Posted by | USA, wastes | Leave a comment