Years after nuclear fiasco soaked ratepayers, leaders look at restarting VC Summer project .

The State, BY SAMMY FRETWELL OCTOBER 15, 2024
Seven years after two power companies abandoned a failing nuclear construction project, a report has concluded that the equipment and existing buildings on the site are in “excellent’’ condition — and it would be worth a look at restarting construction.
A Sep. 16 report by two members of the Governor’s Nuclear Advisory Council said partially completed buildings show “no degradation, corrosion’’ or chipped concrete at the V.C. Summer site northwest of Columbia. The report, discussed Tuesday at the council’s quarterly meeting, said nuclear parts that had already been installed showed some surface rust, but that was not unexpected or a substantial problem.
The V.C. Summer nuclear expansion project marked what many consider the biggest construction failure in South Carolina history. The project to build two reactors to complement an existing one cost $9 billion, soaked ratepayers with higher utility bills and left thousands of employees out of work. Utilities walked away from the project in 2017 because of excessive costs and delays.
But there has been renewed talk of restarting the effort to meet growing energy needs, and the Advisory Council report examined what kind of shape the buildings and equipment were in………………….
The reality of restarting the project is unknown without more study and finding a way to pay for it. Doing so would make for an additional cost, beyond the more than the $9 billion Santee Cooper and SCE&G spent on the V.C. Summer project before it was shelved seven years ago.
Lee and Little’s report recommended a more extensive study of the equipment, buildings and possibility of finishing the project.
Considering the costs to customers — many are still paying for the failed project as part of their monthly energy bills — beginning work on the abandoned reactors could be unpopular with the public, said Tom Clements, a nuclear safety watchdog and critic of the V.C. Summer expansion. As of late last year, ratepayers were still being charged more than 5 percent on their Dominion energy bills for the failed project.
At the same time, SCE&G, which was acquired by Dominion Energy, terminated the federal license to build the plant. Getting a new one for the work could be an extensive process, taking possibly years to complete, he said. “It would take a tremendous amount of effort and financial resources that would make restart of the project highly impractical,’’ Clements said………………………………………………………………
Meanwhile, Santee Cooper is not interested in owning or operating nuclear reactors at V.C. Summer, if they were completed, a spokeswoman said. A Dominion spokesman offered similar comments. The Virginia-headquartered power company “has no plans to restart construction of additional units at V.C. Summer,’’ spokeswoman Rhonda O’Banion said in an email…………………………………………………………
Sen. Tom Davis, R-Beaufort, also has mentioned that the infamous Three Mile Island site in Pennsylvania was under consideration for restart of a nuclear reactor. Davis suggested Lee and Little put together the report discussed Tuesday at the council meeting. Efforts are underway to crank up a unit that shut down in 2019 so that the plant can accommodate a Microsoft data center, Reuters reported. Data centers are tremendous users of energy. The Three-Mile Island site is home to what’s considered the nation’s worst nuclear accident, a meltdown in the 1970s. The reactor to be restarted is not the one in which the 1979 accident occurred.
……………………………………………………………………… Dominion Energy and Santee Cooper jointly own the V.C. Summer property, but Santee and Westinghouse own the equipment. When the V.C. Summer expansion project shut down, SCE&G ratepayers had been charged more than $1 billion for the construction, prompting a public and political outcry. Top utility executives were accused of withholding information about the project’s problems, charged criminally for their actions and sentenced to prison………………………. https://www.thestate.com/news/local/environment/article293978684.html
No comments yet.
-
Archives
- December 2025 (286)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment