Rates that customers now are charged for the project already are in the company’s rate base and “will remain so moving forward,’’ SCE&G spokesman Eric Boomhower said in an email Wednesday night.
The company has hit customers with nine power bill increases to finance the project in less than a decade.
SCE&G abandoned the nuclear project this week, but under a 2007 state law, can continue charging customers for the work unless the state Public Service Commission says otherwise.
Collectively, SCE&G and partner Santee Cooper have spent about $9 billion for the reactor project. As an investor owned-utility, SCE&G will seek to recover its share of the amount it has already spent, which was about $5 billion.
Officials with the state Office of Regulatory Staff said they don’t expect the state Public Service Commission to change any rates this year for the SCE&G project in Jenkinsville…… http://www.thestate.com/news/state/article165119542.html