Does the Flamanville EPR nuclear reactor have a design fault?

Nuclear: is the Flamanville EPR vessel poorly designed? In its edition of
Wednesday January 19, 2022, Le Canard Enchaîné details the problem on the
Taishan EPR and links it to the Cotentin site. “EDF is struggling to sleep
off its nuclear”. This is the title at the top of page 3 of the Chained
Duck of this Wednesday, January 19, 2022.

Is this a new article following the announcement, a week ago, of a delay and an additional cost of 300
million euros for the construction of the future Flamanville EPR reactor?
No, there is no question of re-welding operations taking longer than
expected.

“The energy company must face a formidable puzzle encountered on
the reactor vessel, where nuclear fission takes place”, immediately
announces the journalist Hervé Liffran. The concern was flushed out
following an incident on the other side of the world, in China. The Taishan
nuclear power plant, with the world’s first operating EPR reactor, was shut
down on July 30, 2021, after damaged fuel rods caused a buildup of
radioactive noble gases in the reactor’s primary circuit .

 La Presse de la Manche 20th Jan 2022

https://actu.fr/normandie/flamanville_50184/nucleaire-la-cuve-de-l-epr-de-flamanville-est-elle-mal-concue_48067014.html

January 22, 2022 - Posted by | France, safety

No comments yet.

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.