Sizewell C Nuclear boss challenged on her definition of failure

Nuclear plant boss Julia Pyke (“‘It’s a tough
gig, developing big infrastructure projects in the UK’”, Work &
Careers, March 17) says “I know [some campaigners] want to believe that
it’s all a terrible failure, but truly, it isn’t.”

As one of those campaigners she is trying unsuccessfully to “win over”, I would point
out that all six “EPR” reactors — the type proposed for Sizewell C on
the Suffolk coast — have been significantly late and over budget.

Taishan 1 in China (five years late, double its budget) was offline for almost two
years early in its operational life. Olkiluoto 3 in Finland and Flamanville
3 in France have suffered teething troubles after being 14 and 12 years
late and costing three and four times their budgets, respectively.

Hinkley Point C’s budget has already doubled and the project is four to six years
late, with another four to six years still to go. Given her role, is it not
important to understand how Pyke defines “failure”?

Alison Downes:  FT 18th March 2025
https://www.ft.com/content/0625dfba-9867-446d-9a42-a952c04a2e1b

March 20, 2025 - Posted by | business and costs, UK