nuclear-news

The News That Matters about the Nuclear Industry Fukushima Chernobyl Mayak Three Mile Island Atomic Testing Radiation Isotope

At the end of the Hinkley nuclear power story – massive radioactive clean-up costs

text-relevantHinkley Point C developers face £7.2bn cleanup bill at end of nuclear plant’s lifeDecommissioning
French and Chinese developers will be the first nuclear operators in the UK that will have to pay to decommission the site,
Guardian, , 30 Sept 16 , The French and Chinese companies that are to build the £18bn Hinkley Point C nuclear power station will have to pay up to £7.2bn to dismantle and clean it up.

Documents published yesterday reveal for the first time how much the developers, EDF and China General Nuclear Power Group (CGN), will have to pay to decommission the plant, beginning in 2083.

The new reactors in Somerset will be unique in British nuclear history, as they are the first for which the operator will have to pay to make good the site afterwards.

“Waste transfer contracts signed today mean that, for the first time in the UK, the full costs of decommissioning and waste management associated with the new power station are set aside during generation and are included in the price of the electricity,” EDF said in a statement.

Decommissioning costs ate up around half the budget for the now-disbanded department of energy and climate change, after the liabilities for cleaning up old nuclear plants were effectively nationalised in 2004 and 2005 when two companies faced financial problems.

The Hinkley Point C decommissioning costs are estimated at £5.9bn to £7.2bn, with the dismantling of the plant expected to begin in 2083. The government, EDF and CGN anticipate the winding up of the new reactors will continue well into the 22nd century. The plant is expected to be fully decommissioned “from 2138” when the final spent fuel is disposed of.

Experts said the cost estimate was likely to be on the low side. “The reality in terms of decommissioning is that it always costs more than people say,” said Dr Paul Dorfman, of the Energy Institute at University College London.

He claimed that the precedent of the government taking ownership of the liabilities of British Nuclear Fuels Limited and British Energy more than a decade ago showed that the government would be forced to shoulder the costs if Hinkley’s developers had a shortfall.

The body charged with dismantling 17 of Britain’s old nuclear power plants puts the cost of cleanup at £117bn over 100 years in its latest annual report, more than twice the cost estimated a decade ago. A large proportion of the cost is due to the complexity of Sellafield……..https://www.theguardian.com/environment/2016/sep/30/hinkley-point-c-developers-face-72bn-cleanup-bill-at-end-of-nuclear-plants-life?CMP=twt_a-environment_b-gdneco&utm_content=buffer99004&utm_medium=social&utm_source=twitter.com&utm_campaign=buffer

October 1, 2016 - Posted by | decommission reactor, UK, wastes

No comments yet.

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.