UK’s £31 billion Trident submarines programme on the skids

submarine-missileflag-UKTrident plans ‘in doubt’, says government watchdog, The Ferret,  Rob Edwards on August 8, 2016 The UK’s £31 billion programme to replace Trident submarines in on the skids, according to a high-level government spending watchdog.

A report by the Infrastructure and Projects Authority (IPA) to the Treasury and Cabinet Office has warned that the plan to build four new nuclear weapons submarines for the Clyde is “in doubt”.

This is despite the overwhelming vote in the House of Commons last month in favour of replacing Trident. The plan was opposed by every Scottish MP, except for the lone Tory, David Mundell.

The poor assessment of the Trident programme’s prospects was buried in a report about 143 projects published online by the IPA several days before the vote at Westminster. It gave the submarine successor programme its second worst rating of “amber/red”.

This means that the project is judged to be running into serious difficulties because of cost overruns, management problems and technical issues. “Successful delivery of the project is in doubt, with major risks or issues apparent in a number of key areas,” said the IPA.

“Urgent action is needed to address these problems and/or assess whether resolution is feasible.”

According to critics, costs have already risen by between £15 and £20 billion. The planned date for bringing the submarines into service has been delayed from 2024 to the “early 2030s”……….https://theferret.scot/trident-doubt-government-watchdog/

August 12, 2016 - Posted by | politics, UK, weapons and war