France delays EPR2 reactors to 2038

 The 4th meeting of France’s Nuclear Policy Council (CPN – Conseil de
politique nucléaire), chaired by President Emmanuel Macron, decided to
delay the commissioning of EPR2 reactors to 2038 – a postponement of
three years. The CPN, which has been held regularly since 2022, defines the
main orientations of national nuclear policy.

The EPR2 programme, announced
in February 2022, envisages the construction of six upgraded EPR reactors
with an option for eight more. The first three pairs of EPR2 reactors are
planned for the Penly, Gravelines and Bugey NPP sites. Construction is
expected to start in 2027. The cost was originally estimated at €51.7bn
($56.4bn), but this was revised upwards to €67.4bn in 2023, according to
the Court of Auditors. Taking inflation into account, a total budget of
nearly €80bn is now being considered.

 Nuclear Engineering International 21st March 2025, https://www.neimagazine.com/news/france-delays-epr2-reactors-to-2038/

March 27, 2025 - Posted by | business and costs, France

1 Comment »

  1. […] Is in all sorts of trouble with its nuclear programme – France delays EPR2 reactors to 2038. The Flamanville EPR nuclear reactor will not be able to deliver its full power without […]

    Unknown's avatar Pingback by The irrational optimism of the nuclear power lobby - The Australian Independent Media Network | April 12, 2025 | Reply


Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.