Japan’s $122 billion nuclear fuel reprocessing plant Rokkasho delayed yet again
Japanese nuclear fuel reprocessing plant delayed yet again Nikkei Asian Reviewhttps://asia.nikkei.com/Politics-Economy/Policy-Politics/Japanese-nuclear-fuel-reprocessing-plant-delayed-yet-again
TOKYO — The Japanese company building a reprocessing plant for spent nuclear fuel pushed back the planned completion date by another three years Friday, further clouding prospects for realizing the nuclear fuel cycle sought by the energy-poor country.
Executive President Kenji Kudo apologized Friday to Aomori Vice Gov. Ikuo Sasaki and said his company would work as one to follow the new timetable at all costs.
Sasaki warned that the series of problems at the plant, stemming from age-related deterioration and insufficient inspections, “could cause residents to lose trust in the facility’s safety.”
The reprocessing plant is meant to extract uranium and plutonium from spent nuclear fuel for reuse in reactors, making it a key link in the envisioned nuclear fuel cycle. Work on the Rokkasho facility began in 1993, but it has sat idle for more than two decades, and many parts are deteriorating with age. Rainwater leaked into a building housing an emergency power supply, and corrosion ate holes in exhaust pipes at a uranium enrichment facility.
The cost of the Rokkasho plant, including operating expenses, has climbed to 13.9 trillion yen ($122 billion), and repair costs may push the total even higher. The necessary funds are provided by the big power companies that are Japan Nuclear Fuel’s main shareholders, feeding growing criticism that the burden falls indirectly on consumers.
The government decided last year to scrap the Monju experimental fast-breeder nuclear reactor, another part of the fuel-cycle plan.
Kudo acknowledged the excessive number of delays and said he would accept the criticism levied at his company. “We want to complete [the facility] at the earliest possible date,” he said.
But it remains unclear whether three additional years will be enough to bring the plant in line with tough new standards imposed after the Fukushi
No comments yet.
-
Archives
- December 2025 (249)
- November 2025 (359)
- October 2025 (377)
- September 2025 (258)
- August 2025 (319)
- July 2025 (230)
- June 2025 (348)
- May 2025 (261)
- April 2025 (305)
- March 2025 (319)
- February 2025 (234)
- January 2025 (250)
-
Categories
- 1
- 1 NUCLEAR ISSUES
- business and costs
- climate change
- culture and arts
- ENERGY
- environment
- health
- history
- indigenous issues
- Legal
- marketing of nuclear
- media
- opposition to nuclear
- PERSONAL STORIES
- politics
- politics international
- Religion and ethics
- safety
- secrets,lies and civil liberties
- spinbuster
- technology
- Uranium
- wastes
- weapons and war
- Women
- 2 WORLD
- ACTION
- AFRICA
- Atrocities
- AUSTRALIA
- Christina's notes
- Christina's themes
- culture and arts
- Events
- Fuk 2022
- Fuk 2023
- Fukushima 2017
- Fukushima 2018
- fukushima 2019
- Fukushima 2020
- Fukushima 2021
- general
- global warming
- Humour (God we need it)
- Nuclear
- RARE EARTHS
- Reference
- resources – print
- Resources -audiovicual
- Weekly Newsletter
- World
- World Nuclear
- YouTube
-
RSS
Entries RSS
Comments RSS


Leave a comment