ICIS 5th April 2019 The commissioning of France’s long-overdue 1.65GW Flamanville 3 nuclear project could face further delays, according to industry stakeholders. A group of experts from French nuclear authority ASN, nuclear safety institute IRSN and utility EDF are set to meet on 9 April to discuss what to do about the welds of the plant’s EPR reactor, IRSN’s director Jean Cristophe-Niel said at a conference in Paris on Thursday.

At the meeting ASN could communicate to EDF whether it would want the welds to be entirely rebuilt or just repaired. If ASN does order the welds to be rebuilt this could significantly delay the commissioning of the plant which was previously set for winter 2019-2020.

The project has already faced delays spanning seven years. ASN will have to communicate its final decision on
Flamanville’s welds in May. The director of energy think-tank WISE-paris Yves Marignac also said at the conference that it was possible Flamanville 3 would be delayed further with no clear timeframe in sight. A number of
traders present at the conference said they were not surprised by this possibility given the project’s track record.

https://www.icis.com/explore/resources/news/2019/04/05/10345828/another-flamanville-3-nuclear-plant-delay-increasingly-likely/