Finland’s super-expensive Olkiluoto nuclear project delayed yet again

World Nuclear News 29th Nov 2018, The start of regular electricity generation at the Olkiluoto 3 (OL3) EPR has been pushed back by a further four months and is now expected to begin
in January 2020, Finnish utility Teollisuuden Voima Oyj (TVO) announced
today.

Last month, the plant’s supplier – the Areva-Siemens consortium –
announced it wanted to update the schedule for completing the unit as
commissioning tests were taking longer than planned. TVO said it has been
informed by the Areva-Siemens consortium that fuel will now be loaded into
the reactor core in June 2019, with grid connection to take place next
October, and the start of regular electricity generation scheduled for
January 2020.

Under the previous schedule provided by the plant supplier in
June this year, fuel loading was expected in January 2019, grid connection
in May and the start of regular electricity production in September.
http://www.world-nuclear-news.org/Articles/New-delay-in-start-up-of-Finnish-EPR

December 1, 2018 - Posted by | business and costs, Finland, politics

1 Comment »

  1. Reblogged this on AGR Daily 60 Second News Bites.

    AGR Daily News's avatar Comment by A Green Road Daily News | December 1, 2018 | Reply


Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.