Judge: TVA Deal for Bellefonte Nuclear Plant Stays in Place
Power, 05/17/2019 | Darrell Proctor A federal judge this week ruled the Tennessee Valley Authority (TVA) must continue to honor an agreement to sell the unfinished Bellefonte Nuclear Power Plant to a real estate developer who has said he would complete construction of the long-idled project.
U.S. District Court Judge Liles C. Burke, in a 17-page opinion issued after a hearing this week in Huntsville, Alabama, declined to dismiss a lawsuit brought by developer Franklin Haney, who sued TVA in November 2018 for breach of contract after TVA said it could not complete the sale of the Bellefonte site and its assets to Haney’s Nuclear Development LLC.
Haney in 2016 was the winning bidder in an auction for Bellefonte, agreeing to pay $111 million for the twin-reactor nuclear plant. He sued TVA last year after the federally owned utility said it needed approval from the Nuclear Regulatory Commission (NRC) to authorize the sale.
TVA at the 2016 auction said the winning bidder would have two years to complete the purchase. Haney has argued he was ready to take over Bellefonte last year, though the NRC was still reviewing his application to resume construction at the site. TVA asked the district court to dismiss Haney’s lawsuit, saying federal rules require the sale to be authorized by the NRC, and thus TVA cannot legally sell the plant to Haney.
Nuclear Development filed a license transfer application with the NRC on Nov. 13, 2018, a couple of weeks after the sale’s original closing date, and just more than two weeks before an extended deadline to complete the sale by Nov. 30. TVA told Haney on Nov. 29 that it could not complete the transaction without approval of the license transfer by the NRC. In the sales agreement with Haney, TVA said “federal law at all times govern the validity, interpretation and enforceability” of the sale.
Developer: $30 Million Spent on Project……….
VA has until May 29 to respond to the court ruling. Burke has not ruled out that he could agree with TVA’s arguments if the case goes to trial. TVA, meanwhile, must maintain Bellefonte’s deferred construction permit for a possible transfer to Haney once a decision is reached in the case.
Haney has said his group can finish the nuclear plant, and sell its power for a competitive price. His group has not identified any utility or other customer that would buy Bellefonte’s electricity.
TVA has said that if the deal with Haney falls through, the utility would again put the site Bellefonte up for sale.
https://www.powermag.com/judge-tva-deal-for-bellefonte-nuclear-plant-stays-in-place/
No comments yet.
-
Archives
- December 2025 (249)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment