China again delays building Westinghouse-designed AP1000 nuclear reactor, because of safety worries
![]()
China nuclear reactor delayed again on ‘safety concerns’ https://www.cnbc.com/2018/02/12/china-nuclear-reactor-delayed-again-on-safety-concerns.html
- Fuel loading at the world’s first Westinghouse-designed AP1000 nuclear reactor on China’s east coast has been delayed due to “safety concerns” — the latest in a long line of setbacks for the project.
- Officials with the U.S.-based Westinghouse had expected fuel loading to start last year, and it would have been followed by around six months of performance tests before the reactor could go into full operation in 2018.
Fuel loading at the world’s first Westinghouse-designed AP1000 nuclear reactor on China’s east coast has been delayed due to “safety concerns” — the latest in a long line of setbacks for the project, the China Daily reported on Tuesday.
The third-generation reactor, located in Sanmen in Zhejiang province, was originally expected to make its debut in 2014.
Officials with U.S.-based Westinghouse had expected fuel loading to start last year, and it would have been followed by around six months of performance tests before the reactor could go into full operation in 2018.
Westinghouse was not immediately available for comment when contacted by Reuters on Tuesday.
Westinghouse, owned by Japan’s Toshiba, signed an agreement in 2007 to build four AP1000 reactor units at two sites in China, hoping the projects would serve as a shop window for the firm.
But the company filed for bankruptcy last March, hit by billions of dollars of cost overruns at four nuclear reactors under construction in the United States.
China was originally seen as the lifeline for the global nuclear sector, with the country keen to approve dozens of new reactor projects to ease its dependence on polluting coal-fired electricity.
China is currently targeting total installed nuclear capacity of 58 gigawatts by the end of 2020, up from 35.8 gigawatts by the end of last year. It also said it would aim to have another 30 gigawatts under construction by the end of the decade.
But the pace of planned nuclear construction in the country was scaled back in 2011 in the wake of the Fukushima disaster in Japan.
Delays to the Sanmen and Haiyang AP1000 projects, as well as the French-designed European Pressurised Reactor units at Taishan in Guangdong province, have held back the sector, and no new nuclear project has been approved in China in two years.
China’s nuclear firms are currently building their own homegrown third-generation reactor design known as the Hualong One.
No comments yet.
-
Archives
- December 2025 (249)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment