A layman’s guide to the ‘Regulated Asset Base’ that will fund Sizewell C nuclear power plant.
Dave Toke’s green energy blog, https://realfeed-intariffs.blogspot.com/2019/07/a-laymans-guide-to-regulated-asset-base.html, 23 July 2019
The Government’s proposed new ‘Regulated Asset Base’ (RAB) means of funding nuclear has just been published, and it is living as far down to its expectations as could be expected. I’ve ploughed through the sometimes (deliberately?) convoluted description of the scheme and translated a few key passages to help you understand it all.
The Government failed to learn from the days when nuclear power were constructed from the 1950s to the 1990s. In those days nuclear power was very expensive, but the Government was able to con the public into believing that it was cheap. They did this by making sure the public could not understand the vaguaries of nuclear power funding and by putting all of the cost overruns that building the power stations involved onto consumer bills without them noticing. Basically, we are reurning to these days when the public was kept in the dark about the cost of building nuclear power plant and the same public will be paying for the cost overruns resulting from the project. The Government made the mistake of giving a contract price for Hinkley C. Although it featherbedded the developers EDF by giving an ultra long premium price contract (35 years) and the promise of Government lending to cover the bulk of the costs, the contract (CfD) allowed some sort of comparison to be made with competitior sources. Solar and wind power’s costs have fallen well below the price given to Hinkley C (£92.50 in 2012 prices). So now the Government, having learned this mistake, has produced the RAB. This will allow the Government, though an appointed ‘Regulator’ to launder electricity consumer’s money to pay for the inevitable cost overruns, whilst the Regulator assures the public that this all represents ‘value for money’. The project that is earmarked for RAB funding is Sizewll C, involving the same reactor type (EPR) as is being constructed at Hinkley C. What some key passages mean:1. ‘Despite the progress at HPC, the challenges facing the global nuclear industry have meant that replicating a CfD model for further new nuclear projects has proved very challenging. Few project developers have a balance sheet that can accommodate the £15-20bn cost of delivering a new nuclear project, and financial investors have been unwilling to invest during the construction phase given the long construction period and risk of cost increases and delays. We are therefore looking to work with the sector to develop an alternative funding model for new nuclear projects that can attract private finance at a cost that represents value for money to consumers and are considering its wider applicability to other firm low carbon technologies’ (page 9) 2. ‘A large-scale new nuclear project bears some similarities with the Thames Tideway Tunnel (TTT) project, in that it is a complex single asset construction project with a significant upfront capital expenditure requirement, long construction period and a long asset life. In developing a potential nuclear RAB model, we have taken the model used for TTT, which was also developed under a RAB, as a starting point, whilst recognising that new nuclear projects are greater in scale and face specific challenges that were not relevant to TTT’ (page 11) 3. ‘A target total construction cost would be set for the project company which would be used as the Baseline for incentivisation and risk sharing. If construction costs increased above the Baseline, a portion of the additional costs would be added to the RAB, such that the impact would be shared between investors and suppliers (and through them, their consumers) (page 14)…(this approach will) ‘provide clarity and certainty to investors, suppliers and consumers, which is particularly important for a large single-asset project with a complex and relatively long construction period’ (page 15)
Translation: The Regulator will produce lots of impenetrable accountancy jargon based on hilariously optimistic projections about construction times and costs which the regulator will swallow whole. When the inevitable happens and costs overrun the investors will still get a reasonable rate of return on their investments and the electricity consumers will pay for most of the cost overruns. 4. ‘Role of the Regulator ‘The EPR technology has now started commercial operations in China’ (pages 8-9) You can read the Government’s RAB consultation and make a response at https://www.gov.uk/government/consultations/regulated-asset-base-rab-model-for-nuclear
|
|
No comments yet.
-
Archives
- January 2026 (183)
- December 2025 (358)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS




Leave a comment